THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: NEW LONDON X-A000(846), 15652 COUNTIES AND CODES: MERRIMACK 013 DATE BIDS OPEN: MARCH 17, 2009 SCOPE OF WORK: ROADWAY AND BRIDGE RECONSTRUCTION LOCATION: I-89 NORTHBOUND AND SOUTHBOUND IN THE TOWNS OF NEW LONDON, SUNAPEE, SPRINGFIELD AND GRANTHAM COMPLETION DATE: AUGUST 27, 2010 A PIKE INDUSTRIES, INC. 3 EASTGATE PARK ROAD, BELMONT, NH 03220 $ 6,224,047.25 B CONTINENTAL PAVING INC. ONE CONTINENTAL DR., LONDONDERRY, NH 03053 $ 6,336,741.75 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 202.7 REMOVAL OF GUARDRAIL (F) LF 42,625. 1.20 51,150.00 1.65 70,331.25 203.5554 GUARDRAIL 50' EAGRT PLATFORM U 5. 1,010.00 5,050.00 1,000.00 5,000.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING TON 9,000. 14.00 126,000.00 22.00 198,000.00 304.355 CRUSHED GRAVEL, 55% WEAR (F) CY 35. 37.00 1,295.00 30.00 1,050.00 403.11001 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (QC/QA TIER 1) TON 24,580. 75.00 1,843,500.00 78.00 1,917,240.00 403.11002 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (QC/QA TIER 2) TON 3,100. 80.00 248,000.00 78.00 241,800.00 403.1109 HOT BITUMINOUS PAVEMENT, MACHINE METHOD, HIGH STRENGTH TON 900. 98.00 88,200.00 90.00 81,000.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 147. 150.00 22,050.00 125.00 18,375.00 403.6 PAVEMENT JOINT ADHESIVE LF 121,700. .26 31,642.00 .30 36,510.00 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 219. 275.00 60,225.00 125.00 27,375.00 411.1 HOT BITUMINOUS CONCRETE LEVELING COURSE TON 3,000. 78.00 234,000.00 80.00 240,000.00 417. COLD PLANING BITUMINOUS SURFACES SY 141,000. 2.50 352,500.00 2.30 324,300.00 417.51 COLD PLANING EXISTING RUMBLE STRIPS (F) LF 21,519. .50 10,759.50 .50 10,759.50 15652 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 16,100.00 16,100.00 29,500.00 29,500.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 24,100.00 24,100.00 29,500.00 29,500.00 502.104 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 16,100.00 16,100.00 29,500.00 29,500.00 502.105 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 24,100.00 24,100.00 29,500.00 29,500.00 502.106 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 16,100.00 16,100.00 29,500.00 29,500.00 502.107 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 24,100.00 24,100.00 29,500.00 29,500.00 502.108 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 21,100.00 21,100.00 29,500.00 29,500.00 502.109 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 28,100.00 28,100.00 29,500.00 29,500.00 504.1 COMMON BRIDGE EXCAVATION (F) CY 51. 31.50 1,606.50 50.00 2,550.00 511.0001 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 783. 11.00 8,613.00 10.00 7,830.00 511.0002 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 803. 11.00 8,833.00 10.00 8,030.00 511.0003 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 224. 11.00 2,464.00 12.00 2,688.00 511.0004 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 290. 11.00 3,190.00 12.00 3,480.00 511.0005 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 290. 11.00 3,190.00 12.00 3,480.00 511.0006 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 354. 11.00 3,894.00 12.00 4,248.00 511.0007 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 354. 11.00 3,894.00 12.00 4,248.00 511.0008 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 398. 11.00 4,378.00 12.00 4,776.00 511.0009 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 317. 11.00 3,487.00 12.00 3,804.00 511.02 PREPARATION FOR PARTIAL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 395. 251.00 99,145.00 260.00 102,700.00 511.03 PREPARATION FOR FULL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 254. 552.00 140,208.00 450.00 114,300.00 512.0101 PREPARATION FOR CONCRETE REPAIRS, CLASS I SY 20. 301.00 6,020.00 600.00 12,000.00 512.0201 PREPARATION FOR CONCRETE REPAIRS, CLASS II SY 40. 602.00 24,080.00 750.00 30,000.00 520.01 CONCRETE CLASS AA CY 47. 703.00 33,041.00 550.00 25,850.00 520.02 CONCRETE CLASS AA, ABOVE FOOTINGS CY 92. 803.00 73,876.00 1,200.00 110,400.00 534.1 WATER REPELLENT (LINSEED OIL) GAL 67. 15.00 1,005.00 100.00 6,700.00 15652 PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 534.3 WATER REPELLENT (SILANE- SILOXANE) GAL 13. 35.00 455.00 100.00 1,300.00 538.2 BARRIER MEMBRANE, VERTICAL SURFACES (F) SY 76. 40.00 3,040.00 45.00 3,420.00 538.6 BARRIER MEMBRANE, WELDED BY TORCH, MACHINE METHOD (F) SY 3,788. 30.00 113,640.00 23.00 87,124.00 559.41 MODIFIED ELASTOMERIC PLUG TYPE EXPANSION JOINT, 6" WIDE (F) LF 96. 54.00 5,184.00 54.00 5,184.00 559.412 MODIFIED ELASTOMERIC PLUG TYPE EXPANSION JOINT, 20" WIDE (F) LF 359. 78.50 28,181.50 80.00 28,720.00 560.201 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT, REHABILITATION (F) LF 299. 141.00 42,159.00 120.00 35,880.00 561.1121 PREFABRICATED EXPANSION JOINT, TYPE A REHABILITATION (F) LF 116. 90.50 10,498.00 65.00 7,540.00 565.801 RESETTING BRIDGE APPROACH RAIL LF 1,500. 8.90 13,350.00 8.00 12,000.00 604.0007 POLYETHYLENE LINER EA 145. 225.00 32,625.00 140.00 20,300.00 604.4 RECONSTRUCTING/ADJUSTING CATCH BASIN & DROP INLET LF 210. 250.00 52,500.00 325.00 68,250.00 604.72 GRATES & FRAMES, TYPE B EA 95. 475.00 45,125.00 275.00 26,125.00 604.76 GRATES & FRAMES, TYPE F EA 50. 575.00 28,750.00 350.00 17,500.00 606.120 BEAM GUARDRAIL (STANDARD SECTION-STEEL POST) LF 41,200. 14.50 597,400.00 14.25 587,100.00 606.1454 BEAM GUARDRAIL (TERM. UNIT TYPE EAGRT 50 FT.) U 30. 1,980.00 59,400.00 1,850.00 55,500.00 606.147 BEAM GUARDRAIL (TERMINAL UNIT TYPE G-2) U 30. 420.00 12,600.00 500.00 15,000.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 3,700. 25.00 92,500.00 15.00 55,500.00 606.9523 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 3 U 5. 5,700.00 28,500.00 8,000.00 40,000.00 608.28 8" CONCRETE SIDEWALK (F) SY 54. 48.00 2,592.00 60.00 3,240.00 609.5 RESET GRANITE CURB LF 475. 16.50 7,837.50 10.00 4,750.00 609.55 RESET GRANITE CURB (BRIDGE) LF 216. 55.00 11,880.00 85.00 18,360.00 609.811 BITUMINOUS CURB, TYPE B (4" REVEAL) LF 400. 10.00 4,000.00 4.50 1,800.00 616.95 INSTALL TRAFFIC STUDY EQUIPMENT U 1. 4,580.00 4,580.00 5,000.00 5,000.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 200,000.00 200,000.00 200,000.00 200,000.00 618.7 FLAGGERS HR 4,200. 18.00 75,600.00 23.00 96,600.00 619.1 MAINTENANCE OF TRAFFIC U 1. 121,500.00 121,500.00 150,000.00 150,000.00 619.253 PORTABLE CHANGEABLE MESSAGE SIGN (UNIT WEEK) UWK 20. 301.00 6,020.00 300.00 6,000.00 15652 PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 470. 4.30 2,021.00 4.00 1,880.00 621.31 SINGLE DELINEATOR WITH POST EA 575. 28.00 16,100.00 28.00 16,100.00 621.32 DOUBLE DELINEATOR WITH POST EA 50. 38.00 1,900.00 32.00 1,600.00 628.2 SAWED BITUMINOUS PAVEMENT LF 2,500. .95 2,375.00 1.00 2,500.00 628.22 SAWED BITUMINOUS PAVEMENT (BRIDGE) LF 415. .95 394.25 2.00 830.00 632.0106 RETROREFLECTIVE PAINT PAVE. MARKING, 6" LINE LF 464,000. .11 51,040.00 .11 51,040.00 632.0112 RETROREFLECTIVE PAINT PAVE. MARKING, 12" LINE LF 14,300. .18 2,574.00 .18 2,574.00 632.0118 RETROREFLECTIVE PAINT PAVE. MARKING, 18" LINE LF 500. 1.50 750.00 1.50 750.00 632.3112 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 12" LINE LF 7,200. 1.50 10,800.00 1.50 10,800.00 632.3118 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 18" LINE LF 250. 3.00 750.00 3.00 750.00 632.9112 OBLITERATE PAVEMENT MARKING, 12" LINE LF 18,500. .60 11,100.00 .60 11,100.00 645.531 SILT FENCE LF 500. 2.00 1,000.00 3.00 1,500.00 646.3 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS A 16. 1,630.00 26,080.00 1,700.00 27,200.00 647.1 HUMUS CY 7,500. 20.00 150,000.00 16.00 120,000.00 670.104 TEMPORARY PORTABLE LIGHTING U 5. 1,510.00 7,550.00 500.00 2,500.00 692. MOBILIZATION U 1. 290,000.00 290,000.00 275,000.00 275,000.00 693. ON-THE-JOB TRAINING OF UNSKILLED WORKERS $ 1. 600.00 600.00 600.00 600.00 698.14 FIELD OFFICE TYPE D MON 19. 1,000.00 19,000.00 2,000.00 38,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 1002.1 REPAIRS OR REPLACEMENTS AS NEEDED $ 1. 100,000.00 100,000.00 100,000.00 100,000.00 1010.15 FUEL ADJUSTMENT $ 1. 70,000.00 70,000.00 70,000.00 70,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 75,000.00 75,000.00 75,000.00 75,000.00 1010.3 QUALITY CONTROL QUALITY ASSURANCE (QC/QA ASPHALT $ 1. 110,000.00 110,000.00 110,000.00 110,000.00 $6,224,047.25 $6,336,741.75