THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: RESURFACING DISTRICT IV 16164 AND HARRISVILLE 16224 COUNTIES AND CODES: CHESHIRE 005 HILLSBOROUGH 011 DATE BIDS OPEN: MARCH 1, 2011 SCOPE OF WORK: ROADWAY RESURFACING LOCATION: SEE THE PROSECUTION OF WORK COMPLETION DATE: AUGUST 26, 2011 A PIKE INDUSTRIES, INC. 3 EASTGATE PARK RD., BELMONT, NH 03220 $ 1,860,000.00 B BROX INDUSTRIES, INC. 1471 METHUEN STREET, DRACUT, MA 01826 $ 1,912,695.00 C CONTINENTAL PAVING, INC. 1 CONTINENTAL DRIVE, LONDONDERY, NH 03053 $ 1,999,996.25 D FRANK W. WHITCOMB CONSTRUCTION CORPORATION 187 WHITCOMB ROAD, PO BOX 1000, WALPOLE, NH 03608 $ 2,400,004.75 E THE LANE CONSTRUCTION, CORP. 90 FIELDSTONE COURT, CHESHIRE, CT 06410 $ 2,599,330.00 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 214. FINE GRADING U 1. 40,000.00 40,000.00 25,000.00 25,000.00 15,000.00 15,000.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING TON 4,500. 10.00 45,000.00 16.00 72,000.00 12.00 54,000.00 306.112 RECLAIMED STABILIZED BASE PROCESSED IN PLACE, 12 IN DEEP (F) SY 52,825. .72 38,034.00 .76 40,147.00 1.25 66,031.25 306.36 STONE FOR RECLAIMED STABILIZED BASE TON 6,900. 10.00 69,000.00 5.00 34,500.00 14.00 96,600.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD TON 11,850. 58.00 687,300.00 62.00 734,700.00 61.00 722,850.00 403.1109 HOT BITUMINOUS PAVEMENT, MACHINE METHOD, HIGH STRENGTH TON 1,050. 75.00 78,750.00 78.00 81,900.00 70.00 73,500.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 50. 105.00 5,250.00 110.00 5,500.00 115.00 5,750.00 403.21 WARM BITUMINOUS PAVEMENT, MACHINE METHOD TON 4,750. 58.00 275,500.00 62.00 294,500.00 65.00 308,750.00 411.3 PLANT MIX SURFACE TREAT- MENT (AC), PAVER SHIM TON 5,850. 58.00 339,300.00 63.00 368,550.00 62.90 367,965.00 417. COLD PLANING BITUMINOUS SURFACES SY 98,300. .95 93,385.00 1.30 127,790.00 1.50 147,450.00 604.51 RECONSTRUCTING/ADJUSTING SEWER MANHOLES LF 3. 266.00 798.00 300.00 900.00 350.00 1,050.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 16164 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 618.7 FLAGGERS HR 2,050. 18.50 37,925.00 14.00 28,700.00 21.00 43,050.00 619.253 PORTABLE CHANGEABLE MESSAGE SIGN (UNIT WEEK) UWK 6. 168.00 1,008.00 200.00 1,200.00 250.00 1,500.00 692. MOBILIZATION U 1. 77,250.00 77,250.00 25,808.00 25,808.00 25,000.00 25,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1008.11 ALTERATIONS AND ADDITIONS AS NEEDED- UNANTICIPATED WORK $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1010.15 FUEL ADJUSTMENT $ 1. 21,500.00 21,500.00 21,500.00 21,500.00 21,500.00 21,500.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00 $1,860,000.00 $1,912,695.00 $1,999,996.25 THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: RESURFACING DISTRICT IV 16164 AND HARRISVILLE 16224 COUNTIES AND CODES: CHESHIRE 005 HILLSBOROUGH 011 DATE BIDS OPEN: MARCH 1, 2011 SCOPE OF WORK: ROADWAY RESURFACING LOCATION: SEE THE PROSECUTION OF WORK COMPLETION DATE: AUGUST 26, 2011 A PIKE INDUSTRIES, INC. 3 EASTGATE PARK RD., BELMONT, NH 03220 $ 1,860,000.00 B BROX INDUSTRIES, INC. 1471 METHUEN STREET, DRACUT, MA 01826 $ 1,912,695.00 C CONTINENTAL PAVING, INC. 1 CONTINENTAL DRIVE, LONDONDERY, NH 03053 $ 1,999,996.25 D FRANK W. WHITCOMB CONSTRUCTION CORPORATION 187 WHITCOMB ROAD, PO BOX 1000, WALPOLE, NH 03608 $ 2,400,004.75 E THE LANE CONSTRUCTION, CORP. 90 FIELDSTONE COURT, CHESHIRE, CT 06410 $ 2,599,330.00 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 214. FINE GRADING U 1. 43,000.00 43,000.00 15,000.00 15,000.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING TON 4,500. 24.00 108,000.00 25.00 112,500.00 306.112 RECLAIMED STABILIZED BASE PROCESSED IN PLACE, 12 IN DEEP (F) SY 52,825. .75 39,618.75 2.00 105,650.00 306.36 STONE FOR RECLAIMED STABILIZED BASE TON 6,900. 19.00 131,100.00 10.00 69,000.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD TON 11,850. 72.00 853,200.00 76.50 906,525.00 403.1109 HOT BITUMINOUS PAVEMENT, MACHINE METHOD, HIGH STRENGTH TON 1,050. 95.00 99,750.00 105.00 110,250.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 50. 160.00 8,000.00 129.00 6,450.00 403.21 WARM BITUMINOUS PAVEMENT, MACHINE METHOD TON 4,750. 77.50 368,125.00 78.50 372,875.00 411.3 PLANT MIX SURFACE TREAT- MENT (AC), PAVER SHIM TON 5,850. 78.00 456,300.00 92.50 541,125.00 417. COLD PLANING BITUMINOUS SURFACES SY 98,300. 1.48 145,484.00 1.50 147,450.00 604.51 RECONSTRUCTING/ADJUSTING SEWER MANHOLES LF 3. 200.00 600.00 500.00 1,500.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 16164 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 618.7 FLAGGERS HR 2,050. 18.94 38,827.00 29.30 60,065.00 619.253 PORTABLE CHANGEABLE MESSAGE SIGN (UNIT WEEK) UWK 6. 250.00 1,500.00 740.00 4,440.00 692. MOBILIZATION U 1. 35,000.00 35,000.00 75,000.00 75,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 1008.11 ALTERATIONS AND ADDITIONS AS NEEDED- UNANTICIPATED WORK $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 1010.15 FUEL ADJUSTMENT $ 1. 21,500.00 21,500.00 21,500.00 21,500.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 35,000.00 35,000.00 35,000.00 35,000.00 $2,400,004.75 $2,599,330.00 STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION A-PS&E COMPARISION PROJECT: RESURFACING DISTRICT IV 16164 AND HARRISVILLE 16224 COUNTIES AND CODES: CHESHIRE 005 HILLSBOROUGH 011 DATE BIDS OPEN: MARCH 1, 2011 SCOPE OF WORK: ROADWAY RESURFACING LOCATION: SEE THE PROSECUTION OF WORK COMPLETION DATE: AUGUST 26, 2011 A PIKE INDUSTRIES, INC. 3 EASTGATE PARK RD., BELMONT, NH 03220 $ 1,860,000.00 B BROX INDUSTRIES, INC. 1471 METHUEN STREET, DRACUT, MA 01826 $ 1,912,695.00 C CONTINENTAL PAVING, INC. 1 CONTINENTAL DRIVE, LONDONDERY, NH 03053 $ 1,999,996.25 D FRANK W. WHITCOMB CONSTRUCTION CORPORATION 187 WHITCOMB ROAD, PO BOX 1000, WALPOLE, NH 03608 $ 2,400,004.75 E THE LANE CONSTRUCTION, CORP. 90 FIELDSTONE COURT, CHESHIRE, CT 06410 $ 2,599,330.00 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 214. FINE GRADING U 1. 40,000.00 40,000.00 15,000.00 15,000.00 25,000.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING TON 4,500. 10.00 45,000.00 16.50 74,250.00 -29,250.00 306.112 RECLAIMED STABILIZED BASE PROCESSED IN PLACE, 12 IN DEEP (F) SY 52,825. .72 38,034.00 1.00 52,825.00 -14,791.00 306.36 STONE FOR RECLAIMED STABILIZED BASE TON 6,900. 10.00 69,000.00 16.00 110,400.00 -41,400.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD TON 11,850. 58.00 687,300.00 68.00 805,800.00 -118,500.00 403.1109 HOT BITUMINOUS PAVEMENT, MACHINE METHOD, HIGH STRENGTH TON 1,050. 75.00 78,750.00 80.00 84,000.00 -5,250.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 50. 105.00 5,250.00 100.00 5,000.00 250.00 403.21 WARM BITUMINOUS PAVEMENT, MACHINE METHOD TON 4,750. 58.00 275,500.00 69.00 327,750.00 -52,250.00 411.3 PLANT MIX SURFACE TREAT- MENT (AC), PAVER SHIM TON 5,850. 58.00 339,300.00 72.50 424,125.00 -84,825.00 417. COLD PLANING BITUMINOUS SURFACES SY 98,300. .95 93,385.00 1.50 147,450.00 -54,065.00 604.51 RECONSTRUCTING/ADJUSTING SEWER MANHOLES LF 3. 266.00 798.00 250.00 750.00 48.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 16164 PAGE 2 A-BIDDER PS&E ----------------------- ----------------------- A-PS&E ITEM NO. ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT DIFFERENCE 618.7 FLAGGERS HR 2,050. 18.50 37,925.00 22.00 45,100.00 -7,175.00 619.253 PORTABLE CHANGEABLE MESSAGE SIGN (UNIT WEEK) UWK 6. 168.00 1,008.00 300.00 1,800.00 -792.00 692. MOBILIZATION U 1. 77,250.00 77,250.00 60,000.00 60,000.00 17,250.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 1008.11 ALTERATIONS AND ADDITIONS AS NEEDED- UNANTICIPATED WORK $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 1010.15 FUEL ADJUSTMENT $ 1. 21,500.00 21,500.00 21,500.00 21,500.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 35,000.00 35,000.00 35,000.00 35,000.00 $1,860,000.00 $2,225,750.00 -365,750.00