THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: KEENE-SURRY STP-X-000S(387), 13338 COUNTIES AND CODES: CHESHIRE 005 DATE BIDS OPEN: JANUARY 30, 2008 SCOPE OF WORK: ROADWAY AND BRIDGE REHABILITATION LOCATION: NH ROUTE 12 SOUTH OF THE INTERSECTION WITH ROUTE 9 COMPLETION DATE: SEPTEMBER 5, 2008 A THE LANE CONSTRUCTION CORP. 90 FIELDSTONE COURT, CHESHIRE, CT 06410 $ 2,837,003.00 B FRANK W. WHITCOMB CONSTRUCTION CORPORATION 187 WHITCOMB ROAD, P.O. BOX 1000, WALPOLE, NH 03608 $ 3,065,090.00 C WEAVER BROS. CONST. CO. INC. PO BOX 1326, CONCORD, NH 03301 $ 3,169,775.75 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 202.7 REMOVAL OF GUARDRAIL (F) LF 2,825. 4.10 11,582.50 3.00 8,475.00 3.10 8,757.50 203.1 COMMON EXCAVATION CY 350. 10.00 3,500.00 15.00 5,250.00 8.25 2,887.50 203.2 ROCK EXCAVATION CY 200. 50.00 10,000.00 50.00 10,000.00 20.00 4,000.00 203.5540 GUARDRAIL TAPERED RAIL PLATFORM LF 150. 10.00 1,500.00 15.00 2,250.00 16.00 2,400.00 203.55541 GUARDRAIL 50' EAGRT PLATFORM ALTERNATE U 23. 1,200.00 27,600.00 1,100.00 25,300.00 1,000.00 23,000.00 203.5596 GUARDRAIL TERMINAL E-2 PLATFORM LF 250. 12.00 3,000.00 25.00 6,250.00 13.00 3,250.00 203.601 EMBANKMENT IN PLACE CY 575. 5.00 2,875.00 20.00 11,500.00 15.00 8,625.00 203.91 ROCK SCALING HAND METHOD HR 200. 50.00 10,000.00 125.00 25,000.00 500.00 100,000.00 203.92 ROCK SCALING MACHINE METHOD HR 200. 100.00 20,000.00 225.00 45,000.00 150.00 30,000.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 15. 40.00 600.00 75.00 1,125.00 35.00 525.00 304.301 CRUSHED GRAVEL CY 250. 21.00 5,250.00 35.00 8,750.00 26.00 6,500.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING TON 1,400. 21.00 29,400.00 21.00 29,400.00 24.00 33,600.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 10. 25.00 250.00 35.00 350.00 30.00 300.00 403.11001 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (QC/QA TIER 1) TON 11,400. 52.00 592,800.00 65.00 741,000.00 68.00 775,200.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 50. 95.00 4,750.00 150.00 7,500.00 160.00 8,000.00 403.6 PAVEMENT JOINT ADHESIVE LF 59,250. .22 13,035.00 .22 13,035.00 .25 14,812.50 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 40. 160.00 6,400.00 225.00 9,000.00 225.00 9,000.00 13338 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 411.1 HOT BITUMINOUS CONCRETE LEVELING COURSE TON 2,200. 65.00 143,000.00 73.00 160,600.00 76.00 167,200.00 411.46 PLANT MIX SURFACE TREAT- MENT (ASPHALT CEMENT), 3/4 INCH TON 2,500. 65.00 162,500.00 65.00 162,500.00 70.00 175,000.00 413.19 HOT POURED CRACK SEALANT (NIGHT) LB 1,900. 3.25 6,175.00 3.00 5,700.00 3.00 5,700.00 415.8 GLASS FIBER PAVEMENT REINFORCEMENT MESH SY 34,750. 5.90 205,025.00 3.00 104,250.00 3.25 112,937.50 417. COLD PLANING BITUMINOUS SURFACES SY 49,750. 1.40 69,650.00 3.00 149,250.00 3.25 161,687.50 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 50,000.00 50,000.00 15,000.00 15,000.00 5,000.00 5,000.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 114,500.00 114,500.00 55,000.00 55,000.00 8,000.00 8,000.00 511.0001 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 706. 11.00 7,766.00 30.00 21,180.00 15.00 10,590.00 511.02 PREPARATION FOR PARTIAL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 59. 205.00 12,095.00 450.00 26,550.00 400.00 23,600.00 511.03 PREPARATION FOR FULL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 115. 330.00 37,950.00 550.00 63,250.00 500.00 57,500.00 520.01 CONCRETE CLASS AA CY 7. 500.00 3,500.00 1,200.00 8,400.00 2,000.00 14,000.00 520.02 CONCRETE CLASS AA ABOVE FOOTINGS CY 28. 1,100.00 30,800.00 1,200.00 33,600.00 2,700.00 75,600.00 534.1 WATER REPELLENT (LINSEED OIL) GAL 10. 100.00 1,000.00 50.00 500.00 11.00 110.00 538.6 BARRIER MEMBRANE, WELDED BY TORCH, MACHINE METHOD (F) SY 706. 26.75 18,885.50 20.00 14,120.00 28.00 19,768.00 544.2 REINFORCING STEEL, EPOXY COATED (F) LB 850. 1.85 1,572.50 7.00 5,950.00 3.25 2,762.50 550.13 STRUCTURAL STEEL LB 500. 5.50 2,750.00 23.00 11,500.00 14.00 7,000.00 559.41 MODIFIED ELASTOMERIC PLUG TYPE EXPANSION JOINT (F) LF 103. 80.00 8,240.00 60.00 6,180.00 65.00 6,695.00 561.04 REHABILITATE EXPANSION JOINT U 1. 4,000.00 4,000.00 9,500.00 9,500.00 5,000.00 5,000.00 570.401 MORTAR RUBBLE MASONRY CY 3. 500.00 1,500.00 800.00 2,400.00 600.00 1,800.00 585.3 STONE FILL, CLASS C CY 15. 25.00 375.00 185.00 2,775.00 40.00 600.00 603.34112 12" STEEL END SECTIONS EA 4. 150.00 600.00 300.00 1,200.00 160.00 640.00 603.83112 12" PLASTIC PIPE (CORR. INTERIOR) LF 50. 25.00 1,250.00 45.00 2,250.00 20.00 1,000.00 604.0007 POLYETHYLENE LINER EA 8. 200.00 1,600.00 175.00 1,400.00 230.00 1,840.00 604.4 RECONSTRUCTING/ADJUSTING CATCH BASIN & DROP INLET LF 8. 250.00 2,000.00 350.00 2,800.00 300.00 2,400.00 605.506 6" PERF. CORR. POLYETHYL PIPE UND. LF 6,250. 20.00 125,000.00 25.00 156,250.00 19.00 118,750.00 605.512 12" PERF. CORR. POLYETHLY PIPE UND. LF 550. 24.00 13,200.00 35.00 19,250.00 26.00 14,300.00 13338 PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 605.515 15" PERF. CORR. POLYETHLY PIPE UND. LF 960. 26.00 24,960.00 45.00 43,200.00 28.00 26,880.00 605.518 18" PERF. CORR. POLYETHYL PIPE UND. LF 300. 30.00 9,000.00 55.00 16,500.00 32.00 9,600.00 606.000 STEEL BEAM FOR BEAM GUARDRAIL LF 100. 8.00 800.00 10.00 1,000.00 9.00 900.00 606.014 6"X8" WOOD POST REPLACE- MENTS FOR BEAM GUARDRAIL POSTS EA 20. 55.00 1,100.00 55.00 1,100.00 60.00 1,200.00 606.0142 6"X8" WOOD POST ASSEMBLIES FOR BEAM GUARDRAIL POSTS EA 20. 10.00 200.00 25.00 500.00 11.00 220.00 606.140 BEAM GUARDRAIL (STANDARD SECTION- WOOD POSTS) LF 3,700. 17.65 65,305.00 18.00 66,600.00 19.00 70,300.00 606.1454 BEAM GUARDRAIL (TERM. UNIT TYPE EAGRT 50 FT.) U 25. 2,000.00 50,000.00 2,000.00 50,000.00 2,200.00 55,000.00 606.1496 BEAM GUARDRAIL (TERMINAL UNIT TYPE E-2) LF 400. 24.00 9,600.00 25.00 10,000.00 26.00 10,400.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 1,090. 21.00 22,890.00 35.00 38,150.00 18.00 19,620.00 606.91 RESETTING OR SETTING GUARDRAIL LF 75. 12.00 900.00 15.00 1,125.00 15.00 1,125.00 606.9522 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 2 U 4. 4,350.00 17,400.00 2,500.00 10,000.00 3,000.00 12,000.00 609.55 RESET GRANITE CURB (BRIDGE) LF 24. 61.00 1,464.00 75.00 1,800.00 20.00 480.00 615.012 TRAFFIC SIGN TYPE A, BREAKAWAY MOUNTS (F) SF 388.5 58.00 22,533.00 60.00 23,310.00 63.00 24,475.50 615.013 REMOVING TRAFFIC SIGN TYPE A U 4. 800.00 3,200.00 400.00 1,600.00 850.00 3,400.00 615.02 TRAFFIC SIGN TYPE B (F) SF 69. 50.00 3,450.00 70.00 4,830.00 53.00 3,657.00 615.022 TRAFFIC SIGN TYPE B, BREAKAWAY MOUNTS (F) SF 126.25 64.00 8,080.00 80.00 10,100.00 67.00 8,458.75 615.03 TRAFFIC SIGN TYPE C (F) SF 108.5 32.00 3,472.00 50.00 5,425.00 35.00 3,797.50 615.05 TRAFFIC SIGN TYPE BB (F) SF 13. 18.00 234.00 20.00 260.00 20.00 260.00 615.06 TRAFFIC SIGN TYPE CC (F) SF 117.5 12.00 1,410.00 20.00 2,350.00 13.00 1,527.50 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 125,000.00 125,000.00 125,000.00 125,000.00 125,000.00 125,000.00 618.7 FLAGGERS HR 3,000. 14.00 42,000.00 23.00 69,000.00 22.00 66,000.00 619.1 MAINTENANCE OF TRAFFIC U 1. 150,000.00 150,000.00 125,000.00 125,000.00 90,000.00 90,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 2. 3,500.00 7,000.00 7,500.00 15,000.00 4,000.00 8,000.00 619.27 TRAILER-MOUNTED SPEED LIMIT SIGN U 2. 500.00 1,000.00 2,500.00 5,000.00 500.00 1,000.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 130. 4.00 520.00 5.00 650.00 5.00 650.00 621.31 SINGLE DELINEATOR WITH POST EA 200. 28.00 5,600.00 30.00 6,000.00 30.00 6,000.00 622.1 STEEL WITNESS MARKERS EA 25. 25.00 625.00 30.00 750.00 25.00 625.00 13338 PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 628.2 SAWED BITUMINOUS PAVEMENT LF 700. 3.00 2,100.00 3.00 2,100.00 1.75 1,225.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 287,500. .10 28,750.00 .12 34,500.00 .11 31,625.00 632.0108 RETROREFLECTIVE PAINT PAVE. MARKING, 8" LINE LF 16,500. .18 2,970.00 .15 2,475.00 .19 3,135.00 632.1104 PREFORMED RETROREFLECTIVE TAPE, TYPE I (REMOVABLE) 4" LINE LF 1,275. 1.10 1,402.50 2.00 2,550.00 1.20 1,530.00 632.3118 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 18" LINE LF 110. 3.00 330.00 3.00 330.00 3.30 363.00 632.32 RETROREFLECT. THERMOPLAS. PAVEMENT MARKING, SYMBOL OR WORD SF 425. 5.00 2,125.00 6.00 2,550.00 5.50 2,337.50 632.9104 OBLITERATE PAVEMENT MARKING, 4" LINE LF 21,800. .25 5,450.00 .40 8,720.00 .27 5,886.00 632.93 OBLITERATE PAVEMENT MARKINGS, RAISED PAVEMENT MARKINGS EA 460. 7.75 3,565.00 5.00 2,300.00 15.00 6,900.00 645.3 EROSION STONE TON 500. 25.00 12,500.00 20.00 10,000.00 34.00 17,000.00 645.531 SILT FENCE LF 4,500. 2.00 9,000.00 2.00 9,000.00 2.50 11,250.00 645.7 STORM WATER POLLUTION PREVENTION PLAN U 1. 2,500.00 2,500.00 2,500.00 2,500.00 2,800.00 2,800.00 645.71 MONITORING SWPPP AND EROSION AND SEDIMENT CONTROLS HR 25. 110.00 2,750.00 100.00 2,500.00 150.00 3,750.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 13,650. .34 4,641.00 .50 6,825.00 .40 5,460.00 647.1 HUMUS CY 1,525. 20.00 30,500.00 30.00 45,750.00 16.00 24,400.00 692. MOBILIZATION U 1. 250,000.00 250,000.00 175,000.00 175,000.00 335,000.00 335,000.00 698.13 FIELD OFFICE TYPE C MON 6. 1,500.00 9,000.00 1,500.00 9,000.00 2,000.00 12,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1002.11 REPAIRS OR REPLACEMENTS AS NEEDED (BRIDGE) $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 1008.1 ALTERATIONS AND ADDITIONS AS NEEDED - TEMPORARY LIGHTING $ 1. 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 1008.11 ALTERATIONS AND ADDITIONS AS NEEDED- UNANTICIPATED WORK $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1010.15 FUEL ADJUSTMENT $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00 1010.3 QUALITY CONTROL QUALITY ASSURANCE (QC/QA ASPHALT $ 1. 34,200.00 34,200.00 34,200.00 34,200.00 34,200.00 34,200.00 $2,837,003.00 $3,065,090.00 $3,169,775.75