Night Time Lane Closures on I-293 at Exit 4 in Manchester
Pavement Striping Operations from 10/21 through 10/24/15

The New Hampshire Department of Transportation (NHDOT) announces temporary night time lane closures are planned on I-293 northbound and southbound in Manchester in the vicinity of Exit 4.

Weather permitting, the I-293 northbound and southbound lane closures are scheduled to take place from Wednesday, October 21 to Saturday, October 24 from 7:00 pm until 6:00 am each night. Interstate 293 northbound and southbound will have one open lane at all times.

The temporary night time lane closures are to allow for pavement striping operations. Electronic message boards and traffic control devices will be used to alert and assist motorists during the lane closures.

This work is part of the I-293 widening and bridge replacement project in the vicinity of Exit 4. The project includes the replacement of four "Red Listed" bridges and the rehabilitation of one "Red Listed" bridge at the I-293 Exit 4 Interchange.

The road work includes: construction of a third southbound lane, beginning approximately 150 feet north of the existing northbound on-ramp and continuing approximately 0.6 mile south; Exit 4 ramps reconstruction and pavement rehabilitation; sound wall construction; drainage improvements; water line reconstruction; installation of concrete median barrier; and guardrail improvements.

Severino Trucking Inc., of Candia, New Hampshire is the general contractor for the $26.2 million project, which has a completion date of November 18, 2016.