THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: BEDFORD X-A000(297), 13692A COUNTIES AND CODES: HILLSBOROUGH 011 DATE BIDS OPEN: MARCH 13, 2008 SCOPE OF WORK: ROADWAY REHABILITATION LOCATION: NH ROUTE 101, WEST OF THE INTERSECTION OF NH ROUTE 114 COMPLETION DATE: JUNE 26, 2009 A WEAVER BROS. CONST CO., INC. PO BOX 1326, CONCORD, NH 03302 $ 1,642,938.90 B PARK CONSTRUCTION CORP. PO BOX 600, FITZWILLIAM, NH 03447 $ 1,978,657.00 C R. S. AUDLEY, INC. 609 RT 3A, BOW, NH 03304 $ 1,998,386.00 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 201.1 CLEARING AND GRUBBING (F) A 1.4 4,500.00 6,300.00 5,500.00 7,700.00 12,000.00 16,800.00 201.21 REMOVING SMALL TREES EA 5. 125.00 625.00 300.00 1,500.00 300.00 1,500.00 201.22 REMOVING LARGE TREES EA 2. 300.00 600.00 600.00 1,200.00 500.00 1,000.00 202.31 FILL ABANDONED PIPE CY 20. 115.00 2,300.00 250.00 5,000.00 125.00 2,500.00 202.41 REMOVAL OF EXISTING PIPE 0-24" DIAMETER LF 143. 12.00 1,716.00 15.00 2,145.00 20.00 2,860.00 202.5 REMOVAL OF CATCH BASINS, DROP INLETS, AND MANHOLES EA 4. 250.00 1,000.00 350.00 1,400.00 550.00 2,200.00 203.1 COMMON EXCAVATION CY 9,000. 4.85 43,650.00 10.00 90,000.00 14.00 126,000.00 203.2 ROCK EXCAVATION CY 4,900. 27.00 132,300.00 30.00 147,000.00 31.00 151,900.00 203.5554 GUARDRAIL 50' EAGRT PLATFORM U 2. 900.00 1,800.00 2,500.00 5,000.00 1,550.00 3,100.00 203.6 EMBANKMENT-IN-PLACE (F) CY 2,000. 6.75 13,500.00 10.00 20,000.00 14.00 28,000.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 100. 10.00 1,000.00 25.00 2,500.00 18.00 1,800.00 206.2 ROCK STRUCTURE EXCAVATION CY 300. 66.00 19,800.00 100.00 30,000.00 97.00 29,100.00 209.1 GRANULAR BACKFILL CY 350. 12.00 4,200.00 25.00 8,750.00 34.00 11,900.00 214. FINE GRADING U 1. 22,000.00 22,000.00 45,000.00 45,000.00 36,000.00 36,000.00 304.1 SAND (F) CY 1,750. 16.50 28,875.00 19.00 33,250.00 24.00 42,000.00 304.2 GRAVEL (F) CY 3,600. 16.50 59,400.00 19.00 68,400.00 27.00 97,200.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING TON 200. 22.00 4,400.00 30.00 6,000.00 20.00 4,000.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 20. 25.00 500.00 35.00 700.00 33.00 660.00 304.4 CRUSHED STONE (FINE GRADATION) (F) CY 3,725. 20.00 74,500.00 25.00 93,125.00 27.00 100,575.00 403.11002 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (QC/QA TIER 2) TON 4,000. 57.00 228,000.00 65.00 260,000.00 54.00 216,000.00 13692A PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 200. 100.00 20,000.00 110.00 22,000.00 90.00 18,000.00 403.6 PAVEMENT JOINT ADHESIVE LF 17,500. .23 4,025.00 .30 5,250.00 .22 3,850.00 403.98 HOT BITUMINOUS CONCRETE LEVELING, MACHINE METHOD TON 500. 57.00 28,500.00 65.00 32,500.00 59.00 29,500.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 100. 80.00 8,000.00 90.00 9,000.00 80.00 8,000.00 411.1 HOT BITUMINOUS CONCRETE LEVELING COURSE TON 300. 63.00 18,900.00 65.00 19,500.00 59.00 17,700.00 417. COLD PLANING BITUMINOUS SURFACES SY 1,400. 7.75 10,850.00 10.00 14,000.00 7.00 9,800.00 520.1 CONCRETE CLASS A CY 3. 300.00 900.00 550.00 1,650.00 1,700.00 5,100.00 544.1 REINFORCING STEEL (ROADWAY) LB 20. 5.00 100.00 4.00 80.00 2.50 50.00 585.3 STONE FILL, CLASS C CY 56. 40.00 2,240.00 50.00 2,800.00 38.00 2,128.00 593.421 GEOTEXTILE; PERM CONTROL CL.2, NON-WOVEN SY 70. 3.00 210.00 3.00 210.00 3.50 245.00 603.00215 15" R.C. PIPE, 2000D LF 260. 27.00 7,020.00 55.00 14,300.00 80.00 20,800.00 603.00218 18" R.C. PIPE, 2000D LF 520. 42.00 21,840.00 64.00 33,280.00 85.00 44,200.00 603.13015 15" CORR. ALUMINIZED STEEL (TYPE2) PIPE .064" LF 60. 26.00 1,560.00 40.00 2,400.00 50.00 3,000.00 603.34115 15" STEEL END SECTIONS EA 4. 135.00 540.00 400.00 1,600.00 265.00 1,060.00 603.34124 24" STEEL END SECTIONS EA 1. 250.00 250.00 600.00 600.00 340.00 340.00 604.0007 POLYETHYLENE LINER EA 2. 225.00 450.00 250.00 500.00 250.00 500.00 604.12 CATCH BASINS TYPE B U 4. 1,600.00 6,400.00 1,800.00 7,200.00 2,150.00 8,600.00 604.15 CATCH BASINS TYPE E U 6. 1,700.00 10,200.00 2,000.00 12,000.00 2,280.00 13,680.00 605.506 6" PERF. CORR. POLYETHYL PIPE UND. LF 1,800. 16.50 29,700.00 22.00 39,600.00 27.50 49,500.00 605.79 UNDERDRAIN FLUSHING BASINS EA 7. 350.00 2,450.00 450.00 3,150.00 600.00 4,200.00 606.140 BEAM GUARDRAIL (STANDARD SECTION- WOOD POSTS) LF 700. 19.00 13,300.00 20.00 14,000.00 18.25 12,775.00 606.1454 BEAM GUARDRAIL (TERM. UNIT TYPE EAGRT 50 FT.) U 2. 2,200.00 4,400.00 2,400.00 4,800.00 2,100.00 4,200.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 500. 11.00 5,500.00 30.00 15,000.00 24.00 12,000.00 606.9522 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 2 U 2. 2,000.00 4,000.00 6,500.00 13,000.00 3,000.00 6,000.00 608.26 6" CONCRETE SIDEWALK (F) SY 645. 41.00 26,445.00 55.00 35,475.00 44.00 28,380.00 609.21 STRAIGHT GRANITE SLOPE CURB LF 2,010. 13.75 27,637.50 14.00 28,140.00 11.00 22,110.00 609.22 STRAIGHT GRANITE SLOPE CURB WITH RADIAL JOINTS LF 38. 14.00 532.00 14.00 532.00 11.00 418.00 614.511 CONCRETE PULL BOX 14" EA 12. 260.00 3,120.00 300.00 3,600.00 250.00 3,000.00 614.523 MOLDED PULL BOX 17"X30" EA 3. 500.00 1,500.00 500.00 1,500.00 450.00 1,350.00 614.7314 3" PVC PLASTIC CONDUIT, SCHEDULE 40 LF 400. 6.75 2,700.00 7.00 2,800.00 6.50 2,600.00 614.7318 3" PVC PLASTIC CONDUIT, SCHEDULE 80 LF 125. 13.00 1,625.00 15.00 1,875.00 12.00 1,500.00 13692A PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 614.7324 3" 2-DUCT PVC PLASTIC CONDUIT, SCHEDULE 40 LF 225. 10.00 2,250.00 10.00 2,250.00 10.00 2,250.00 614.7328 3" 2-DUCT PVC PLASTIC CONDUIT, SCHEDULE 80 LF 300. 17.00 5,100.00 18.00 5,400.00 16.00 4,800.00 615.02 TRAFFIC SIGN TYPE B (F) SF 25. 80.00 2,000.00 60.00 1,500.00 50.00 1,250.00 615.03 TRAFFIC SIGN TYPE C (F) SF 104. 43.00 4,472.00 45.00 4,680.00 35.00 3,640.00 615.034 RELOCATING TRAFFIC SIGN, TYPE C U 3. 210.00 630.00 200.00 600.00 180.00 540.00 615.06 TRAFFIC SIGN TYPE CC (F) SF 33. 16.00 528.00 20.00 660.00 20.00 660.00 616.101 TRAFFIC SIGNALS U 1. 82,000.00 82,000.00 85,000.00 85,000.00 73,800.00 73,800.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 210,000.00 210,000.00 210,000.00 210,000.00 210,000.00 210,000.00 618.7 FLAGGERS HR 6,500. 19.00 123,500.00 22.00 143,000.00 17.00 110,500.00 619.1 MAINTENANCE OF TRAFFIC U 1. 35,000.00 35,000.00 45,000.00 45,000.00 24,000.00 24,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 2. 3,500.00 7,000.00 10,000.00 20,000.00 17,000.00 34,000.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 10. 5.00 50.00 6.00 60.00 5.00 50.00 621.31 SINGLE DELINEATOR WITH POST EA 70. 26.00 1,820.00 30.00 2,100.00 28.00 1,960.00 622.1 STEEL WITNESS MARKERS EA 7. 25.00 175.00 30.00 210.00 25.00 175.00 622.2 CONCRETE BOUNDS EA 6. 350.00 2,100.00 300.00 1,800.00 280.00 1,680.00 625.22 CONCRETE LIGHT POLE BASES, TYPE B (FOR HIGH- WAY LIGHTING) EA 2. 575.00 1,150.00 550.00 1,100.00 500.00 1,000.00 625.52 LIGHT POLE (HIGHWAY) U 2. 2,400.00 4,800.00 2,500.00 5,000.00 2,250.00 4,500.00 628.2 SAWED BITUMINOUS PAVEMENT LF 300. 2.70 810.00 2.00 600.00 1.50 450.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 85,500. .11 9,405.00 .10 8,550.00 .10 8,550.00 632.3118 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 18" LINE LF 140. 2.50 350.00 3.00 420.00 2.50 350.00 632.32 RETROREFLECT. THERMOPLAS. PAVEMENT MARKING, SYMBOL OR WORD SF 544. 3.85 2,094.40 5.00 2,720.00 3.75 2,040.00 641. LOAM CY 250. 18.00 4,500.00 25.00 6,250.00 26.00 6,500.00 644.82 SALT-TOLERANT GRASS SEED, TYPE 82 LB 5. 27.00 135.00 15.00 75.00 10.00 50.00 645.111 MULCH SY 2,000. .20 400.00 .30 600.00 .20 400.00 645.21 SLOPE STABILIZATION (2:1 OR FLATTER) SY 260. 1.65 429.00 2.00 520.00 2.00 520.00 645.23 CHANNEL STABILIZATION (LOW VELOCITY) SY 300. 1.85 555.00 2.00 600.00 2.00 600.00 645.3 EROSION STONE TON 400. 23.00 9,200.00 30.00 12,000.00 27.00 10,800.00 645.531 SILT FENCE LF 5,000. 2.50 12,500.00 3.00 15,000.00 2.50 12,500.00 645.7 STORM WATER POLLUTION PREVENTION PLAN U 1. 2,400.00 2,400.00 3,000.00 3,000.00 2,000.00 2,000.00 645.71 MONITORING SWPPP AND EROSION AND SEDIMENT CONTROLS HR 160. 40.00 6,400.00 60.00 9,600.00 40.00 6,400.00 646.3 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS A 3. 1,350.00 4,050.00 1,500.00 4,500.00 1,250.00 3,750.00 13692A PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 647.1 HUMUS CY 1,250. 13.50 16,875.00 25.00 31,250.00 23.00 28,750.00 670.066 MAILBOX SUPPORT ASSEMBLIES EA 6. 125.00 750.00 350.00 2,100.00 190.00 1,140.00 692. MOBILIZATION U 1. 85,850.00 85,850.00 100,000.00 100,000.00 144,000.00 144,000.00 698.13 FIELD OFFICE TYPE C MON 16. 1,900.00 30,400.00 1,200.00 19,200.00 1,400.00 22,400.00 698.2 PHYSICAL TESTING LABORATORY MON 8. 700.00 5,600.00 750.00 6,000.00 800.00 6,400.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 1008.1 ALTERATIONS AND ADDITIONS AS NEEDED - TEMPORARY LIGHTING $ 1. 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00 1008.53 ALTERATIONS AND ADDITIONS AS NEEDED - INVASIVE SPECIES CONTROL $ 1. 5,500.00 5,500.00 5,500.00 5,500.00 5,500.00 5,500.00 1008.8 ALTERATIONS AND ADDITIONS AS NEEDED - WINTER MAINTENANCE $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1010.15 FUEL ADJUSTMENT $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 1010.3 QUALITY CONTROL QUALITY ASSURANCE (QC/QA ASPHALT $ 1. 4,800.00 4,800.00 4,800.00 4,800.00 4,800.00 4,800.00 $1,642,938.90 $1,978,657.00 $1,998,386.00