Smaller text size Reset text size Larger text size
skip navigation
Air Rail Highway Bike/Ped Public Transit

NEWS RELEASE

For Immediate Release
December 14, 2016
Contacts:
Andrew Hall, Bridge Maintenance Bureau, 603-271-3667
Bill Boynton, Public Information Office, 603-271-6495
Bridge Repairs on NH Route 103B in Sunapee
Date Changed for the Beginning of Work

The New Hampshire Department of Transportation (NHDOT) announces the start date of the scheduled work at the NH Route 103B Bridge over Sucker Brook in Sunapee has been changed to January 3, 2017.

The bridge deck replacement project is expected to be completed by April 14, 2017. The start date was revised to allow additional fabrication to accommodate current site conditions.

During the project, one-way alternating traffic with be maintained with a 14-foot lane width, and will be controlled by stop and yield signs.






New Hampshire Department of Transportation
PO Box 483 | 7 Hazen Drive | Concord, NH | 03302-0483
Tel: 603.271-3734 | Fax: 603.271.3914

copyright 2015. State of New Hampshire