THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: SALEM-MANCHESTER A000(122), 13933B COUNTIES AND CODES: ROCKINGHAM 015 HILLSBOROUGH 011 DATE BIDS OPEN: OCTOBER 12, 2006 SCOPE OF WORK: BRIDGE AND ROADWAY REHABILITATION LOCATION: CROSS STREET BRIDGE OVER I-93 COMPLETION DATE: JULY 25, 2008 A R. S. AUDLEY, INC. 609 RT 3A, BOW, NH 03304 $ 6,650,644.60 B E. D. SWETT, INC. 8 INDUSTRIAL PARK DR., CONCORD, NH 03301 $ 6,817,321.05 C C P M CONSTRUCTORS PO BOX B, 30 BONNEY ST., FREEPORT, ME 04032 $ 7,116,789.50 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 201.1 CLEARING AND GRUBBING (F) A .48 20,000.00 9,600.00 12,000.00 5,760.00 20,000.00 9,600.00 201.21 REMOVING SMALL TREES EA 5. 400.00 2,000.00 350.00 1,750.00 400.00 2,000.00 201.22 REMOVING LARGE TREES EA 2. 650.00 1,300.00 750.00 1,500.00 850.00 1,700.00 202.2 DEMOLISHING BUILDINGS U 1. 6,500.00 6,500.00 25,000.00 25,000.00 12,000.00 12,000.00 202.3 BUILDING ASBESTOS ABATEMENT U 1. 2,500.00 2,500.00 5,000.00 5,000.00 12,000.00 12,000.00 202.41 REMOVAL OF EXISTING PIPE 0-24" DIAMETER LF 210. 16.50 3,465.00 10.00 2,100.00 55.00 11,550.00 202.5 REMOVAL OF CATCH BASINS, DROP INLETS, AND MANHOLES EA 3. 250.00 750.00 250.00 750.00 460.00 1,380.00 202.7 REMOVAL OF GUARDRAIL (F) LF 3,115. 3.00 9,345.00 3.00 9,345.00 2.50 7,787.50 203.1 COMMON EXCAVATION CY 16,250. 12.00 195,000.00 9.00 146,250.00 13.00 211,250.00 203.5554 GUARDRAIL 50' EAGRT PLATFORM U 2. 1,000.00 2,000.00 1,500.00 3,000.00 2,650.00 5,300.00 203.5555 GUARDRAIL 25'EAGRT PLATFORM U 4. 675.00 2,700.00 1,200.00 4,800.00 1,550.00 6,200.00 203.6 EMBANKMENT-IN-PLACE (F) CY 12,500. 14.50 181,250.00 10.00 125,000.00 11.00 137,500.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 100. 39.00 3,900.00 20.00 2,000.00 70.00 7,000.00 209.2 GRANULAR BACKFILL (BRIDGE) CY 5,550. 36.00 199,800.00 45.00 249,750.00 20.00 111,000.00 214. FINE GRADING U 1. 60,000.00 60,000.00 25,000.00 25,000.00 40,000.00 40,000.00 304.1 SAND (F) CY 955. 26.00 24,830.00 20.00 19,100.00 27.00 25,785.00 304.2 GRAVEL (F) CY 1,020. 28.00 28,560.00 22.00 22,440.00 30.00 30,600.00 304.3 CRUSHED GRAVEL (F) CY 1,580. 28.00 44,240.00 25.00 39,500.00 32.00 50,560.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 110. 32.50 3,575.00 30.00 3,300.00 40.00 4,400.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD TON 1,200. 56.00 67,200.00 57.50 69,000.00 70.00 84,000.00 13933B PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 75. 125.00 9,375.00 120.00 9,000.00 135.00 10,125.00 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 79. 125.00 9,875.00 125.00 9,875.00 150.00 11,850.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 530. 60.00 31,800.00 57.50 30,475.00 75.00 39,750.00 417. COLD PLANING BITUMINOUS SURFACES SY 200. 20.00 4,000.00 30.00 6,000.00 15.00 3,000.00 502. REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 255,000.00 255,000.00 400,000.00 400,000.00 150,000.00 150,000.00 503.201 COFFERDAMS U 1. 125,000.00 125,000.00 200,000.00 200,000.00 150,000.00 150,000.00 503.202 COFFERDAMS U 1. 125,000.00 125,000.00 200,000.00 200,000.00 150,000.00 150,000.00 503.301 COFFERDAMS WITH SHEETING LEFT-IN-PLACE U 1. 59,000.00 59,000.00 50,000.00 50,000.00 100,000.00 100,000.00 504.101 COMMON BRIDGE EXCAVATION CY 2,600. 12.00 31,200.00 25.00 65,000.00 10.00 26,000.00 508. STRUCTURAL FILL CY 690. 40.00 27,600.00 50.00 34,500.00 33.00 22,770.00 510.1 PILE DRIVING EQUIPMENT U 1. 35,000.00 35,000.00 10,000.00 10,000.00 100,000.00 100,000.00 510.11 MOBILIZATION & DEMOBIL. OF PREBORING EQUIPMENT U 1. 25,000.00 25,000.00 25,000.00 25,000.00 20,000.00 20,000.00 510.602 PREBORING THROUGH SOIL FOR STEEL BEARING PILES LF 50. 250.00 12,500.00 850.00 42,500.00 250.00 12,500.00 510.603 PREBORING & CONCRETING ROCK SOCKET FOR STEEL BEARING PILES LF 40. 1,800.00 72,000.00 1,250.00 50,000.00 2,000.00 80,000.00 510.61 FURNISHING & DRIVING STEE BEARING PILES LB 45,990. .54 24,834.60 .22 10,117.80 1.75 80,482.50 510.65 DRIVING-POINTS FOR STEEL BEARING PILES EA 7. 200.00 1,400.00 150.00 1,050.00 150.00 1,050.00 520.0102 CONCRETE CLASS AA (QC/QA) (F) CY 167. 1,050.00 175,350.00 650.00 108,550.00 800.00 133,600.00 520.0302 CONCRETE CLASS AA, APPROACH SLABS (QC/QA) (F) CY 65. 450.00 29,250.00 250.00 16,250.00 250.00 16,250.00 520.12 CONCRETE CLASS A, ABOVE FOOTINGS (F) CY 73. 1,100.00 80,300.00 750.00 54,750.00 800.00 58,400.00 520.2109 CONCRETE CLASS B (MODIFIED), FOOTINGS (F) CY 160. 275.00 44,000.00 250.00 40,000.00 250.00 40,000.00 520.70026 CONCRETE BRIDGE DECK (QC/QA)(PANEL OPTION)(F) CY 600. 670.00 402,000.00 750.00 450,000.00 900.00 540,000.00 534.3 WATER REPELLENT (SILANE- SILOXANE) GAL 49. 50.00 2,450.00 100.00 4,900.00 60.00 2,940.00 536.11 EPOXY COATING FOR CONCRETE (F) SF 1,330. 8.00 10,640.00 10.00 13,300.00 5.00 6,650.00 537. CONCRETE SEALER (F) SF 3,625. .50 1,812.50 1.00 3,625.00 .70 2,537.50 538.2 BARRIER MEMBRANE, VERTICAL SURFACES (F) SY 26. 35.00 910.00 50.00 1,300.00 50.00 1,300.00 538.5 BARRIER MEMBRANE, WELDED BY TORCH (F) SY 1,390. 22.00 30,580.00 25.00 34,750.00 20.00 27,800.00 13933B PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 541.1 PVC WATERSTOPS, NH TYPE 1 (F) LF 71. 5.00 355.00 10.00 710.00 7.00 497.00 544.3 REINFORCING STEEL (CONTRACTOR DETAILED) LB 44,000. 1.05 46,200.00 1.00 44,000.00 1.10 48,400.00 544.31 REINFORCING STEEL, EPOXY COATED (CONTRACTOR DETAILED) LB 185,000. 1.10 203,500.00 1.25 231,250.00 1.00 185,000.00 547. SHEAR CONNECTORS (F) EA 2,524. 2.50 6,310.00 2.50 6,310.00 3.00 7,572.00 550.1 STRUCTURAL STEEL (F) LB 944,750. 1.39 1,313,202.50 1.50 1,417,125.00 1.48 1,398,230.00 550.210 BRIDGE SHOES (F) EA 15. 3,200.00 48,000.00 5,000.00 75,000.00 3,500.00 52,500.00 559.5 SILICONE JOINT SEALANT (F LF 310. 10.00 3,100.00 10.00 3,100.00 6.00 1,860.00 561.301 PREFABRICATED EXPANSION JOINT, FINGER JOINT (F) LF 52. 1,100.00 57,200.00 1,000.00 52,000.00 1,250.00 65,000.00 561.302 PREFABRICATED EXPANSION JOINT, FINGER JOINT (F) LF 43. 1,100.00 47,300.00 1,000.00 43,000.00 1,300.00 55,900.00 563.221 BRIDGE RAIL T2 WITH PROTECTIVE SCREENING (F) LF 428. 143.00 61,204.00 200.00 85,600.00 140.00 59,920.00 563.241 BRIDGE RAIL T4 WITH PROTECTIVE SCREENING (F) LF 422. 200.00 84,400.00 250.00 105,500.00 200.00 84,400.00 565.22 BRIDGE APPROACH RAIL T2 (F) LF 59. 120.00 7,080.00 130.00 7,670.00 125.00 7,375.00 565.24 BRIDGE APPROACH RAIL T4 (F) LF 59. 166.00 9,794.00 175.00 10,325.00 170.00 10,030.00 565.64 BRIDGE APPRACH RAIL, E U 3. 2,150.00 6,450.00 2,500.00 7,500.00 2,200.00 6,600.00 585.3 STONE FILL, CLASS C CY 40. 60.00 2,400.00 45.00 1,800.00 70.00 2,800.00 592.1 MECHANICALLY STABILIZED EARTH RETAINING WALL SF 7,200. 43.00 309,600.00 35.00 252,000.00 50.00 360,000.00 593.411 GEOTEXTILE; PERM CONTROL CL.1, NON-WOVEN SY 80. 4.00 320.00 5.00 400.00 2.50 200.00 603.00215 15" R.C. PIPE, 2000D LF 405. 42.00 17,010.00 45.00 18,225.00 65.00 26,325.00 603.36115 15" ALUMINIZED STEEL END SECTIONS EA 1. 340.00 340.00 300.00 300.00 270.00 270.00 603.36118 18" ALUMINIZED STEEL END SECTIONS EA 3. 380.00 1,140.00 350.00 1,050.00 400.00 1,200.00 603.44015 15" PIPE FOR SLOPE DRAIN (PLASTIC) LF 85. 37.00 3,145.00 37.00 3,145.00 75.00 6,375.00 604.0007 POLYETHYLENE LINER EA 5. 230.00 1,150.00 200.00 1,000.00 250.00 1,250.00 604.16 CATCH BASINS TYPE F U 5.2 2,200.00 11,440.00 2,000.00 10,400.00 2,200.00 11,440.00 604.4 RECONSTRUCTING/ADJUSTING CATCH BASIN & DROP INLET LF 5. 225.00 1,125.00 400.00 2,000.00 500.00 2,500.00 606.140 BEAM GUARDRAIL (STANDARD SECTION- WOOD POSTS) LF 2,550. 19.00 48,450.00 18.00 45,900.00 19.00 48,450.00 606.1403 BEAM GUARDRAIL (THRIE BEAM) INCLUDING TRANSITION SECTION LF 425. 28.00 11,900.00 28.00 11,900.00 28.00 11,900.00 606.1454 BEAM GUARDRAIL (TERM. UNIT TYPE EAGRT 50 FT.) U 2. 2,200.00 4,400.00 2,500.00 5,000.00 2,200.00 4,400.00 606.1455 BEAM GUARDRAIL (TERM. UNIT EAGRT 25 FT.) U 4. 1,700.00 6,800.00 2,000.00 8,000.00 7,000.00 28,000.00 606.147 BEAM GUARDRAIL (TERMINAL UNIT TYPE G-2) U 2. 500.00 1,000.00 500.00 1,000.00 1,200.00 2,400.00 13933B PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 760. 25.00 19,000.00 30.00 22,800.00 60.00 45,600.00 608.12 2" BITUMINOUS SIDEWALK (F) SY 310. 13.00 4,030.00 13.55 4,200.50 15.00 4,650.00 609.01 STRAIGHT GRANITE CURB LF 200. 15.00 3,000.00 24.00 4,800.00 27.00 5,400.00 609.5 RESET GRANITE CURB LF 570. 6.00 3,420.00 10.80 6,156.00 16.50 9,405.00 611.05206 6" CEMENT LINED DUCTILE IRON WATER PIPE , CL.52 LF 30. 50.00 1,500.00 53.00 1,590.00 130.00 3,900.00 611.05212 12" CEMENT LINED DUCTILE IRON WATER PIPE , CL.52 LF 290. 60.00 17,400.00 75.00 21,750.00 130.00 37,700.00 611.5002 2" SERVICE CONNECTION LF 20. 45.00 900.00 55.00 1,100.00 130.00 2,600.00 611.52007 3/4" CURB STOP EA 2. 230.00 460.00 125.00 250.00 250.00 500.00 611.70012 12" FITTING EA 6. 700.00 4,200.00 600.00 3,600.00 1,130.00 6,780.00 611.71006 6" GATE VALVE EA 1. 870.00 870.00 850.00 850.00 1,000.00 1,000.00 611.71012 12" GATE VALVE EA 2. 1,850.00 3,700.00 2,200.00 4,400.00 2,160.00 4,320.00 611.74 CHLORINE INJECTION TAP EA 1. 800.00 800.00 500.00 500.00 960.00 960.00 611.81 HYDRANTS EA 1. 2,600.00 2,600.00 3,500.00 3,500.00 3,600.00 3,600.00 611.819 RESET HYDRANT EA 1. 1,200.00 1,200.00 2,500.00 2,500.00 3,300.00 3,300.00 614.342 4" 2-DUCT STEEL CONDUIT LF 50. 30.00 1,500.00 31.00 1,550.00 50.00 2,500.00 614.3429 4 INCH 2-DUCT STEEL CONDUIT (BRIDGE) LF 427. 29.00 12,383.00 60.00 25,620.00 30.00 12,810.00 614.441 4 INCH SPLIT-SLEEVE CONDUIT LF 80. 24.00 1,920.00 22.00 1,760.00 25.00 2,000.00 614.522 MOLDED PULL BOX 13"X24" EA 10. 260.00 2,600.00 280.00 2,800.00 300.00 3,000.00 614.7314 3" PVC PLASTIC CONDUIT, SCHEDULE 40 LF 150. 6.00 900.00 8.00 1,200.00 10.00 1,500.00 614.74481 4" 4-DUCT PVC PLASTIC CONDUIT, SCHEDULE 80, CONCRETE ENCASED LF 115. 25.00 2,875.00 28.00 3,220.00 30.00 3,450.00 615.014 RELOCATING TRAFFIC SIGN, TYPE A U 1. 3,500.00 3,500.00 5,000.00 5,000.00 750.00 750.00 615.03 TRAFFIC SIGN TYPE C (F) SF 17.5 40.00 700.00 25.00 437.50 50.00 875.00 615.033 REMOVING TRAFFIC SIGN, TYPE C U 3. 200.00 600.00 10.00 30.00 120.00 360.00 615.034 RELOCATING TRAFFIC SIGN, TYPE C U 3. 250.00 750.00 75.00 225.00 120.00 360.00 615.06 TRAFFIC SIGN TYPE CC (F) SF 12.5 30.00 375.00 25.00 312.50 50.00 625.00 615.303 REMOVING BRIDGE MOUNTED TRAFFIC SIGN U 1. 4,000.00 4,000.00 1,000.00 1,000.00 5,000.00 5,000.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 305,000.00 305,000.00 305,000.00 305,000.00 305,000.00 305,000.00 618.7 FLAGGERS HR 700. 22.00 15,400.00 22.00 15,400.00 20.00 14,000.00 619.1 MAINTENANCE OF TRAFFIC U 1. 95,000.00 95,000.00 100,000.00 100,000.00 200,000.00 200,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 5. 25,000.00 125,000.00 10,000.00 50,000.00 15,000.00 75,000.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 40. 5.00 200.00 5.00 200.00 5.00 200.00 621.31 SINGLE DELINEATOR WITH POST EA 20. 32.00 640.00 32.00 640.00 35.00 700.00 622.1 STEEL WITNESS MARKERS EA 4. 29.00 116.00 29.00 116.00 33.00 132.00 13933B PAGE 5 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 622.2 CONCRETE BOUNDS EA 3. 250.00 750.00 275.00 825.00 300.00 900.00 622.4 STONE BOUNDS EA 3. 325.00 975.00 375.00 1,125.00 300.00 900.00 628.2 SAWED BITUMINOUS PAVEMENT LF 155. 2.00 310.00 3.00 465.00 7.00 1,085.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 20,400. .14 2,856.00 .10 2,040.00 .20 4,080.00 632.3118 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 18" LINE LF 25. 40.00 1,000.00 20.00 500.00 20.00 500.00 632.9104 OBLITERATE PAVEMENT MARKING, 4" LINE LF 2,500. .65 1,625.00 .40 1,000.00 .50 1,250.00 641. LOAM CY 70. 30.00 2,100.00 35.00 2,450.00 41.00 2,870.00 645.23 CHANNEL STABILIZATION (LOW VELOCITY) SY 885. 1.80 1,593.00 1.95 1,725.75 5.00 4,425.00 645.3 EROSION STONE TON 102. 34.00 3,468.00 40.00 4,080.00 53.00 5,406.00 645.51 HAY BALES FOR TEMPORARY EROSION CONTROL EA 230. 7.50 1,725.00 8.00 1,840.00 7.50 1,725.00 645.52 RYEGRASS FOR TEMPORARY EROSION CONTROL LB 105. 2.00 210.00 2.00 210.00 2.00 210.00 645.531 SILT FENCE LF 2,900. 2.50 7,250.00 3.25 9,425.00 3.00 8,700.00 645.7 STORM WATER POLLUTION PREVENTION PLAN U 1. 2,500.00 2,500.00 2,500.00 2,500.00 15,000.00 15,000.00 645.71 MONITORING SWPPP AND EROSION AND SEDIMENT CONTROLS HR 170. 60.00 10,200.00 70.00 11,900.00 50.00 8,500.00 646.3 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS A 2.5 1,400.00 3,500.00 1,400.00 3,500.00 1,400.00 3,500.00 647.1 HUMUS CY 1,100. 24.00 26,400.00 20.00 22,000.00 20.00 22,000.00 670.0451 CONSTRUCT AND REMOVE DETOUR U 1. 125,000.00 125,000.00 125,000.00 125,000.00 70,000.00 70,000.00 670.0452 CONSTRUCT AND REMOVE DETOUR U 1. 35,000.00 35,000.00 45,000.00 45,000.00 10,000.00 10,000.00 670.066 MAILBOX SUPPORT ASSEMBLIES EA 4. 200.00 800.00 150.00 600.00 300.00 1,200.00 670.101 TEMPORARY LIGHTING U 1. 2,000.00 2,000.00 2,000.00 2,000.00 5,000.00 5,000.00 670.95 TEMPORARY SAFETY FENCE LF 100. 3.50 350.00 7.50 750.00 15.00 1,500.00 671.6118 WATER MAIN, 18" DIRECTIONAL BORE LF 770. 350.00 269,500.00 350.00 269,500.00 320.00 246,400.00 692. MOBILIZATION U 1. 465,000.00 465,000.00 395,000.00 395,000.00 660,000.00 660,000.00 693. ON-THE-JOB TRAINING OF UNSKILLED WORKERS $ 1. 600.00 600.00 600.00 600.00 600.00 600.00 698.13 FIELD OFFICE TYPE C MON 20. 1,500.00 30,000.00 1,000.00 20,000.00 800.00 16,000.00 698.2 PHYSICAL TESTING LABORATORY MON 20. 1,000.00 20,000.00 500.00 10,000.00 250.00 5,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 814.11 TEMPORARY UTILITY SUPPORT (PIER) U 1. 5,000.00 5,000.00 1,000.00 1,000.00 5,000.00 5,000.00 814.12 TEMPORARY UTILITY SUPPORT (ABUTMENT A) U 1. 9,000.00 9,000.00 2,500.00 2,500.00 5,000.00 5,000.00 814.449 4 INCH 4-DUCT CONDUIT (BRIDGE) (SUPPLIED BY OTHERS) LF 426. 11.00 4,686.00 30.00 12,780.00 25.00 10,650.00 13933B PAGE 6 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 1008.7 ALTERATIONS AND ADDITIONS AS NEEDED - SITE CLEAN-UP $ 1. 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 1010.15 FUEL ADJUSTMENT $ 1. 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1010.41 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR CONCRETE $ 1. 32,000.00 32,000.00 32,000.00 32,000.00 32,000.00 32,000.00 $6,650,644.60 $6,817,321.05 $7,116,789.50