Bridge Deck Repairs On US Route 3 in Meredith
Lane Restrictions and Shifts Needed for Project Work

The New Hampshire Department of Transportation (NHDOT) announces construction work is scheduled to begin on Monday, April 9, 2018 on the US Route 3 bridge over Mill Stream in Meredith.

This bridge deck repair project will require temporary lane shifts and restrictions in order to be completed. Traffic on US Route 3 near the bridge will be restricted to one lane northbound and one lane southbound. The turning lanes on NH 25 at the traffic signals, left hand turns on to US 3 be reduced to one left hand turn lane only.

Normal traffic patterns will be resumed by June 9, 2018. The project will then be suspended for the summer months, resuming on September 4, 2018.

This project includes roadway and intersection improvements on US Route 3 and NH Route 25 from NH Route 104 to the Meredith/Center Harbor town line. It include traffic signals, drainage, guardrail and sidewalk work, as well as a new signalized crosswalk on US Route 3.

R.M. Piper, of Plymouth, New Hampshire is the contractor for the $2.58 million project, which has a final completion date of November 2, 2018.