THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: HOPKINTON-NEW LONDON X-A000(474), 14511 COUNTIES AND CODES: MERRIMACK 013 DATE BIDS OPEN: JANUARY 31, 2008 SCOPE OF WORK: ROADWAY AND BRIDGE REHABILITATION LOCATION: I-89 FROM EXIT 7 TO 8 AND EXIT 9 TO 11 COMPLETION DATE: SEPTEMBER 18, 2009 A CONTINENTAL PAVING INC. ONE CONTINENTAL DR., LONDONDERRY, NH 03053 $ 9,671,292.00 B PIKE INDUSTRIES, INC. 3 EASTGATE PARK ROAD, BELMONT, NH 03220 $ 9,974,269.26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 201.01 CLEARING (F) A 4. 4,000.00 16,000.00 6,000.00 24,000.00 201.1 CLEARING AND GRUBBING (F) A .2 10,000.00 2,000.00 10,000.00 2,000.00 201.21 REMOVING SMALL TREES EA 3. 300.00 900.00 200.00 600.00 201.22 REMOVING LARGE TREES EA 5. 400.00 2,000.00 500.00 2,500.00 202.6 CURB REMOVAL FOR STORAGE LF 1,500. 2.00 3,000.00 1.60 2,400.00 202.7 REMOVAL OF GUARDRAIL (F) LF 19,700. 2.00 39,400.00 2.00 39,400.00 203.1 COMMON EXCAVATION CY 550. 12.00 6,600.00 7.50 4,125.00 203.5540 GUARDRAIL TAPERED RAIL PLATFORM LF 300. 12.00 3,600.00 16.00 4,800.00 203.5554 GUARDRAIL 50' EAGRT PLATFORM U 12. 1,500.00 18,000.00 1,000.00 12,000.00 203.601 EMBANKMENT-IN-PLACE CY 10,900. 10.00 109,000.00 9.90 107,910.00 203.81 PRESPLITTING HOLES LF 50. 20.00 1,000.00 100.00 5,000.00 203.91 ROCK SCALING HAND METHOD HR 80. 100.00 8,000.00 750.00 60,000.00 206.1 COMMON STRUCTURE EXCAVATION CY 155. 30.00 4,650.00 30.00 4,650.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 50. 500.00 25,000.00 15.00 750.00 206.2 ROCK STRUCTURE EXCAVATION CY 13. 100.00 1,300.00 40.00 520.00 209.1 GRANULAR BACKFILL CY 15. 20.00 300.00 46.00 690.00 209.201 GRANULAR BACKFILL (BRIDGE) (F) CY 112. 40.00 4,480.00 30.00 3,360.00 225.2 PRESTRESSED ROCK BOLTS LF 500. 80.00 40,000.00 130.00 65,000.00 304.3 CRUSHED GRAVEL (F) CY 300. 25.00 7,500.00 18.00 5,400.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING TON 3,000. 15.00 45,000.00 25.00 75,000.00 403.11001 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (QC/QA TIER 1) TON 53,100. 57.00 3,026,700.00 56.50 3,000,150.00 14511 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 403.11002 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (QC/QA TIER 2) TON 6,600. 57.00 376,200.00 56.50 372,900.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 80. 95.00 7,600.00 65.00 5,200.00 403.6 PAVEMENT JOINT ADHESIVE LF 390,300. .22 85,866.00 .19 74,157.00 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 413. 120.00 49,560.00 230.00 94,990.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 150. 75.00 11,250.00 75.00 11,250.00 417. COLD PLANING BITUMINOUS SURFACES SY 485,700. 1.35 655,695.00 1.08 524,556.00 500.021 PREPARATION FOR COVER PLATE INSPECTION U 48. 75.00 3,600.00 450.00 21,600.00 500.022 PREPARATION FOR COVER PLATE INSPECTION W/ LEAD PAINT POLLUTION CONTROLS U 72. 250.00 18,000.00 1,400.00 100,800.00 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 75,000.00 75,000.00 54,000.00 54,000.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 75,000.00 75,000.00 69,000.00 69,000.00 502.103 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 200,000.00 200,000.00 210,000.00 210,000.00 502.104 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 200,000.00 200,000.00 210,000.00 210,000.00 502.105 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 150,000.00 150,000.00 150,000.00 150,000.00 502.106 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 150,000.00 150,000.00 150,000.00 150,000.00 504.1 COMMON BRIDGE EXCAVATION (F) CY 180. 20.00 3,600.00 35.00 6,300.00 511.0001 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 210. 10.00 2,100.00 12.50 2,625.00 511.0002 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 210. 10.00 2,100.00 12.50 2,625.00 511.0003 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 1,181. 10.00 11,810.00 12.50 14,762.50 511.0004 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 711. 10.00 7,110.00 12.50 8,887.50 511.0005 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 405. 10.00 4,050.00 12.50 5,062.50 511.0006 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 446. 10.00 4,460.00 12.50 5,575.00 511.0007 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 168. 10.00 1,680.00 12.50 2,100.00 511.0008 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 235. 10.00 2,350.00 12.50 2,937.50 511.0009 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 506. 10.00 5,060.00 12.50 6,325.00 14511 PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 511.0010 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 506. 10.00 5,060.00 12.50 6,325.00 511.0011 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 202. 10.00 2,020.00 12.50 2,525.00 511.0012 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 202. 10.00 2,020.00 12.50 2,525.00 511.02 PREPARATION FOR PARTIAL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 270. 260.00 70,200.00 550.00 148,500.00 511.03 PREPARATION FOR FULL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 71. 450.00 31,950.00 1,400.00 99,400.00 512.0101 PREPARATION FOR CONCRETE REPAIRS, CLASS I SY 6. 900.00 5,400.00 550.00 3,300.00 512.0201 PREPARATION FOR CONCRETE REPAIRS, CLASS II SY 70. 700.00 49,000.00 800.00 56,000.00 520.01 CONCRETE CLASS AA CY 48. 701.00 33,648.00 750.00 36,000.00 520.02 CONCRETE CLASS AA, ABOVE FOOTINGS CY 126. 1,191.00 150,066.00 1,350.00 170,100.00 520.12 CONCRETE CLASS A, ABOVE FOOTINGS (F) CY 14. 2,101.00 29,414.00 1,800.00 25,200.00 520.7102 CONCRETE BRIDGE DECK (QC/QA) (F) CY 201. 830.00 166,830.00 950.00 190,950.00 520.7202 CONCRETE BRIDGE DECK (QC/QA) (F) CY 201. 830.00 166,830.00 950.00 190,950.00 520.73026 CONCRETE BRIDGE DECK (QC/QA) (PANEL OPTION) (F) CY 122. 820.00 100,040.00 1,100.00 134,200.00 520.74026 CONCRETE BRIDGE DECK (QC/QA) (PANEL OPTION) (F) CY 122. 820.00 100,040.00 1,100.00 134,200.00 534.1 WATER REPELLENT (LINSEED OIL) GAL 21. 100.00 2,100.00 35.00 735.00 534.3 WATER REPELLENT (SILANE- SILOXANE) GAL 86. 100.00 8,600.00 75.00 6,450.00 536.11 EPOXY COATING FOR CONCRETE (F) SF 702. 11.00 7,722.00 10.00 7,020.00 538.2 BARRIER MEMBRANE, VERTICAL SURFACES (F) SY 126. 45.00 5,670.00 44.00 5,544.00 538.6 BARRIER MEMBRANE, WELDED BY TORCH, MACHINE METHOD (F) SY 7,042. 20.00 140,840.00 20.00 140,840.00 541.201 PVC WATERSTOPS, NH TYPE 2 LF 32. 5.00 160.00 5.00 160.00 541.5 PVC WATERSTOPS, NH TYPE 5 (F) LF 198. 5.00 990.00 9.00 1,782.00 544.2 REINFORCING STEEL, EPOXY COATED (F) LB 167,860. 1.95 327,327.00 1.30 218,218.00 544.21 REINFORCING STEEL, EPOXY COATED,MECHANICAL CONNECTORS (F) LB 9,374. 2.90 27,184.60 4.20 39,370.80 14511 PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 547. SHEAR CONNECTORS (F) EA 7,884. 3.00 23,652.00 3.00 23,652.00 559.4 ELASTOMERIC PLUG TYPE EXPANSION JOINT (F) LF 184. 100.00 18,400.00 90.00 16,560.00 559.41 MODIFIED ELASTOMERIC PLUG TYPE EXPANSION JOINT (F) LF 100. 48.00 4,800.00 42.00 4,200.00 559.5 SILICONE JOINT SEALANT (F LF 107. 15.00 1,605.00 17.00 1,819.00 560.101 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 49. 635.00 31,115.00 650.00 31,850.00 560.102 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT (F) LF 49. 635.00 31,115.00 650.00 31,850.00 560.2 PREFABRICATED COMPRESSION SEAL EXPANSION JOINT - REHABILITATION (F) LF 104. 100.00 10,400.00 150.00 15,600.00 563.22 BRIDGE RAIL T2 (F) LF 1,211.9 90.00 109,071.00 90.00 109,071.00 563.223 BRIDGE RAIL T2 WITH SNOW SCREENING (F) LF 620.4 125.00 77,550.00 126.00 78,170.40 565.22 BRIDGE APPROACH RAIL T2 (F) LF 699. 137.00 95,763.00 137.00 95,763.00 570.4 MORTAR RUBBLE MASONRY (F) CY 25. 500.00 12,500.00 425.00 10,625.00 570.9 RESETTING MASONRY WALL CY 1. 500.00 500.00 425.00 425.00 585.2 STONE FILL, CLASS B CY 240. 35.00 8,400.00 22.00 5,280.00 585.3 STONE FILL, CLASS C CY 24. 50.00 1,200.00 46.00 1,104.00 593.411 GEOTEXTILE; PERM CONTROL CL.1, NON-WOVEN SY 500. 2.50 1,250.00 3.00 1,500.00 603.00330 30" R.C. PIPE, 3000D LF 8. 100.00 800.00 100.00 800.00 603.83115 15" PLASTIC PIPE (CORR. INTERIOR) LF 16. 75.00 1,200.00 35.00 560.00 604.0007 POLYETHYLENE LINER EA 14. 120.00 1,680.00 260.00 3,640.00 604.12 CATCH BASINS TYPE B U 1. 2,500.00 2,500.00 1,700.00 1,700.00 604.4 RECONSTRUCTING/ADJUSTING CATCH BASIN & DROP INLET LF 49. 300.00 14,700.00 330.00 16,170.00 604.6 MANHOLE COVERS & FRAMES EA 1. 450.00 450.00 475.00 475.00 604.75 GRATES & FRAMES, TYPE E EA 1. 450.00 450.00 625.00 625.00 606.012 W6X9 STEEL POST REPLACE- MENTS FOR BEAM GUARDRAIL POSTS EA 25. 40.00 1,000.00 40.00 1,000.00 606.0122 STEEL POST ASSEMBLIES FOR BEAM GUARDRAIL POSTS EA 25. 5.50 137.50 5.50 137.50 606.120 BEAM GUARDRAIL (STANDARD SECTION-STEEL POST) LF 18,350. 15.40 282,590.00 15.50 284,425.00 606.1454 BEAM GUARDRAIL (TERM. UNIT TYPE EAGRT 50 FT.) U 15. 1,925.00 28,875.00 1,930.00 28,950.00 606.147 BEAM GUARDRAIL (TERMINAL UNIT TYPE G-2) U 17. 550.00 9,350.00 550.00 9,350.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 8,500. 20.00 170,000.00 16.50 140,250.00 606.4175 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL- ANCHORED LF 580. 30.00 17,400.00 45.00 26,100.00 606.9523 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 3 U 6. 4,000.00 24,000.00 4,270.00 25,620.00 14511 PAGE 5 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 607.1 WOVEN WIRE FENCE LF 50. 20.00 1,000.00 20.00 1,000.00 607.41 POST ASSEMBLIES FOR WOVEN WIRE FENCE EA 4. 250.00 1,000.00 80.00 320.00 608.28 8" CONCRETE SIDEWALK (F) SY 250. 60.00 15,000.00 50.00 12,500.00 609.5 RESET GRANITE CURB LF 2,800. 6.00 16,800.00 6.90 19,320.00 609.811 BITUMINOUS CURB, TYPE B (4" REVEAL) LF 2,000. 4.00 8,000.00 3.50 7,000.00 615.01 TRAFFIC SIGN TYPE A (F) SF 235. 45.00 10,575.00 42.00 9,870.00 615.012 TRAFFIC SIGN TYPE A, BREAKAWAY MOUNTS (F) SF 806. 65.00 52,390.00 58.00 46,748.00 615.013 REMOVING TRAFFIC SIGN TYPE A U 11. 500.00 5,500.00 800.00 8,800.00 615.02 TRAFFIC SIGN TYPE B (F) SF 229.5 65.00 14,917.50 50.00 11,475.00 615.022 TRAFFIC SIGN TYPE B, BREAKAWAY MOUNTS (F) SF 588.75 75.00 44,156.25 64.00 37,680.00 615.03 TRAFFIC SIGN TYPE C (F) SF 410.75 35.00 14,376.25 34.00 13,965.50 615.04 TRAFFIC SIGN TYPE AA (F) SF 144. 20.00 2,880.00 16.00 2,304.00 615.05 TRAFFIC SIGN TYPE BB (F) SF 41.67 20.00 833.40 18.00 750.06 615.06 TRAFFIC SIGN TYPE CC (F) SF 128.5 15.00 1,927.50 12.00 1,542.00 616.95 INSTALL TRAFFIC STUDY EQUIPMENT U 1. 5,000.00 5,000.00 4,950.00 4,950.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 250,000.00 250,000.00 250,000.00 250,000.00 619.1 MAINTENANCE OF TRAFFIC U 1. 150,000.00 150,000.00 200,000.00 200,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 1. 20,000.00 20,000.00 20,000.00 20,000.00 619.27 TRAILER-MOUNTED SPEED LIMIT SIGN U 3. 3,000.00 9,000.00 300.00 900.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 190. 4.00 760.00 4.00 760.00 621.31 SINGLE DELINEATOR WITH POST EA 100. 24.00 2,400.00 28.00 2,800.00 621.73 FLEXIBLE DELINEATOR (TEMPORARY) EA 200. 45.00 9,000.00 35.00 7,000.00 622.1 STEEL WITNESS MARKERS EA 40. 22.00 880.00 25.00 1,000.00 628.2 SAWED BITUMINOUS PAVEMENT LF 2,790. 1.00 2,790.00 2.00 5,580.00 632.0106 RETROREFLECTIVE PAINT PAVE. MARKING, 6" LINE LF 1,161,000. .11 127,710.00 .11 127,710.00 632.1106 PREFORMED RETROREFLECTIVE TAPE, TYPE I (REMOVABLE) 6" LINE LF 33,000. 1.10 36,300.00 1.10 36,300.00 632.1112 PREFORMED RETROREFLECTIVE TAPE, TYPE I (REMOVABLE) 12" LINE LF 300. 2.50 750.00 2.50 750.00 632.3112 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 12" LINE LF 40,000. 1.35 54,000.00 1.40 56,000.00 632.3116 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 16" LINE LF 130. 2.00 260.00 2.00 260.00 632.3118 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 18" LINE LF 130. 3.00 390.00 3.00 390.00 14511 PAGE 6 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 632.9106 OBLITERATE PAVEMENT MARKING, 6" LINE LF 20,000. .30 6,000.00 .30 6,000.00 632.9112 OBLITERATE PAVEMENT MARKING, 12" LINE LF 600. 1.00 600.00 1.00 600.00 645.2 MATTING FOR EROSION CONTROL SY 100. 2.00 200.00 2.50 250.00 645.21 SLOPE STABILIZATION (2:1 OR FLATTER) SY 200. 2.15 430.00 1.90 380.00 645.22 SLOPE STABILIZATION (STEEPER THAN 2:1) SY 1,200. 2.15 2,580.00 2.20 2,640.00 645.3 EROSION STONE TON 300. 30.00 9,000.00 33.00 9,900.00 645.531 SILT FENCE LF 2,000. 3.00 6,000.00 2.80 5,600.00 645.7 STORM WATER POLLUTION PREVENTION PLAN U 1. 4,000.00 4,000.00 4,000.00 4,000.00 645.71 MONITORING SWPPP AND EROSION AND SEDIMENT CONTROLS HR 80. 65.00 5,200.00 80.00 6,400.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 5,000. .40 2,000.00 .38 1,900.00 647.1 HUMUS CY 1,500. 16.00 24,000.00 14.50 21,750.00 670.045 CONSTRUCT AND REMOVE DETOUR U 1. 25,000.00 25,000.00 23,000.00 23,000.00 670.104 TEMPORARY PORTABLE LIGHTING U 1. 2,000.00 2,000.00 18,000.00 18,000.00 692. MOBILIZATION U 1. 405,700.00 405,700.00 450,000.00 450,000.00 693. ON-THE-JOB TRAINING OF UNSKILLED WORKERS $ 1. 600.00 600.00 600.00 600.00 698.13 FIELD OFFICE TYPE C MON 20. 2,000.00 40,000.00 1,240.00 24,800.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 1002.1 REPAIRS OR REPLACEMENTS AS NEEDED $ 1. 48,000.00 48,000.00 48,000.00 48,000.00 1008.532 ALTERATIONS AND ADDITIONS AS NEEDED- INVASIVE SPECIES CONTROL $ 1. 1,000.00 1,000.00 1,000.00 1,000.00 1008.533 ALTERATIONS AND ADDITIONS AS NEEDED- INVASIVE SPECIES CONTROL $ 1. 1,000.00 1,000.00 1,000.00 1,000.00 1010.15 FUEL ADJUSTMENT $ 1. 70,000.00 70,000.00 70,000.00 70,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 1010.3 QUALITY CONTROL QUALITY ASSURANCE (QC/QA ASPHALT $ 1. 167,300.00 167,300.00 167,300.00 167,300.00 1010.41 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR CONCRETE $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 $9,671,292.00 $9,974,269.26