Night Work To Begin At Exit 5 In Londonderry
Some Interstate 93 Traffic Delays

The New Hampshire Department of Transportation announces night work associated with the construction of four new Exit 5 Interstate 93 bridges in Londonderry. Paving and line striping operations will take place on the nights of Sunday, April 27, 2014 through Tuesday, April 29, 2014, weather permitting.

This work will require a lane closure and State Police rolling road blocks on Interstate 93 southbound and northbound. Lane closures will take place during the non-commuter hours, from approximately 9:00 pm to 6:00 am. Minor traffic delays can be expected.

This work is part of the construction of four new I-93 Exit 5 bridges, NH Route 28 reconstruction, and I-93 reconstruction in the Exit 5 area. Severino Trucking Co., Inc. of Candia, New Hampshire is the general contractor for the $37 million project, which is scheduled for completion in June 2014.