THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: CLAREMONT-NEWPORT MGS-STP-NHS-F-X-T-014-1(23), 10433 COUNTIES AND CODES: SULLIVAN 019 DATE BIDS OPEN: AUGUST 11, 2006 SCOPE OF WORK: ROADWAY AND BRIDGE REHABILITATION LOCATION: NH ROUTE 11/ OLD NEWPORT ROAD IN CLAREMONT AND KELLYVILLE BRIDGE OVER THE SUGAR RIVER IN NEWPORT COMPLETION DATE: SEPTEMBER 5, 2008 A R. S. AUDLEY INC 609 RT 3A, BOW, NH 03304 $12,133,272.80 B J. A. MCDONALD, INC. BOX 132, LYNDON CENTER, VT 05850 $12,299,070.45 C MORRILL CONSTRUCTION, INC. 190 HORSEMEADOW ROAD, PO BOX 400, N. HAVERHILL, NH 03774$12,537,538.15 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 201.01 CLEARING (F) HA .4 10,000.00 4,000.00 6,000.00 2,400.00 5,000.00 2,000.00 201.1 CLEARING AND GRUBBING (F) HA 4.8 15,000.00 72,000.00 20,000.00 96,000.00 28,950.00 138,960.00 201.21 REMOVING SMALL TREES EA 60. 125.00 7,500.00 350.00 21,000.00 165.00 9,900.00 201.22 REMOVING LARGE TREES EA 1. 250.00 250.00 1,000.00 1,000.00 2,500.00 2,500.00 202.31 FILL ABANDONED PIPE M3 55. 180.00 9,900.00 160.00 8,800.00 230.00 12,650.00 202.41 REMOVAL OF EXISTING PIPE 0-600 MM DIA. LM 2,400. 50.00 120,000.00 35.00 84,000.00 31.17 74,808.00 202.5 REMOVAL OF CATCH BASINS, DROP INLETS, AND MANHOLES EA 30. 300.00 9,000.00 250.00 7,500.00 450.00 13,500.00 202.7 REMOVAL OF GUARDRAIL (F) LM 850. 6.50 5,525.00 14.00 11,900.00 14.30 12,155.00 203.1 COMMON EXCAVATION M3 142,500. 9.00 1,282,500.00 10.25 1,460,625.00 10.53 1,500,525.00 203.17 PREPARE SURFACE FOR PAVEMENT M2 28,600. 3.75 107,250.00 2.00 57,200.00 3.29 94,094.00 203.2 ROCK EXCAVATION M3 50. 90.00 4,500.00 55.00 2,750.00 130.80 6,540.00 203.35 HANDLING OF EXCAVATED, CONTAMINATED SOILS M3 100. 12.50 1,250.00 70.00 7,000.00 725.00 72,500.00 203.5554 GUARDRAIL 15.2M EAGRT PLATFORM U 22. 825.00 18,150.00 2,200.00 48,400.00 2,200.00 48,400.00 203.5555 G PLATFORM U 5. 500.00 2,500.00 1,600.00 8,000.00 1,200.00 6,000.00 203.6 EMBANKMENT-IN-PLACE (F) M3 56,000. 9.00 504,000.00 4.00 224,000.00 5.89 329,840.00 206.1 COMMON STRUCTURE EXCAVATION M3 4,550. 13.50 61,425.00 20.00 91,000.00 26.16 119,028.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY M3 45. 40.00 1,800.00 20.00 900.00 36.62 1,647.90 206.2 ROCK STRUCTURE EXCAVATION M3 20. 100.00 2,000.00 100.00 2,000.00 156.95 3,139.00 207.1 COMMON CHANNEL EXCAVATION M3 200. 42.00 8,400.00 15.00 3,000.00 18.00 3,600.00 10433 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 207.3 UNCLASSIFIED CHANNEL EXCAVATION M3 110. 42.00 4,620.00 31.00 3,410.00 32.00 3,520.00 209.1 GRANULAR BACKFILL M3 300. 35.00 10,500.00 44.00 13,200.00 35.00 10,500.00 209.201 GRANULAR BACKFILL (BRIDGE) (F) M3 680. 45.00 30,600.00 45.00 30,600.00 45.00 30,600.00 211.11 VIBRATION MONITORING SERVICES HR 20. 75.00 1,500.00 120.00 2,400.00 125.00 2,500.00 214. FINE GRADING U 1. 150,000.00 150,000.00 435,000.00 435,000.00 220,000.00 220,000.00 304.1 SAND (F) M3 28,600. 25.00 715,000.00 16.00 457,600.00 26.16 748,176.00 304.2 GRAVEL (F) M3 30,400. 33.50 1,018,400.00 21.00 638,400.00 30.08 914,432.00 304.3 CRUSHED GRAVEL (F) M3 26,750. 33.50 896,125.00 28.00 749,000.00 37.28 997,240.00 304.31 CRUSHED GRAVEL FOR SHIMMING M3 250. 36.00 9,000.00 28.00 7,000.00 44.47 11,117.50 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING T 360. 32.00 11,520.00 20.00 7,200.00 98.11 35,319.60 304.35 CRUSHED GRAVEL FOR DRIVES M3 2,100. 37.00 77,700.00 29.00 60,900.00 47.09 98,889.00 403.11002 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (QC/QA TIER 2) T 27,283. 64.00 1,746,112.00 65.00 1,773,395.00 67.20 1,833,417.60 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD T 925. 100.00 92,500.00 100.00 92,500.00 107.14 99,104.50 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 25 MM BASE COURSE (F) T 5. 250.00 1,250.00 250.00 1,250.00 262.52 1,312.60 403.99 TEMPORARY BITUMINOUS PAVEMENT T 4,750. 64.00 304,000.00 65.00 308,750.00 67.24 319,390.00 417. COLD PLANING BITUMINOUS SURFACES (F) M2 360. 30.00 10,800.00 30.00 10,800.00 39.47 14,209.20 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 62,000.00 62,000.00 15,000.00 15,000.00 15,750.00 15,750.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 28,000.00 28,000.00 45,000.00 45,000.00 47,250.00 47,250.00 503.201 COFFERDAMS U 1. 108,000.00 108,000.00 140,000.00 140,000.00 147,000.00 147,000.00 503.202 COFFERDAMS U 1. 104,000.00 104,000.00 70,000.00 70,000.00 73,500.00 73,500.00 504.1 COMMON BRIDGE EXCAVATION (F) M3 280. 33.00 9,240.00 39.00 10,920.00 42.00 11,760.00 508. STRUCTURAL FILL M3 157. 55.00 8,635.00 57.00 8,949.00 60.00 9,420.00 512.0101 PREPARATION FOR CONCRETE REPAIRS, CLASS I M2 10. 700.00 7,000.00 500.00 5,000.00 525.00 5,250.00 512.0201 PREPARATION FOR CONCRETE REPAIRS, CLASS II M2 4. 975.00 3,900.00 650.00 2,600.00 683.00 2,732.00 520.0001 PRECAST CONCRETE BOX CULVERT (CLASS AAA) U 1. 47,000.00 47,000.00 51,000.00 51,000.00 53,550.00 53,550.00 520.01 CONCRETE CLASS AA M3 40. 1,425.00 57,000.00 1,100.00 44,000.00 1,155.00 46,200.00 520.1 CONCRETE CLASS A M3 85. 1,600.00 136,000.00 850.00 72,250.00 980.96 83,381.60 520.12 CONCRETE CLASS A ABOVE FOOTINGS (F) M3 167. 1,015.00 169,505.00 865.00 144,455.00 909.00 151,803.00 520.213 CONCRETE CLASS B, FOOTINGS (ON SOIL) (F) M3 150. 715.00 107,250.00 530.00 79,500.00 557.00 83,550.00 10433 PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 534.1 WATER REPELLENT (LINSEED OIL) L 80. 12.00 960.00 9.00 720.00 9.45 756.00 534.3 WATER REPELLENT (SILANE- SILOXANE) L 27. 20.00 540.00 19.00 513.00 19.95 538.65 538.1 BARRIER MEMBRANE (F) M2 68. 42.00 2,856.00 51.00 3,468.00 53.52 3,639.36 538.2 BARRIER MEMBRANE, VERTICAL SURFACES (F) M2 55. 48.00 2,640.00 45.00 2,475.00 53.00 2,915.00 538.5 BARRIER MEMBRANE, WELDED BY TORCH (F) M2 100. 67.00 6,700.00 68.00 6,800.00 69.73 6,973.00 541.4 PVC WATERSTOPS, NH TYPE 4 (F) LM 4. 30.00 120.00 38.00 152.00 40.00 160.00 544. REINFORCING STEEL (F) KG 10,376. 2.30 23,864.80 2.20 22,827.20 2.26 23,449.76 544.1 REINFORCING STEEL (ROADWAY) KG 2,000. 4.30 8,600.00 3.00 6,000.00 3.15 6,300.00 544.11 REINFORCING STEEL MECHANICAL CONNECTORS (F KG 25. 14.00 350.00 20.00 500.00 21.00 525.00 544.2 REINFORCING STEEL, EPOXY COATED (F) KG 3,375. 2.40 8,100.00 2.50 8,437.50 2.57 8,673.75 544.21 REINFORCING STEEL, EPOXY COATED MECHANICAL CONNECTORS (F) KG 73. 15.00 1,095.00 16.00 1,168.00 16.80 1,226.40 563.3 BRIDGE RAIL T101 (F) LM 12. 400.00 4,800.00 125.00 1,500.00 413.71 4,964.52 570.4 MORTAR RUBBLE MASONRY (F) M3 175. 525.00 91,875.00 450.00 78,750.00 653.98 114,446.50 571. POINTING STONE MASONRY U 1. 500.00 500.00 3,200.00 3,200.00 1,100.00 1,100.00 584. ROCK FILLED GALVANIZED WIRE MESH BOXES M3 12. 450.00 5,400.00 300.00 3,600.00 360.00 4,320.00 585.2 STONE FILL, CLASS B M3 800. 55.00 44,000.00 55.00 44,000.00 45.00 36,000.00 585.21 STONE FILL, CLASS B (BRIDGE) M3 320. 57.00 18,240.00 50.00 16,000.00 65.40 20,928.00 585.3 STONE FILL, CLASS C M3 1,500. 57.00 85,500.00 55.00 82,500.00 47.74 71,610.00 585.4 STONE FILL, CLASS D M3 5. 78.00 390.00 75.00 375.00 100.00 500.00 593.421 GEOTEXTILE; PERM CONTROL CL.2, NON-WOVEN M2 8,775. 5.00 43,875.00 3.00 26,325.00 3.59 31,502.25 603.00204 375 MM R.C. PIPE, CLASS III LM 225. 145.00 32,625.00 300.00 67,500.00 288.71 64,959.75 603.00205 450 MM R.C. PIPE, CLASS III LM 265. 150.00 39,750.00 290.00 76,850.00 296.59 78,596.35 603.00206 600 MM R.C. PIPE, CLASS III LM 155. 175.00 27,125.00 340.00 52,700.00 321.52 49,835.60 603.00208 750 MM R.C. PIPE, CLASS III LM 60. 215.00 12,900.00 380.00 22,800.00 355.15 21,309.00 603.00209 900 MM R.C. PIPE, CLASS III LM 95. 260.00 24,700.00 400.00 38,000.00 387.14 36,778.30 603.00214 1350 MM R.C. PIPE, CLASS III LM 35. 500.00 17,500.00 820.00 28,700.00 590.55 20,669.25 603.11003 300 MM CORR. STEEL PIPE, 1.63 MM LM 105. 120.00 12,600.00 125.00 13,125.00 150.92 15,846.60 603.11004 375 MM CORR. STEEL PIPE, 1.63 MM LM 40. 125.00 5,000.00 135.00 5,400.00 154.20 6,168.00 603.30104 375 MM R.C. END SECT. EA 3. 700.00 2,100.00 1,000.00 3,000.00 1,050.00 3,150.00 10433 PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 603.30106 600 MM R.C. END SECT. EA 1. 900.00 900.00 1,550.00 1,550.00 1,250.00 1,250.00 603.34103 300 MM STEEL END SECTION EA 16. 170.00 2,720.00 270.00 4,320.00 600.00 9,600.00 603.34104 375 MM STEEL END SECTION EA 4. 185.00 740.00 350.00 1,400.00 620.00 2,480.00 603.34105 450 MM STEEL END SECTION EA 1. 205.00 205.00 500.00 500.00 640.00 640.00 603.49003 300 MM PIPE FOR SLOPE DRAIN. (CONTRACTORS OPTION) LM 80. 107.00 8,560.00 150.00 12,000.00 144.36 11,548.80 603.83109 900MM PLASTIC PIPE (CORR INTERIOR) LM 20. 310.00 6,200.00 250.00 5,000.00 298.56 5,971.20 603.83204 375 MM PLASTIC PIPE (SMOOTH INTERIOR) LM 1,950. 115.00 224,250.00 110.00 214,500.00 121.39 236,710.50 603.83205 450 MM PLASTIC PIPE (SMOOTH INTERIOR) LM 225. 125.00 28,125.00 125.00 28,125.00 220.64 49,644.00 603.83206 600 MM PLASTIC PIPE (SMOOTH INTERIOR) LM 110. 150.00 16,500.00 160.00 17,600.00 244.42 26,886.20 603.85204 375 MM CORR. POLYETHYLENE END SECTION EA 13. 215.00 2,795.00 290.00 3,770.00 575.00 7,475.00 603.85205 450 MM CORR. POLYETHYLENE END SECTION EA 1. 250.00 250.00 395.00 395.00 652.00 652.00 603.85206 600 MM CORR. POLYETHYLENE END SECTION EA 2. 285.00 570.00 565.00 1,130.00 605.00 1,210.00 603.86915 1500 MM SOLID WALL POLYETHYLENE PIPE LINER LM 110. 2,200.00 242,000.00 3,000.00 330,000.00 1,804.46 198,490.60 603.8699 CONTROLLED DENSITY FILL CONCRETE M3 50. 380.00 19,000.00 600.00 30,000.00 359.69 17,984.50 604.0007 POLYETHYLENE LINER EA 50. 200.00 10,000.00 260.00 13,000.00 175.00 8,750.00 604.12 CATCH BASINS TYPE B U 35. 1,950.00 68,250.00 1,600.00 56,000.00 2,000.00 70,000.00 604.1215 CATCH BASINS TYPE B, 1.5 M DIA U 1. 2,950.00 2,950.00 4,000.00 4,000.00 3,875.00 3,875.00 604.13 CATCH BASINS TYPE C U 6. 1,500.00 9,000.00 1,150.00 6,900.00 2,400.00 14,400.00 604.15 CATCH BASINS TYPE E U 45. 2,100.00 94,500.00 1,700.00 76,500.00 1,950.00 87,750.00 604.1515 CATCH BASINS TYPE E, 1.5 M DIA U 15. 3,050.00 45,750.00 2,400.00 36,000.00 2,900.00 43,500.00 604.16 CATCH BASINS TYPE F U 6. 2,075.00 12,450.00 1,850.00 11,100.00 2,400.00 14,400.00 604.1615 CATCH BASINS TYPE F, 1.5 M DIA U 2. 3,025.00 6,050.00 2,700.00 5,400.00 3,350.00 6,700.00 604.22 DROP INLETS TYPE B U 2. 1,500.00 3,000.00 1,250.00 2,500.00 1,700.00 3,400.00 604.242 DROP INLETS TYPE D-B U 8. 1,350.00 10,800.00 1,200.00 9,600.00 1,800.00 14,400.00 604.26 DROP INLETS TYPE F U 4. 1,600.00 6,400.00 1,350.00 5,400.00 1,850.00 7,400.00 604.3224 DRAINAGE MANHOLES, 2.4 M DIA U 2. 10,500.00 21,000.00 9,500.00 19,000.00 12,000.00 24,000.00 604.4 RECONSTRUCTING/ADJUSTING CATCH BASIN & DROP INLET LM 2. 675.00 1,350.00 800.00 1,600.00 328.08 656.16 604.85 WATER REPELLENT FOR EXISTING CB'S AND DI'S EA 2. 260.00 520.00 150.00 300.00 500.00 1,000.00 605.79 UNDERDRAIN FLUSHING BASINS EA 5. 550.00 2,750.00 460.00 2,300.00 500.00 2,500.00 605.82221 600 MM AGGRE. UND TYPE 2, WITH OPTION PIPE LM 220. 110.00 24,200.00 110.00 24,200.00 196.85 43,307.00 605.915 150 MM PIPE UND.(CONTRACT ORS OPTION) LM 2,170. 68.00 147,560.00 55.00 119,350.00 95.14 206,453.80 10433 PAGE 5 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 606.140 BEAM GUARDRAIL (STANDARD SECTION- WOOD POSTS) LM 2,500. 55.00 137,500.00 54.00 135,000.00 55.97 139,925.00 606.141 BEAM GUARDRAIL (CURVED W/CRT POSTS) LM 65. 60.00 3,900.00 59.00 3,835.00 61.94 4,026.10 606.1454 BEAM GUARDRAIL (TERMINAL UNIT EAGRT, 50 FT.) U 22. 1,950.00 42,900.00 2,000.00 44,000.00 2,100.00 46,200.00 606.1455 BEAM GUARDRAIL (TERMINAL UNIT EAGRT, 25 FT.) U 5. 1,800.00 9,000.00 1,850.00 9,250.00 1,942.50 9,712.50 606.147 BEAM GUARDRAIL (TERMINAL UNIT TYPE G-2) U 4. 560.00 2,240.00 550.00 2,200.00 577.50 2,310.00 606.1485 BEAM GUARDRAIL (BRIDGE APPROACH UNIT) U 4. 1,150.00 4,600.00 1,200.00 4,800.00 126.00 504.00 606.1496 BEAM GUARDRAIL TERMINAL UNIT E-2 LM 175. 85.00 14,875.00 85.00 14,875.00 86.09 15,065.75 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LM 1,200. 90.00 108,000.00 145.00 174,000.00 59.06 70,872.00 606.84 ANCHOR FOR CURVED GUARD- RAIL W/CRT POSTS U 9. 1,050.00 9,450.00 1,100.00 9,900.00 1,155.00 10,395.00 607.5442 ORNAMENTAL ALUMINUM FENCE LM 50. 150.00 7,500.00 165.00 8,250.00 172.21 8,610.50 608.210 100 MM CONCRETE SIDEWALK (F) M2 16. 60.00 960.00 60.00 960.00 119.60 1,913.60 609.01 STRAIGHT GRANITE CURB LM 360. 50.00 18,000.00 52.00 18,720.00 68.90 24,804.00 609.811 BITUMINOUS CURB TYPE B (100 MM REVEAL) LM 715. 11.00 7,865.00 11.50 8,222.50 12.14 8,680.10 609.930 SPECIAL STRAIGHT GRANITE CURB (300 MM REVEAL) LM 145. 125.00 18,125.00 190.00 27,550.00 246.06 35,678.70 614.512 CONCRETE PULL BOX 450 MM EA 2. 400.00 800.00 400.00 800.00 500.00 1,000.00 614.70814 75 MM PVC PLASTIC CONDUIT SCHEDULE 40 LM 45. 30.00 1,350.00 30.00 1,350.00 29.40 1,323.00 615.022 TRAFFIC SIGN TYPE B, BREAKAWAY MOUNTS (F) M2 2. 1,000.00 2,000.00 1,200.00 2,400.00 1,260.57 2,521.14 615.03 TRAFFIC SIGN TYPE C (F) M2 15.6 400.00 6,240.00 395.00 6,162.00 415.01 6,474.16 615.034 RELOCATING TRAFFIC SIGN, TYPE C U 9. 200.00 1,800.00 155.00 1,395.00 163.00 1,467.00 615.05 TRAFFIC SIGN TYPE BB (F) M2 .2 400.00 80.00 600.00 120.00 630.29 126.06 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 85,000.00 85,000.00 85,000.00 85,000.00 85,000.00 85,000.00 618.7 FLAGGERS HR 2,850. 17.00 48,450.00 22.00 62,700.00 26.00 74,100.00 619.1 MAINTENANCE OF TRAFFIC U 1. 150,000.00 150,000.00 315,000.00 315,000.00 200,000.00 200,000.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 2. 19,500.00 39,000.00 15,000.00 30,000.00 12,000.00 24,000.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 135. 4.00 540.00 4.00 540.00 4.20 567.00 621.31 SINGLE DELINEATOR WITH POST EA 250. 25.00 6,250.00 27.00 6,750.00 28.35 7,087.50 622.1 STEEL WITNESS MARKERS EA 140. 25.00 3,500.00 25.00 3,500.00 26.25 3,675.00 622.2 CONCRETE BOUNDS EA 70. 250.00 17,500.00 250.00 17,500.00 262.50 18,375.00 625.22 CONCRETE LIGHT POLE BASES, TYPE B (FOR HIGH- WAY LIGHTING) EA 1. 550.00 550.00 600.00 600.00 683.00 683.00 10433 PAGE 6 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 625.52 LIGHT POLE (HIGHWAY) U 1. 2,200.00 2,200.00 2,000.00 2,000.00 2,520.00 2,520.00 628.1 SAWED CONCRETE PAVEMENT LM 5. 50.00 250.00 30.00 150.00 328.08 1,640.40 628.2 SAWED BITUMINOUS PAVEMENT LM 5,350. 6.50 34,775.00 3.50 18,725.00 14.76 78,966.00 632.0110 RETROREFLECTIVE PAINT PAVEMENT MARKING, 100 MM LINE LM 144,300. .40 57,720.00 .40 57,720.00 .43 62,049.00 632.0145 RETROREFLECTIVE PAINT PAVEMENT MARKING, 450 MM LINE LM 25. 5.00 125.00 7.00 175.00 7.35 183.75 632.02 RETROREFLECTIVE PAINT PAVEMENT MARKING, SYMBOL OR WORD M2 25. 28.00 700.00 33.00 825.00 34.65 866.25 632.1110 PREFORMED RETROREFLECTIVE TAPE, TYPE I (REMOVABLE) 100 MM LINE LM 2,525. 4.50 11,362.50 4.25 10,731.25 4.59 11,589.75 632.3145 RETROREFLECT. THERMOPLAS. PAVE. MARKING 450 MM LIN LM 25. 12.00 300.00 13.00 325.00 13.65 341.25 632.32 RETROREFLECT. THERMOPLAS. PAVEMENT MARKING, SYMBOL OR WORD M2 25. 55.00 1,375.00 64.00 1,600.00 67.20 1,680.00 632.9110 OBLITERATE PAVEMENT MARKING, 100 MM LINE LM 23,900. 1.20 28,680.00 1.15 27,485.00 1.38 32,982.00 641. LOAM M3 4,150. 25.00 103,750.00 31.00 128,650.00 44.47 184,550.50 645.21 SLOPE STABILIZATION (2:1 OR FLATTER) M2 3,000. 1.80 5,400.00 1.75 5,250.00 3.59 10,770.00 645.23 CHANNEL STABILIZATION (LOW VELOCITY) M2 3,650. 2.00 7,300.00 2.00 7,300.00 3.59 13,103.50 645.3 EROSION STONE T 2,500. 25.00 62,500.00 40.00 100,000.00 33.07 82,675.00 645.51 HAY BALES FOR TEMPORARY EROSION CONTROL EA 600. 7.50 4,500.00 10.00 6,000.00 8.00 4,800.00 645.531 SILT FENCE LM 5,500. 8.50 46,750.00 8.00 44,000.00 9.84 54,120.00 645.7 STORM WATER POLLUTION PREVENTION PLAN U 1. 3,500.00 3,500.00 15,000.00 15,000.00 4,400.00 4,400.00 645.71 MONITORING SWPPP AND EROSION AND SEDIMENT CONTROL HR 260. 70.00 18,200.00 90.00 23,400.00 82.50 21,450.00 646.3 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS HA 14. 3,500.00 49,000.00 4,000.00 56,000.00 6,177.61 86,486.54 647.1 HUMUS M3 9,100. 20.00 182,000.00 16.00 145,600.00 13.08 119,028.00 670.0451 CONSTRUCT AND REMOVE TEMPORARY WIDENING U 1. 250,000.00 250,000.00 32,000.00 32,000.00 50,000.00 50,000.00 670.066 MAILBOX SUPPORT ASSEMBLIES EA 30. 200.00 6,000.00 200.00 6,000.00 210.00 6,300.00 670.101 TEMPORARY LIGHTING U 1. 22,000.00 22,000.00 23,000.00 23,000.00 25,150.00 25,150.00 670.95 TEMPORARY SAFETY FENCE LM 65. 8.50 552.50 15.00 975.00 13.12 852.80 692. MOBILIZATION U 1. 490,000.00 490,000.00 1,200,000.00 1,200,000.00 300,000.00 300,000.00 693. ON-THE-JOB TRAINING OF UNSKILLED WORKERS $ 1. 1,200.00 1,200.00 1,200.00 1,200.00 1,200.00 1,200.00 698.12 FIELD OFFICE TYPE B MON 16. 1,725.00 27,600.00 2,200.00 35,200.00 1,200.00 19,200.00 698.2 PHYSICAL TESTING LABORATORY MON 16. 900.00 14,400.00 1,000.00 16,000.00 750.00 12,000.00 10433 PAGE 7 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1002.1 REPAIRS OR REPLACEMENTS AS NEEDED $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1009.1 PROJECT HEALTH AND SAFETY PLAN $ 1. 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00 1009.2 TREATMENT OR DISPOSAL OF CONTAMINATED SOIL GROUNDWATER $ 1. 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 1010.15 FUEL ADJUSTMENT $ 1. 70,000.00 70,000.00 70,000.00 70,000.00 70,000.00 70,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 1010.3 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR ASPHALT $ 1. 82,000.00 82,000.00 82,000.00 82,000.00 82,000.00 82,000.00 $12,133,272.80 $12,299,070.45 $12,537,538.15