THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: LITTLETON-DALTON 16355 COUNTIES AND CODES: COOS 007 GRAFTON 009 DATE BIDS OPEN: JUNE 16, 2011 SCOPE OF WORK: ROADWAY RESTORATION LOCATION: ROUTE 135 IN THE TOWNS OF LITTLETON AND DALTON COMPLETION DATE: AUGUST 26, 2011 A PIKE INDUSTRIES, INC. 3 EASTGATE PARK RD., BELMONT, NH 03220 $ 467,500.00 B NORTHEAST EARTH MECHANICS, INC. 159 BARNSTEAD ROAD, PITTSFIELD, NH 03263 $ 538,175.00 C MORRILL CONSTRUCTION, INC. 190 HORSE MEADOW RD., NORTH HAVERHILL, NH 03774 $ 571,817.50 D WINTERSET, INC. PO BOX 968, LYNDONVILLE, VT 05851 $ 588,939.00 E R. M. PIPER, INC. PO BOX 490, PLYMOUTH, NH 03264 $ 671,425.00 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 201.21 REMOVING SMALL TREES EA 10. 150.00 1,500.00 220.00 2,200.00 150.00 1,500.00 201.882 INVASIVE SPECIES CONTROL TYPE II SY 100. 3.00 300.00 20.00 2,000.00 10.00 1,000.00 203.1 COMMON EXCAVATION CY 3,000. 8.00 24,000.00 7.00 21,000.00 9.00 27,000.00 206.1 COMMON STRUCTURE EXCAVATION CY 25. 9.00 225.00 14.00 350.00 15.00 375.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 15. 15.00 225.00 34.00 510.00 30.00 450.00 206.2 ROCK STRUCTURE EXCAVATION CY 25. 50.00 1,250.00 150.00 3,750.00 200.00 5,000.00 209.1 GRANULAR BACKFILL CY 15. 40.00 600.00 22.00 330.00 40.00 600.00 304.301 CRUSHED GRAVEL CY 750. 38.00 28,500.00 26.00 19,500.00 30.00 22,500.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING TON 130. 38.00 4,940.00 26.00 3,380.00 35.00 4,550.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 15. 38.00 570.00 33.00 495.00 35.00 525.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 450. 195.00 87,750.00 200.00 90,000.00 184.00 82,800.00 570.401 MORTAR RUBBLE MASONRY CY 50. 400.00 20,000.00 430.00 21,500.00 450.00 22,500.00 585.2 STONE FILL, CLASS B CY 55. 35.00 1,925.00 25.00 1,375.00 40.00 2,200.00 585.3 STONE FILL, CLASS C CY 1,950. 38.00 74,100.00 29.00 56,550.00 30.00 58,500.00 593.411 GEOTEXTILE; PERM CONTROL CL.1, NON-WOVEN SY 7,500. 1.00 7,500.00 1.50 11,250.00 2.50 18,750.00 603.00215 15" R.C. PIPE, 2000D LF 200. 37.00 7,400.00 50.00 10,000.00 65.00 13,000.00 603.00218 18" R.C. PIPE, 2000D LF 585. 40.00 23,400.00 58.00 33,930.00 68.00 39,780.00 603.00224 24" R.C. PIPE, 2000D LF 50. 45.00 2,250.00 63.00 3,150.00 75.00 3,750.00 16355 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 603.00236 36" R.C. PIPE, 2000D LF 150. 65.00 9,750.00 83.00 12,450.00 85.00 12,750.00 603.00242 42" R.C. PIPE, 2000D LF 50. 71.00 3,550.00 99.00 4,950.00 125.00 6,250.00 603.30118 18" R.C. END SECTIONS EA 2. 535.00 1,070.00 450.00 900.00 1,000.00 2,000.00 603.30124 24" R.C. END SECTIONS EA 2. 650.00 1,300.00 540.00 1,080.00 1,250.00 2,500.00 603.30136 36" R.C. END SECTIONS EA 4. 1,000.00 4,000.00 900.00 3,600.00 1,500.00 6,000.00 603.30142 42" R.C. END SECTIONS EA 2. 1,350.00 2,700.00 1,200.00 2,400.00 2,000.00 4,000.00 603.50015 15" PIPE FOR DRIVES & MINOR APPROACHES LF 50. 26.00 1,300.00 33.00 1,650.00 55.00 2,750.00 604.19 SPECIAL CATCH BASINS U 4. 1,950.00 7,800.00 3,350.00 13,400.00 2,850.00 11,400.00 605.82252 24" AGGREGATE UNDERDRAIN, TYPE 2 WITH 12" PREF. POLYETHYLENE PIPE LF 2,500. 25.00 62,500.00 42.00 105,000.00 35.00 87,500.00 618.7 FLAGGERS HR 1,000. 21.00 21,000.00 24.00 24,000.00 25.00 25,000.00 619.1 MAINTENANCE OF TRAFFIC U 1. 2,000.00 2,000.00 2,200.00 2,200.00 10,000.00 10,000.00 628.2 SAWED BITUMINOUS PAVEMENT LF 4,850. 1.00 4,850.00 2.00 9,700.00 3.00 14,550.00 645.3 EROSION STONE TON 100. 19.00 1,900.00 28.00 2,800.00 30.00 3,000.00 645.41 TEMPORARY SLOPE STABILIZATION TYPE A SY 600. 1.25 750.00 2.00 1,200.00 2.50 1,500.00 645.531 SILT FENCE LF 1,750. 2.00 3,500.00 2.50 4,375.00 3.25 5,687.50 646.3 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS A .6 2,450.00 1,470.00 4,500.00 2,700.00 2,500.00 1,500.00 647.1 HUMUS CY 300. 23.00 6,900.00 18.00 5,400.00 35.00 10,500.00 670.066 MAILBOX SUPPORT ASSEMBLIES EA 1. 125.00 125.00 130.00 130.00 150.00 150.00 692. MOBILIZATION U 1. 30,000.00 30,000.00 44,750.00 44,750.00 45,000.00 45,000.00 697.11 INVASIVE SPECIES CONTROL AND MANAGEMENT PLAN U 1. 600.00 600.00 220.00 220.00 1,000.00 1,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 1008.11 ALTERATIONS AND ADDITIONS AS NEEDED- UNANTICIPATED WORK $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 1010.15 FUEL ADJUSTMENT $ 1. 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 $467,500.00 $538,175.00 $571,817.50 THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: LITTLETON-DALTON 16355 COUNTIES AND CODES: COOS 007 GRAFTON 009 DATE BIDS OPEN: JUNE 16, 2011 SCOPE OF WORK: ROADWAY RESTORATION LOCATION: ROUTE 135 IN THE TOWNS OF LITTLETON AND DALTON COMPLETION DATE: AUGUST 26, 2011 A PIKE INDUSTRIES, INC. 3 EASTGATE PARK RD., BELMONT, NH 03220 $ 467,500.00 B NORTHEAST EARTH MECHANICS, INC. 159 BARNSTEAD ROAD, PITTSFIELD, NH 03263 $ 538,175.00 C MORRILL CONSTRUCTION, INC. 190 HORSE MEADOW RD., NORTH HAVERHILL, NH 03774 $ 571,817.50 D WINTERSET, INC. PO BOX 968, LYNDONVILLE, VT 05851 $ 588,939.00 E R. M. PIPER, INC. PO BOX 490, PLYMOUTH, NH 03264 $ 671,425.00 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 201.21 REMOVING SMALL TREES EA 10. 284.00 2,840.00 300.00 3,000.00 201.882 INVASIVE SPECIES CONTROL TYPE II SY 100. 8.00 800.00 20.00 2,000.00 203.1 COMMON EXCAVATION CY 3,000. 9.00 27,000.00 9.00 27,000.00 206.1 COMMON STRUCTURE EXCAVATION CY 25. 39.00 975.00 15.00 375.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 15. 40.00 600.00 25.00 375.00 206.2 ROCK STRUCTURE EXCAVATION CY 25. 60.00 1,500.00 80.00 2,000.00 209.1 GRANULAR BACKFILL CY 15. 50.00 750.00 30.00 450.00 304.301 CRUSHED GRAVEL CY 750. 39.00 29,250.00 36.00 27,000.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING TON 130. 20.00 2,600.00 40.00 5,200.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 15. 40.00 600.00 40.00 600.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 450. 212.00 95,400.00 195.00 87,750.00 570.401 MORTAR RUBBLE MASONRY CY 50. 435.00 21,750.00 425.00 21,250.00 585.2 STONE FILL, CLASS B CY 55. 37.00 2,035.00 45.00 2,475.00 585.3 STONE FILL, CLASS C CY 1,950. 41.00 79,950.00 35.00 68,250.00 593.411 GEOTEXTILE; PERM CONTROL CL.1, NON-WOVEN SY 7,500. 2.50 18,750.00 2.50 18,750.00 603.00215 15" R.C. PIPE, 2000D LF 200. 49.00 9,800.00 70.00 14,000.00 603.00218 18" R.C. PIPE, 2000D LF 585. 55.00 32,175.00 85.00 49,725.00 603.00224 24" R.C. PIPE, 2000D LF 50. 95.00 4,750.00 100.00 5,000.00 16355 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 603.00236 36" R.C. PIPE, 2000D LF 150. 105.00 15,750.00 110.00 16,500.00 603.00242 42" R.C. PIPE, 2000D LF 50. 117.00 5,850.00 150.00 7,500.00 603.30118 18" R.C. END SECTIONS EA 2. 620.00 1,240.00 725.00 1,450.00 603.30124 24" R.C. END SECTIONS EA 2. 710.00 1,420.00 825.00 1,650.00 603.30136 36" R.C. END SECTIONS EA 4. 1,111.00 4,444.00 1,200.00 4,800.00 603.30142 42" R.C. END SECTIONS EA 2. 1,400.00 2,800.00 1,750.00 3,500.00 603.50015 15" PIPE FOR DRIVES & MINOR APPROACHES LF 50. 31.00 1,550.00 50.00 2,500.00 604.19 SPECIAL CATCH BASINS U 4. 2,600.00 10,400.00 3,950.00 15,800.00 605.82252 24" AGGREGATE UNDERDRAIN, TYPE 2 WITH 12" PREF. POLYETHYLENE PIPE LF 2,500. 27.00 67,500.00 58.00 145,000.00 618.7 FLAGGERS HR 1,000. 31.00 31,000.00 21.00 21,000.00 619.1 MAINTENANCE OF TRAFFIC U 1. 19,000.00 19,000.00 27,500.00 27,500.00 628.2 SAWED BITUMINOUS PAVEMENT LF 4,850. 2.00 9,700.00 1.50 7,275.00 645.3 EROSION STONE TON 100. 35.00 3,500.00 40.00 4,000.00 645.41 TEMPORARY SLOPE STABILIZATION TYPE A SY 600. 2.50 1,500.00 3.00 1,800.00 645.531 SILT FENCE LF 1,750. 4.00 7,000.00 3.00 5,250.00 646.3 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS A .6 2,300.00 1,380.00 2,150.00 1,290.00 647.1 HUMUS CY 300. 27.00 8,100.00 12.50 3,750.00 670.066 MAILBOX SUPPORT ASSEMBLIES EA 1. 180.00 180.00 160.00 160.00 692. MOBILIZATION U 1. 49,000.00 49,000.00 50,000.00 50,000.00 697.11 INVASIVE SPECIES CONTROL AND MANAGEMENT PLAN U 1. 2,100.00 2,100.00 1,500.00 1,500.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 2,000.00 2,000.00 2,000.00 2,000.00 1008.11 ALTERATIONS AND ADDITIONS AS NEEDED- UNANTICIPATED WORK $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 1010.15 FUEL ADJUSTMENT $ 1. 2,000.00 2,000.00 2,000.00 2,000.00 $588,939.00 $671,425.00 STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION A-PS&E COMPARISION PROJECT: LITTLETON-DALTON 16355 COUNTIES AND CODES: COOS 007 GRAFTON 009 DATE BIDS OPEN: JUNE 16, 2011 SCOPE OF WORK: ROADWAY RESTORATION LOCATION: ROUTE 135 IN THE TOWNS OF LITTLETON AND DALTON COMPLETION DATE: AUGUST 26, 2011 A PIKE INDUSTRIES, INC. 3 EASTGATE PARK RD., BELMONT, NH 03220 $ 467,500.00 B NORTHEAST EARTH MECHANICS, INC. 159 BARNSTEAD ROAD, PITTSFIELD, NH 03263 $ 538,175.00 C MORRILL CONSTRUCTION, INC. 190 HORSE MEADOW RD., NORTH HAVERHILL, NH 03774 $ 571,817.50 D WINTERSET, INC. PO BOX 968, LYNDONVILLE, VT 05851 $ 588,939.00 E R. M. PIPER, INC. PO BOX 490, PLYMOUTH, NH 03264 $ 671,425.00 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 201.21 REMOVING SMALL TREES EA 10. 150.00 1,500.00 200.00 2,000.00 -500.00 201.882 INVASIVE SPECIES CONTROL TYPE II SY 100. 3.00 300.00 10.00 1,000.00 -700.00 203.1 COMMON EXCAVATION CY 3,000. 8.00 24,000.00 7.50 22,500.00 1,500.00 206.1 COMMON STRUCTURE EXCAVATION CY 25. 9.00 225.00 45.00 1,125.00 -900.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 15. 15.00 225.00 40.00 600.00 -375.00 206.2 ROCK STRUCTURE EXCAVATION CY 25. 50.00 1,250.00 60.00 1,500.00 -250.00 209.1 GRANULAR BACKFILL CY 15. 40.00 600.00 35.00 525.00 75.00 304.301 CRUSHED GRAVEL CY 750. 38.00 28,500.00 31.00 23,250.00 5,250.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING TON 130. 38.00 4,940.00 25.00 3,250.00 1,690.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 15. 38.00 570.00 40.00 600.00 -30.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 450. 195.00 87,750.00 130.00 58,500.00 29,250.00 570.401 MORTAR RUBBLE MASONRY CY 50. 400.00 20,000.00 600.00 30,000.00 -10,000.00 585.2 STONE FILL, CLASS B CY 55. 35.00 1,925.00 38.00 2,090.00 -165.00 585.3 STONE FILL, CLASS C CY 1,950. 38.00 74,100.00 25.00 48,750.00 25,350.00 593.411 GEOTEXTILE; PERM CONTROL CL.1, NON-WOVEN SY 7,500. 1.00 7,500.00 3.00 22,500.00 -15,000.00 603.00215 15" R.C. PIPE, 2000D LF 200. 37.00 7,400.00 40.00 8,000.00 -600.00 603.00218 18" R.C. PIPE, 2000D LF 585. 40.00 23,400.00 45.00 26,325.00 -2,925.00 16355 PAGE 2 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 603.00224 24" R.C. PIPE, 2000D LF 50. 45.00 2,250.00 45.00 2,250.00 603.00236 36" R.C. PIPE, 2000D LF 150. 65.00 9,750.00 80.00 12,000.00 -2,250.00 603.00242 42" R.C. PIPE, 2000D LF 50. 71.00 3,550.00 100.00 5,000.00 -1,450.00 603.30118 18" R.C. END SECTIONS EA 2. 535.00 1,070.00 700.00 1,400.00 -330.00 603.30124 24" R.C. END SECTIONS EA 2. 650.00 1,300.00 750.00 1,500.00 -200.00 603.30136 36" R.C. END SECTIONS EA 4. 1,000.00 4,000.00 1,200.00 4,800.00 -800.00 603.30142 42" R.C. END SECTIONS EA 2. 1,350.00 2,700.00 1,500.00 3,000.00 -300.00 603.50015 15" PIPE FOR DRIVES & MINOR APPROACHES LF 50. 26.00 1,300.00 25.00 1,250.00 50.00 604.19 SPECIAL CATCH BASINS U 4. 1,950.00 7,800.00 2,750.00 11,000.00 -3,200.00 605.82252 24" AGGREGATE UNDERDRAIN, TYPE 2 WITH 12" PREF. POLYETHYLENE PIPE LF 2,500. 25.00 62,500.00 25.00 62,500.00 618.7 FLAGGERS HR 1,000. 21.00 21,000.00 22.00 22,000.00 -1,000.00 619.1 MAINTENANCE OF TRAFFIC U 1. 2,000.00 2,000.00 10,000.00 10,000.00 -8,000.00 628.2 SAWED BITUMINOUS PAVEMENT LF 4,850. 1.00 4,850.00 1.30 6,305.00 -1,455.00 645.3 EROSION STONE TON 100. 19.00 1,900.00 22.00 2,200.00 -300.00 645.41 TEMPORARY SLOPE STABILIZATION TYPE A SY 600. 1.25 750.00 1.50 900.00 -150.00 645.531 SILT FENCE LF 1,750. 2.00 3,500.00 3.50 6,125.00 -2,625.00 646.3 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS A .6 2,450.00 1,470.00 1,800.00 1,080.00 390.00 647.1 HUMUS CY 300. 23.00 6,900.00 30.00 9,000.00 -2,100.00 670.066 MAILBOX SUPPORT ASSEMBLIES EA 1. 125.00 125.00 200.00 200.00 -75.00 692. MOBILIZATION U 1. 30,000.00 30,000.00 20,000.00 20,000.00 10,000.00 697.11 INVASIVE SPECIES CONTROL AND MANAGEMENT PLAN U 1. 600.00 600.00 2,000.00 2,000.00 -1,400.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 2,000.00 2,000.00 2,000.00 2,000.00 1008.11 ALTERATIONS AND ADDITIONS AS NEEDED- UNANTICIPATED WORK $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 1010.15 FUEL ADJUSTMENT $ 1. 2,000.00 2,000.00 2,000.00 2,000.00 $467,500.00 $451,025.00 16,475.00