THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: MANCHESTER A000 (320), 10622-C MANCHESTER X-A000 (294), 14025-C COUNTIES AND CODES: HILLSBOROUGH 011 DATE BIDS OPEN: JUNE 29, 2005 SCOPE OF WORK: ROAD AND BRIDGE IMPROVEMENTS LOCATION: EXIT 5 INTERCHANGE ALONG I-293 AND GRANITE STREET CORRIDORS COMPLETION DATE: MAY 30, 2008 A THE MIDDLESEX CORPORATION ONE SPECTACLE POND ROAD, LITTLETON, MA 01460 $28,687,750.00 B REED & REED INC P O BOX 370, WOOLWICH, ME 04579 $28,768,567.27 C R.S. AUDLEY, INC. 609 ROUTE 3A, BOW, NH 03304 $28,984,650.45 D WEAVER BROS. CONST. CO., INC. P.O. BOX 132C CONCORD, NH 03302 $30,266,492.55 E E. D. SWETT, INC. 8 INDUSTRIAL PARK DR., CONCORD, NH 03301 $30,875,185.00 F PARK CONSTRUCTION CORP P O BOX 600 FITZWILLIAM, NH 03447 $32,528,829.91 G R. ZOPPO CORP. 160 OLD MAPLE STREET, STOUGHTON, MA 02072 $34,343,677.61 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 201.1 CLEARING AND GRUBBING (F) A 1.7 20,000.00 34,000.00 10,000.00 17,000.00 10,000.00 17,000.00 201.21 REMOVING SMALL TREES EA 6. 300.00 1,800.00 400.00 2,400.00 375.00 2,250.00 201.22 REMOVING LARGE TREES EA 2. 1,200.00 2,400.00 1,000.00 2,000.00 750.00 1,500.00 202.201 DEMOLISHING BUILDINGS U 1. 120,000.00 120,000.00 40,000.00 40,000.00 30,000.00 30,000.00 202.31 FILL ABANDONED PIPE CY 9. 200.00 1,800.00 400.00 3,600.00 225.00 2,025.00 202.41 REMOVAL OF EXISTING PIPE 0-24" DIAMETER LF 199. 16.00 3,184.00 15.00 2,985.00 16.50 3,283.50 202.5 REMOVAL OF CATCH BASINS, DROP INLETS, AND MANHOLES EA 31. 500.00 15,500.00 400.00 12,400.00 250.00 7,750.00 202.6 CURB REMOVAL FOR STORAGE LF 5,525. 3.00 16,575.00 2.00 11,050.00 2.50 13,812.50 202.7 REMOVAL OF GUARDRAIL (F) LF 13,800. 4.00 55,200.00 2.00 27,600.00 2.25 31,050.00 202.9 REMOVAL OF FUEL TANKS U 1. 40,000.00 40,000.00 35,000.00 35,000.00 8,000.00 8,000.00 203.1 COMMON EXCAVATION CY 67,600. 7.00 473,200.00 8.50 574,600.00 9.50 642,200.00 203.2 ROCK EXCAVATION CY 340. 75.00 25,500.00 25.00 8,500.00 35.00 11,900.00 203.35 HANDLING EXCAVATED, CONTAMINATED SOIL CY 22,245. 4.00 88,980.00 7.00 155,715.00 9.50 211,327.50 203.37 SEGREGATING AND REHANDLING, NON-CONTAMINATED SOIL CY 800. 10.00 8,000.00 15.00 12,000.00 7.50 6,000.00 10622-C PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 203.6 EMBANKMENT-IN-PLACE (F) CY 51,536. 6.00 309,216.00 6.00 309,216.00 11.00 566,896.00 203.62 EMBANKMENT-IN-PLACE, REPLACEMENT MATERIAL CY 2,900. 16.00 46,400.00 15.00 43,500.00 12.00 34,800.00 206.1 COMMON STRUCTURE EXCAVATION CY 1,650. 12.00 19,800.00 20.00 33,000.00 12.00 19,800.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 100. 64.00 6,400.00 50.00 5,000.00 34.00 3,400.00 206.2 ROCK STRUCTURE EXCAVATION CY 160. 68.00 10,880.00 125.00 20,000.00 75.00 12,000.00 207.3 UNCLASSIFIED CHANNEL EXCAVATION CY 2,108. 12.00 25,296.00 20.00 42,160.00 12.00 25,296.00 209.1 GRANULAR BACKFILL CY 165. 26.00 4,290.00 35.00 5,775.00 27.00 4,455.00 209.2 GRANULAR BACKFILL (BRIDGE) CY 65,185. 16.00 1,042,960.00 30.00 1,955,550.00 28.00 1,825,180.00 209.2014 GRANULAR BACKFILL (COARSE AGGREGATE) CY 3,521. 20.00 70,420.00 35.00 123,235.00 31.00 109,151.00 209.3 GRANULAR BACKFILL (SAND) CY 118. 50.00 5,900.00 35.00 4,130.00 27.00 3,186.00 209.4 GRANULAR BACKFILL (GRAV) CY 110. 34.00 3,740.00 35.00 3,850.00 27.00 2,970.00 210.62 GROUNDWATER OBSERVATION WELL (DRILLED) LF 192. 80.00 15,360.00 32.00 6,144.00 42.00 8,064.00 210.7 PROTECTIVE CASING WITH CAP AND LOCK EA 12. 80.00 960.00 150.00 1,800.00 500.00 6,000.00 214. FINE GRADING U 1. 150,000.00 150,000.00 150,000.00 150,000.00 130,000.00 130,000.00 214.1 FINE GRADING U 1. 40,000.00 40,000.00 90,000.00 90,000.00 80,000.00 80,000.00 304.1 SAND (F) CY 19,687. 19.00 374,053.00 17.00 334,679.00 13.00 255,931.00 304.2 GRAVEL (F) CY 18,321. 18.00 329,778.00 18.00 329,778.00 24.00 439,704.00 304.3 CRUSHED GRAVEL (F) CY 24,585. 23.00 565,455.00 20.00 491,700.00 24.00 590,040.00 304.31 CRUSHED GRAVEL FOR SHIMMING CY 500. 24.00 12,000.00 30.00 15,000.00 26.00 13,000.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 150. 32.00 4,800.00 30.00 4,500.00 26.00 3,900.00 403.1105 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (SUPERPAVE) TON 27,905. 46.00 1,283,630.00 45.00 1,255,725.00 41.75 1,165,033.75 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 670. 75.00 50,250.00 90.00 60,300.00 80.00 53,600.00 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 334. 50.00 16,700.00 75.00 25,050.00 75.00 25,050.00 403.98 HOT BITUMINOUS CONCRETE LEVELING, MACHINE METHOD TON 160. 70.00 11,200.00 70.00 11,200.00 55.00 8,800.00 403.989 HOT BITUMINOUS CONCRETE LEVELING, MACH. METHOD (NIGHT) TON 175. 70.00 12,250.00 70.00 12,250.00 60.00 10,500.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 3,450. 62.00 213,900.00 52.00 179,400.00 50.00 172,500.00 411.1 HOT BITUMINOUS CONCRETE LEVELING COURSE TON 225. 70.00 15,750.00 70.00 15,750.00 60.00 13,500.00 413.1 HOT-POURED CRACK SEALANT LB 8,250. 3.00 24,750.00 2.00 16,500.00 1.50 12,375.00 417. COLD PLANING BITUMINOUS SURFACES (F) SY 5,317. 3.20 17,014.40 5.00 26,585.00 4.00 21,268.00 417.19 COLD PLANING BITUMINOUS SURFACES (NIGHT) (F) SY 4,650. 5.20 24,180.00 6.00 27,900.00 5.00 23,250.00 10622-C PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 100,000.00 100,000.00 275,000.00 275,000.00 175,000.00 175,000.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 200,000.00 200,000.00 75,000.00 75,000.00 60,000.00 60,000.00 503.201 COFFERDAMS U 1. 60,000.00 60,000.00 40,000.00 40,000.00 33,000.00 33,000.00 503.202 COFFERDAMS U 1. 120,000.00 120,000.00 50,000.00 50,000.00 65,000.00 65,000.00 503.203 COFFERDAMS U 1. 100,000.00 100,000.00 50,000.00 50,000.00 65,000.00 65,000.00 503.204 COFFERDAMS U 1. 180,000.00 180,000.00 325,000.00 325,000.00 190,000.00 190,000.00 503.205 COFFERDAMS U 1. 25,000.00 25,000.00 65,000.00 65,000.00 28,000.00 28,000.00 503.206 COFFERDAMS U 1. 25,000.00 25,000.00 65,000.00 65,000.00 500.00 500.00 503.207 COFFERDAMS U 1. 25,000.00 25,000.00 65,000.00 65,000.00 28,000.00 28,000.00 503.208 COFFERDAMS U 1. 25,000.00 25,000.00 65,000.00 65,000.00 500.00 500.00 503.209 COFFERDAMS U 1. 65,000.00 65,000.00 750,000.00 750,000.00 41,000.00 41,000.00 503.210 COFFERDAMS U 1. 150,000.00 150,000.00 275,000.00 275,000.00 145,000.00 145,000.00 503.211 COFFERDAMS U 1. 1.00 1.00 50,000.00 50,000.00 24,000.00 24,000.00 503.212 COFFERDAMS U 1. 90,000.00 90,000.00 750,000.00 750,000.00 126,000.00 126,000.00 504.101 COMMON BRIDGE EXCAVATION CY 43,377. 3.50 151,819.50 11.00 477,147.00 12.00 520,524.00 504.2 ROCK BRIDGE EXCAVATION CY 644. 65.00 41,860.00 100.00 64,400.00 61.00 39,284.00 508. STRUCTURAL FILL CY 1,250. 28.00 35,000.00 30.00 37,500.00 26.00 32,500.00 510.11 PILE DRIVING EQUIPMENT (MINI-PILES) U 1. 50,000.00 50,000.00 11,000.00 11,000.00 95,000.00 95,000.00 510.2 PILE LOADING TESTS EA 2. 30,000.00 60,000.00 30,000.00 60,000.00 28,000.00 56,000.00 510.501 C-I-P CONCRETE PILES (DRILLED MINI-PILES) LF 24,985. 71.00 1,773,935.00 74.00 1,848,890.00 67.00 1,673,995.00 511.00 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 2,276. 9.00 20,484.00 4.00 9,104.00 9.00 20,484.00 511.02 PREPARATION FOR PARTIAL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 569. 116.00 66,004.00 250.00 142,250.00 165.00 93,885.00 511.03 PREPARATION FOR FULL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 114. 380.00 43,320.00 700.00 79,800.00 260.00 29,640.00 512.0201 PREPARATION FOR CONCRETE REPAIRS, CLASS II SY 50. 580.00 29,000.00 425.00 21,250.00 740.00 37,000.00 520.01 CONCRETE CLASS AA CY 51. 1,000.00 51,000.00 1,700.00 86,700.00 500.00 25,500.00 520.0102 CONCRETE CLASS AA (QC/QA) (F) CY 3,212. 380.00 1,220,560.00 425.00 1,365,100.00 660.00 2,119,920.00 520.028 PRECAST CONCRETE ARCHITECTURAL PANELS U 1. 400,000.00 400,000.00 350,000.00 350,000.00 290,000.00 290,000.00 520.12 CONCRETE CLASS A, ABOVE FOOTINGS (F) CY 1,050. 380.00 399,000.00 450.00 472,500.00 380.00 399,000.00 520.2 CONCRETE CLASS B CY 210. 350.00 73,500.00 390.00 81,900.00 275.00 57,750.00 520.21 CONCRETE CLASS B, FOOTINGS (F) CY 2,750. 180.00 495,000.00 225.00 618,750.00 220.00 605,000.00 520.421 CONCRETE CLASS F, FLOWABLE FILL, EXCAVATABLE CY 52. 200.00 10,400.00 150.00 7,800.00 125.00 6,500.00 520.7002 CONCRETE BRIDGE DECK (QC/QA) (F) CY 780. 720.00 561,600.00 800.00 624,000.00 560.00 436,800.00 10622-C PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 532.1 ANTI-GRAFFITI COATING SF 6,230. 2.00 12,460.00 2.00 12,460.00 1.00 6,230.00 534.1 WATER REPELLENT (LINSEED OIL) GAL 20. 450.00 9,000.00 50.00 1,000.00 30.00 600.00 534.3 WATER REPELLENT (SILANE- SILOXANE) GAL 773. 84.00 64,932.00 65.00 50,245.00 45.00 34,785.00 536.11 EPOXY COATING FOR CONCRETE (F) SF 1,550. 13.00 20,150.00 8.00 12,400.00 9.00 13,950.00 537. CONCRETE SEALER (F) SF 6,500. 1.20 7,800.00 1.65 10,725.00 1.00 6,500.00 538.2 BARRIER MEMBRANE, VERTICAL SURFACES (F) SY 110. 65.00 7,150.00 30.00 3,300.00 30.00 3,300.00 538.3 BARRIER MEMBRANE, LIQUID SPRAY (F) SY 3,725. 52.00 193,700.00 51.00 189,975.00 58.00 216,050.00 538.5 BARRIER MEMBRANE, WELDED BY TORCH (F) SY 5,456. 17.00 92,752.00 16.00 87,296.00 16.00 87,296.00 541.2 PVC WATERSTOPS, NH TYPE 2 (F) LF 113. 6.00 678.00 10.00 1,130.00 5.00 565.00 541.3 PVC WATERSTOPS, NH TYPE 3 (F) LF 55. 7.00 385.00 10.00 550.00 6.00 330.00 541.5 PVC WATERSTOPS, NH TYPE 5 (F) LF 119. 8.00 952.00 10.00 1,190.00 7.00 833.00 544. REINFORCING STEEL (F) LB 335,276. .85 284,984.60 .75 251,457.00 .90 301,748.40 544.1 REINFORCING STEEL (ROADWAY) LB 15,300. 1.00 15,300.00 .85 13,005.00 1.00 15,300.00 544.11 REINFORCING STEEL-MECH'L. CONNECTORS (F) LB 534. 1.00 534.00 6.00 3,204.00 3.50 1,869.00 544.2 REINFORCING STEEL, EPOXY COATED (F) LB 614,717. 1.10 676,188.70 1.02 627,011.34 .92 565,539.64 544.21 REINFORCING STEEL, EPOXY COATED-MECHANICAL CONNECTORS (F) LB 4,548. 1.00 4,548.00 6.00 27,288.00 3.50 15,918.00 547. SHEAR CONNECTORS (F) EA 7,137. 3.00 21,411.00 2.00 14,274.00 2.10 14,987.70 548.21 ELASTOMERIC BEARING ASSEMBLIES (F) EA 13. 4,800.00 62,400.00 2,000.00 26,000.00 4,000.00 52,000.00 550.1 STRUCTURAL STEEL (F) LB 2,017,267. 1.20 2,420,720.40 1.14 2,299,684.38 .98 1,976,921.66 550.2 BRIDGE SHOES (F) EA 13. 2,500.00 32,500.00 5,000.00 65,000.00 1,800.00 23,400.00 559.4 ELASTOMERIC PLUG TYPE EXPANSION JOINT (F) LF 410. 70.00 28,700.00 75.00 30,750.00 70.00 28,700.00 561.04 REHABILITATE EXPANSION JOINT U 1. 20,000.00 20,000.00 10,000.00 10,000.00 15,000.00 15,000.00 561.110 PREFABRICATED EXPANSION JOINT, TYPE A (F) LF 122. 330.00 40,260.00 300.00 36,600.00 375.00 45,750.00 563.22 BRIDGE RAIL T2 (F) LF 2,379. 100.00 237,900.00 85.00 202,215.00 89.00 211,731.00 563.223 BRIDGE RAIL T2 WITH SNOW SCREENING (F) LF 2,405. 130.00 312,650.00 120.00 288,600.00 124.00 298,220.00 563.225 BRIDGE RAIL T4 TO T2 TRANSITION (F) LF 52. 135.00 7,020.00 90.00 4,680.00 86.00 4,472.00 563.24 BRIDGE RAIL T4 (F) LF 139. 106.00 14,734.00 142.00 19,738.00 146.00 20,294.00 565.22 BRIDGE APPROACH RAIL T2 (F) LF 256. 100.00 25,600.00 125.00 32,000.00 125.00 32,000.00 565.24 BRIDGE APPROACH RAIL T4 (F) LF 110. 106.00 11,660.00 175.00 19,250.00 170.00 18,700.00 10622-C PAGE 5 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 565.63 BRIDGE APPROACH RAIL E LF 232. 80.00 18,560.00 105.00 24,360.00 110.00 25,520.00 570.9 RESETTING MASONRY WALL CY 110. 1.00 110.00 350.00 38,500.00 350.00 38,500.00 585.2 STONE FILL, CLASS B CY 385. 38.00 14,630.00 35.00 13,475.00 35.00 13,475.00 585.21 STONE FILL, CLASS B (BRIDGE) CY 2,190. 40.00 87,600.00 35.00 76,650.00 35.00 76,650.00 587.1 KEYED STONE FILL CY 1,950. 30.00 58,500.00 40.00 78,000.00 38.00 74,100.00 592.11 MECHANICALLY STABILIZED EARTH RETAINING WALL SF 71,111. 24.00 1,706,664.00 10.00 711,110.00 19.25 1,368,886.75 592.12 MECHANICALLY STABILIZED EARTH RETAINING WALL SF 20,181. 1.00 20,181.00 8.00 161,448.00 9.00 181,629.00 593.231 GEOTEXTILE; SEPARATION CL.3, NON-WOVEN SY 3,250. 3.00 9,750.00 2.00 6,500.00 3.50 11,375.00 593.411 GEOTEXTILE; PERM CONTROL CL.1, NON-WOVEN SY 2,770. 4.00 11,080.00 2.00 5,540.00 3.75 10,387.50 603.00212 12" R.C. PIPE, 2000D LF 103. 40.00 4,120.00 50.00 5,150.00 36.00 3,708.00 603.00215 15" R.C. PIPE, 2000D LF 8,600. 35.00 301,000.00 25.00 215,000.00 40.00 344,000.00 603.00218 18" R.C. PIPE, 2000D LF 1,950. 38.00 74,100.00 27.00 52,650.00 45.00 87,750.00 603.00224 24" R.C. PIPE, 2000D LF 515. 53.00 27,295.00 35.00 18,025.00 55.00 28,325.00 603.00230 30" R.C. PIPE, 2000D LF 1,600. 65.00 104,000.00 42.00 67,200.00 65.00 104,000.00 603.00236 36" R.C. PIPE, 2000D LF 21. 90.00 1,890.00 75.00 1,575.00 90.00 1,890.00 603.00248 48" R.C. PIPE, 2000D LF 4. 280.00 1,120.00 200.00 800.00 120.00 480.00 603.99015 15" TEMPORARY PIPE LF 135. 60.00 8,100.00 35.00 4,725.00 40.00 5,400.00 604.0007 POLYETHYLENE LINER EA 112. 210.00 23,520.00 300.00 33,600.00 225.00 25,200.00 604.0009 OIL-WATER SEPARATORS FOR CATCH BASINS EA 3. 700.00 2,100.00 450.00 1,350.00 650.00 1,950.00 604.12 CATCH BASINS TYPE B U 120. 1,750.00 210,000.00 1,500.00 180,000.00 1,600.00 192,000.00 604.125 CATCH BASINS TYPE B, 5-FOOT DIAMETER U 33. 1,800.00 59,400.00 2,150.00 70,950.00 2,400.00 79,200.00 604.126 CATCH BASINS TYPE B, 6-FOOT DIAMETER U 4. 2,000.00 8,000.00 2,700.00 10,800.00 3,200.00 12,800.00 604.15 CATCH BASINS TYPE E U 21. 1,700.00 35,700.00 2,300.00 48,300.00 1,700.00 35,700.00 604.155 CATCH BASINS TYPE E, 5-FOOT DIAMETER U 4. 2,000.00 8,000.00 2,500.00 10,000.00 2,500.00 10,000.00 604.191 SPECIAL CATCH BASINS U 1. 8,000.00 8,000.00 6,000.00 6,000.00 7,400.00 7,400.00 604.192 SPECIAL CATCH BASINS U 1. 7,500.00 7,500.00 5,650.00 5,650.00 7,350.00 7,350.00 604.193 SPECIAL CATCH BASINS U 1. 8,400.00 8,400.00 6,675.00 6,675.00 7,200.00 7,200.00 604.390 SPECIAL MANHOLE U 8. 2,500.00 20,000.00 2,000.00 16,000.00 400.00 3,200.00 604.4 RECONSTRUCTING CATCH BASINS & DROP INLETS LF 2. 250.00 500.00 500.00 1,000.00 270.00 540.00 604.45 ADJUSTING CATCH BASIN DROP INLET GRATE AND FRAMES EA 13. 180.00 2,340.00 400.00 5,200.00 270.00 3,510.00 604.51 RECONSTRUCT SEWER MANHOLE LF 17. 400.00 6,800.00 400.00 6,800.00 300.00 5,100.00 604.54 RECONSTRUCT MANHOLES (TELEPHONE) EA 2. 200.00 400.00 500.00 1,000.00 1,000.00 2,000.00 604.55 ADJUSTING MANHOLE COVERS AND FRAMES EA 35. 160.00 5,600.00 400.00 14,000.00 270.00 9,450.00 604.6 MANHOLE COVERS & FRAMES EA 1. 350.00 350.00 450.00 450.00 430.00 430.00 604.72 GRATES & FRAMES, TYPE B EA 4. 400.00 1,600.00 400.00 1,600.00 450.00 1,800.00 604.76 GRATES & FRAMES, TYPE F EA 1. 500.00 500.00 500.00 500.00 530.00 530.00 10622-C PAGE 6 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 604.85 WATER REPELLENT FOR EXISTING CB'S AND DI'S EA 11. 200.00 2,200.00 250.00 2,750.00 125.00 1,375.00 605.904 4" PIPE UND. (CONTRACTORS OPTION) LF 225. 16.00 3,600.00 15.00 3,375.00 15.00 3,375.00 606.000 STEEL BEAM FOR BEAM GUARDRAIL LF 6,900. 8.00 55,200.00 8.00 55,200.00 8.00 55,200.00 606.003 STEEL BEAM (THRIE BEAM) FOR BEAM GUARDRAIL LF 2,800. 19.00 53,200.00 14.00 39,200.00 13.00 36,400.00 606.014 6"X8" WOOD POST REPLACE- MENTS FOR BEAM GUARDRAIL POSTS EA 252. 55.00 13,860.00 60.00 15,120.00 50.00 12,600.00 606.0142 6"X8" WOOD POST ASSEMBLIES FOR BEAM GUARDRAIL POSTS EA 250. 12.00 3,000.00 15.00 3,750.00 15.00 3,750.00 606.140 BEAM GUARDRAIL (STANDARD SECTION- WOOD POSTS) LF 4,880. 19.00 92,720.00 17.00 82,960.00 16.00 78,080.00 606.1403 BEAM GUARDRAIL (THRIE BEAM) INCLUDING TRANSITION SECTION LF 20. 74.00 1,480.00 60.00 1,200.00 50.00 1,000.00 606.14422 BEAM GUARDRAIL (THRIE BEAM, DOUB. NEST.) INCL. TRANS. SECTS LF 20. 85.00 1,700.00 75.00 1,500.00 75.00 1,500.00 606.1454 BEAM GUARDRAIL (TERM. UNIT TYPE EAGRT 50 FT.) U 7. 2,500.00 17,500.00 2,200.00 15,400.00 1,950.00 13,650.00 606.1455 BEAM GUARDRAIL (TERM. UNIT EAGRT 25 FT.) U 1. 2,300.00 2,300.00 1,850.00 1,850.00 1,750.00 1,750.00 606.147 BEAM GUARDRAIL (TERMINAL UNIT TYPE G-2) U 6. 720.00 4,320.00 500.00 3,000.00 500.00 3,000.00 606.21403 DOUBLE-FACED BEAM GUARDRAIL (THRIE BEAM) INCLUD. TRANS. SECTION LF 275. 72.00 19,800.00 35.00 9,625.00 40.00 11,000.00 606.402 CONCRETE BARRIER, DOUBLE- FACED LF 1,940. 90.00 174,600.00 90.00 174,600.00 97.00 188,180.00 606.4029 MODIFIED CONCRETE MEDIAN BARRIER LF 1,340. 115.00 154,100.00 115.00 154,100.00 115.00 154,100.00 606.411 CONCRETE BARRIER, SINGLE- FACED, PRECAST LF 615. 84.00 51,660.00 80.00 49,200.00 84.00 51,660.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 11,300. 30.00 339,000.00 32.00 361,600.00 30.00 339,000.00 606.4175 PORTABLE CONCRETE BARRIER ANCHORED LF 480. 40.00 19,200.00 65.00 31,200.00 33.00 15,840.00 606.9523 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 3 U 7. 6,500.00 45,500.00 3,000.00 21,000.00 7,500.00 52,500.00 607.655 CHAIN LINK FENCE WITH VINYL-COATED STEEL FABRIC, 5 FEET HIGH LF 95. 30.00 2,850.00 36.00 3,420.00 30.00 2,850.00 607.659 POST ASSEMBLIES FOR CHAIN LINK FENCE, 5 FT. HIGH EA 2. 220.00 440.00 160.00 320.00 175.00 350.00 607.665 CHAIN LINK FENCE WITH VINYL-COATED STEEL FABRIC, 6 FEET HIGH LF 1,900. 18.50 35,150.00 19.00 36,100.00 18.00 34,200.00 10622-C PAGE 7 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 607.669 POST ASSEMBLIES FOR CHAIN LINK FENCE, 6 FT. HIGH EA 8. 235.00 1,880.00 160.00 1,280.00 175.00 1,400.00 608.12 2" BITUMINOUS SIDEWALK (F) SY 210. 11.00 2,310.00 12.00 2,520.00 12.50 2,625.00 608.24 4" CONCRETE SIDEWALK (F) SY 70. 35.00 2,450.00 36.00 2,520.00 36.00 2,520.00 608.263 6" BRICK EDGED CONCRETE SIDEWALK (F) SY 3,562. 125.00 445,250.00 125.00 445,250.00 110.00 391,820.00 608.28 8" CONCRETE SIDEWALK (F) SY 460. 45.00 20,700.00 47.00 21,620.00 45.00 20,700.00 608.46 6" TEXTURED REINFORCED CONCRETE SIDEWALK (F) SY 1,516. 82.00 124,312.00 224.00 339,584.00 200.00 303,200.00 608.52 DETECTABLE WARNING PAVERS (SIDEWALK RAMPS) SY 60. 300.00 18,000.00 450.00 27,000.00 400.00 24,000.00 609.01 STRAIGHT GRANITE CURB LF 3,300. 16.00 52,800.00 15.00 49,500.00 14.00 46,200.00 609.014 STRAIGHT GRANITE CURB 4" REVEAL LF 800. 14.00 11,200.00 12.00 9,600.00 10.00 8,000.00 609.02 CURVED GRANITE CURB LF 400. 25.00 10,000.00 23.00 9,200.00 25.00 10,000.00 609.0918 STRAIGHT GRANITE CURB 18" HIGH LF 145. 130.00 18,850.00 66.00 9,570.00 75.00 10,875.00 609.21 STRAIGHT GRANITE SLOPE CURB LF 8,900. 12.00 106,800.00 11.00 97,900.00 10.00 89,000.00 609.216 STRAIGHT GRANITE SLOPE CURB 6" HIGH LF 10. 34.00 340.00 13.00 130.00 15.00 150.00 609.22 STRAIGHT GRANITE SLOPE CURB WITH RADIAL JOINTS LF 110. 12.00 1,320.00 11.00 1,210.00 10.00 1,100.00 609.224 STRAIGHT GRANITE SLOPE CURB WITH RADIAL JOINTS, 4" HIGH LF 40. 15.00 600.00 11.00 440.00 10.00 400.00 609.23 CURVED GRANITE SLOPE CURB LF 7. 54.00 378.00 51.00 357.00 40.00 280.00 609.3 STRAIGHT GRANITE CURB (BRIDGE) LF 4,947. 26.00 128,622.00 30.00 148,410.00 27.00 133,569.00 609.35 CURVED GRANITE CURB (BRIDGE) LF 25. 52.00 1,300.00 85.00 2,125.00 40.00 1,000.00 609.5 RESET GRANITE CURB LF 4,745. 5.60 26,572.00 6.00 28,470.00 8.00 37,960.00 609.811 BITUMINOUS CURB, TYPE B (4" REVEAL) LF 1,100. 2.60 2,860.00 3.00 3,300.00 2.50 2,750.00 611.05206 6" CEMENT LINED DUCTILE IRON WATER PIPE , CL.52 LF 20. 28.00 560.00 100.00 2,000.00 110.00 2,200.00 611.811 ADJUSTING/RELOCATING HYDRANTS EA 1. 600.00 600.00 1,500.00 1,500.00 1,100.00 1,100.00 611.90001 ADJUSTING WATER GATES AND SHUTOFFS SET BY OTHERS EA 22. 130.00 2,860.00 200.00 4,400.00 225.00 4,950.00 613.411 STORMWATER TREATMENT SYSTEM (LEVEL 1) U 1. 90,000.00 90,000.00 36,000.00 36,000.00 65,000.00 65,000.00 613.412 STORMWATER TREATMENT SYSTEM (LEVEL 1) U 1. 40,000.00 40,000.00 90,000.00 90,000.00 125,000.00 125,000.00 614.01 TRANSFORMER SLAB U 3. 700.00 2,100.00 650.00 1,950.00 500.00 1,500.00 614.121 2 IN CONDUIT CONCRETE ENCASED LF 90. 8.00 720.00 8.00 720.00 6.50 585.00 614.131 3 IN CONDUIT CONCRETE ENCASED LF 1,300. 12.00 15,600.00 12.00 15,600.00 10.00 13,000.00 10622-C PAGE 8 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 614.132 3" 2-DUCT CONDUIT, CONC. ENCASED LF 100. 16.00 1,600.00 16.00 1,600.00 15.00 1,500.00 614.141 4" CONDUIT, CONC. ENCASED ENCASED LF 80. 14.00 1,120.00 14.00 1,120.00 12.00 960.00 614.142 4" 2-DUCT CONDUIT, CONC. ENCASED LF 400. 20.00 8,000.00 20.00 8,000.00 18.00 7,200.00 614.144 4 IN 4 DUCT CONDUIT CONCRETE ENCASED LF 350. 35.00 12,250.00 35.00 12,250.00 25.00 8,750.00 614.152 5 IN 2 DUCT CONDUIT CONCRETE ENCASED LF 275. 35.00 9,625.00 35.00 9,625.00 30.00 8,250.00 614.342 4 IN 2-DUCT STEEL CONDUIT LF 608. 75.00 45,600.00 80.00 48,640.00 50.00 30,400.00 614.511 CONCRETE PULL BOX 14" EA 24. 200.00 4,800.00 185.00 4,440.00 200.00 4,800.00 614.513 CONCRETE PULL BOX 24" EA 27. 400.00 10,800.00 375.00 10,125.00 325.00 8,775.00 614.523 MOLDED PULL BOX 17"X30" EA 9. 350.00 3,150.00 350.00 3,150.00 300.00 2,700.00 614.524 MOLDED PULL BOX 11" X 18" EA 32. 200.00 6,400.00 185.00 5,920.00 225.00 7,200.00 614.7214 2" PVC PLASTIC CONDUIT, SCHEDULE 40 LF 2,200. 5.00 11,000.00 5.00 11,000.00 5.00 11,000.00 614.7218 2" PVC PLASTIC CONDUIT, SCHEDULE 80 LF 1,330. 6.00 7,980.00 6.50 8,645.00 6.00 7,980.00 614.7314 3" PVC PLASTIC CONDUIT, SCHEDULE 40 LF 3,400. 6.00 20,400.00 6.00 20,400.00 6.00 20,400.00 614.7318 3" PVC PLASTIC CONDUIT, SCHEDULE 80 LF 850. 9.00 7,650.00 8.00 6,800.00 7.00 5,950.00 614.7424 4" 2-DUCT PVC CONDUIT, SCHEDULE 40 LF 5,250. 12.00 63,000.00 12.00 63,000.00 10.00 52,500.00 614.7428 4" 2-DUCT PVC CONDUIT, SCHEDULE 80 LF 980. 15.00 14,700.00 15.00 14,700.00 12.00 11,760.00 615.01 TRAFFIC SIGN TYPE A (F) SF 144. 42.00 6,048.00 43.00 6,192.00 42.00 6,048.00 615.012 TRAFFIC SIGN TYPE A, BREAKAWAY MOUNTS (F) SF 144. 52.00 7,488.00 53.00 7,632.00 52.00 7,488.00 615.02 TRAFFIC SIGN TYPE B (F) SF 158. 50.00 7,900.00 51.00 8,058.00 52.00 8,216.00 615.022 TRAFFIC SIGN TYPE B, BREAKAWAY MOUNTS (F) SF 179.83 60.00 10,789.80 65.00 11,688.95 65.00 11,688.95 615.03 TRAFFIC SIGN TYPE C (F) SF 397.8 40.00 15,912.00 35.00 13,923.00 32.00 12,729.60 615.032 TRAFFIC SIGN TYPE C, BREAKAWAY MOUNTS (F) SF 92. 40.00 3,680.00 58.00 5,336.00 55.00 5,060.00 615.034 RELOCATING TRAFFIC SIGN, TYPE C U 16. 175.00 2,800.00 175.00 2,800.00 125.00 2,000.00 615.04 TRAFFIC SIGN TYPE AA (F) SF 144.5 18.00 2,601.00 18.00 2,601.00 17.00 2,456.50 615.043 REMOVING TRAFFIC SIGN TYPE AA U 2. 50.00 100.00 250.00 500.00 150.00 300.00 615.046 RELOCATING TRAFFIC SIGN TYPE AA ON NEW FACILITIES SF 1,784.5 8.00 14,276.00 8.00 14,276.00 11.00 19,629.50 615.05 TRAFFIC SIGN TYPE BB (F) SF 14. 20.00 280.00 20.00 280.00 20.00 280.00 615.06 TRAFFIC SIGN TYPE CC (F) SF 164.3 12.00 1,971.60 12.00 1,971.60 10.00 1,643.00 615.10001 FULL TRAFFIC SIGN STRUCTURE U 1. 30,000.00 30,000.00 29,000.00 29,000.00 29,000.00 29,000.00 615.10002 FULL TRAFFIC SIGN STRUCTURE U 1. 30,000.00 30,000.00 31,000.00 31,000.00 28,000.00 28,000.00 10622-C PAGE 9 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 615.10003 FULL TRAFFIC SIGN STRUCTURE U 1. 30,000.00 30,000.00 29,000.00 29,000.00 27,250.00 27,250.00 615.10004 FULL TRAFFIC SIGN STRUCTURE U 1. 70,000.00 70,000.00 70,000.00 70,000.00 65,500.00 65,500.00 615.10301 REMOVING FULL TRAFFIC SIGN STRUCTURE U 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 615.20001 CANTILEVER TRAFFIC SIGN STRUCTURE U 1. 28,000.00 28,000.00 28,000.00 28,000.00 27,000.00 27,000.00 615.20301 REMOVING CANTILEVER TRAFFIC SIGN STRUCTURE U 1. 4,000.00 4,000.00 4,000.00 4,000.00 2,500.00 2,500.00 615.20302 REMOVING CANTILEVER TRAFFIC SIGN STRUCTURE U 1. 4,000.00 4,000.00 4,000.00 4,000.00 2,500.00 2,500.00 615.30001 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 9,000.00 9,000.00 9,000.00 9,000.00 8,500.00 8,500.00 615.30002 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 7,000.00 7,000.00 7,000.00 7,000.00 7,500.00 7,500.00 615.30003 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 9,000.00 9,000.00 9,000.00 9,000.00 8,000.00 8,000.00 615.30004 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 7,000.00 7,000.00 7,000.00 7,000.00 7,500.00 7,500.00 616.101 TRAFFIC SIGNALS U 1. 110,000.00 110,000.00 105,000.00 105,000.00 110,000.00 110,000.00 616.102 TRAFFIC SIGNALS U 1. 80,000.00 80,000.00 72,000.00 72,000.00 75,000.00 75,000.00 616.103 TRAFFIC SIGNALS U 1. 80,000.00 80,000.00 77,000.00 77,000.00 75,000.00 75,000.00 616.111 VIDEO DETECTION SYSTEM U 1. 18,000.00 18,000.00 14,000.00 14,000.00 17,500.00 17,500.00 616.112 BACKUP POWER CONNECTION U 1. 2,000.00 2,000.00 1,700.00 1,700.00 2,000.00 2,000.00 616.122 COMMUNICATIONS CABLE LF 420. 3.20 1,344.00 2.00 840.00 2.00 840.00 616.123 COMMUNICATIONS CABLE LF 1,870. 3.20 5,984.00 2.30 4,301.00 3.00 5,610.00 616.141 COMPUTER EQUIPMENT AND SOFTWARE U 1. 8,000.00 8,000.00 7,600.00 7,600.00 4,500.00 4,500.00 616.1415 OPERATIONS AND MAINTENANCE TRAINING U 1. 2,000.00 2,000.00 3,200.00 3,200.00 2,000.00 2,000.00 616.161 TRAFFIC SIGNALS (TEMP.) U 1. 20,000.00 20,000.00 13,500.00 13,500.00 7,800.00 7,800.00 616.162 TRAFFIC SIGNAL (TEMP.) U 1. 20,000.00 20,000.00 11,000.00 11,000.00 8,250.00 8,250.00 616.163 TRAFFIC SIGNAL (TEMP.) U 1. 20,000.00 20,000.00 9,200.00 9,200.00 10,000.00 10,000.00 618.6 UNIFORMED OFFICERS $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 618.601 UNIFORMED OFFICERS WITH VEHICLES $ 1. 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 500,000.00 500,000.00 500,000.00 500,000.00 500,000.00 500,000.00 618.7 FLAGGERS HR 11,360. 10.00 113,600.00 15.00 170,400.00 18.00 204,480.00 619.1 MAINTENANCE OF TRAFFIC U 1. 400,000.00 400,000.00 160,000.00 160,000.00 150,000.00 150,000.00 619.11 MAINTENANCE OF TRAFFIC U 1. 200,000.00 200,000.00 65,000.00 65,000.00 75,000.00 75,000.00 619.253 PORTABLE CHANGEABLE MESSAGE SIGN (UNIT WEEK) UWK 544. 160.00 87,040.00 250.00 136,000.00 250.00 136,000.00 619.27 TRAILER-MOUNTED SPEED LIMIT SIGN U 4. 12,000.00 48,000.00 5,000.00 20,000.00 4,000.00 16,000.00 621.1 RETROREFLECTIVE MEDIAN BARRIER DELINEATOR EA 50. 7.00 350.00 7.00 350.00 8.00 400.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 110. 5.00 550.00 7.00 770.00 4.00 440.00 10622-C PAGE 10 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 621.31 SINGLE DELINEATOR WITH POST EA 300. 24.00 7,200.00 24.00 7,200.00 20.00 6,000.00 621.32 DOUBLE DELINEATOR WITH POST EA 40. 30.00 1,200.00 28.00 1,120.00 25.00 1,000.00 621.725 FLEXIBLE DELINEATORS, BRIDGE (YELLOW) EA 49. 30.00 1,470.00 10.00 490.00 30.00 1,470.00 622.1 STEEL WITNESS MARKERS EA 27. 24.00 648.00 24.00 648.00 22.00 594.00 622.4 STONE BOUNDS EA 19. 250.00 4,750.00 325.00 6,175.00 250.00 4,750.00 625.2 CONCRETE LIGHT POLE BASES, TYPE B EA 19. 500.00 9,500.00 475.00 9,025.00 500.00 9,500.00 625.22 CONCRETE LIGHT POLE BASES, TYPE B (FOR HIGH- WAY LIGHTING) EA 7. 500.00 3,500.00 475.00 3,325.00 550.00 3,850.00 625.52 LIGHT POLE (HIGHWAY) U 7. 1,700.00 11,900.00 1,520.00 10,640.00 1,650.00 11,550.00 625.521 RELOCATED LIGHT POLE (HIGHWAY) U 2. 650.00 1,300.00 625.00 1,250.00 650.00 1,300.00 625.551 ORNAMENTAL STREET LIGHTING, TYPE A EA 15. 7,700.00 115,500.00 7,700.00 115,500.00 8,250.00 123,750.00 625.554 ORNAMENTAL STREET LIGHTING, TYPE D EA 4. 7,700.00 30,800.00 7,700.00 30,800.00 8,250.00 33,000.00 625.555 ORNAMENTAL STREET LIGHTING, TYPE F (WALL MOUNT) EA 4. 7,700.00 30,800.00 7,700.00 30,800.00 8,250.00 33,000.00 628.2 SAWED BITUMINOUS PAVEMENT LF 16,500. 1.60 26,400.00 2.00 33,000.00 2.00 33,000.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 32,000. .15 4,800.00 .10 3,200.00 .10 3,200.00 632.0106 RETROREFLECTIVE PAINT PAVE. MARKING, 6" LINE LF 111,300. .18 20,034.00 .13 14,469.00 .12 13,356.00 632.0108 RETROREFLECTIVE PAINT PAVE. MARKING, 8" LINE LF 300. .50 150.00 .35 105.00 .35 105.00 632.0112 RETROREFLECTIVE PAINT PAVE. MARKING, 12" LINE LF 10,700. .30 3,210.00 .75 8,025.00 .75 8,025.00 632.0118 RETROREFLECTIVE PAINT PAVE. MARKING, 18" LINE LF 1,100. 2.00 2,200.00 1.15 1,265.00 1.00 1,100.00 632.02 RETROREFLECTIVE PAINT PAVEMENT MARKING, SYMBOL OR WORD SF 2,000. 1.80 3,600.00 1.45 2,900.00 1.25 2,500.00 632.3106 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 6" LINE LF 550. 1.50 825.00 .95 522.50 .85 467.50 632.3112 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 12" LINE LF 1,700. 1.50 2,550.00 1.45 2,465.00 1.00 1,700.00 632.3118 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 18" LINE LF 530. 2.00 1,060.00 2.20 1,166.00 2.00 1,060.00 632.32 RETROREFLECT. THERMOPLAS. PAVEMENT MARKING, SYMBOL OR WORD SF 1,330. 7.00 9,310.00 3.75 4,987.50 5.00 6,650.00 632.9104 OBLITERATE PAVEMENT MARKING, 4" LINE LF 8,000. .35 2,800.00 .40 3,200.00 .40 3,200.00 632.9106 OBLITERATE PAVEMENT MARKING, 6" LINE LF 27,800. .40 11,120.00 .45 12,510.00 .50 13,900.00 10622-C PAGE 11 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 632.9112 OBLITERATE PAVEMENT MARKING, 12" LINE LF 1,750. 1.00 1,750.00 .90 1,575.00 .80 1,400.00 632.92 OBLITERATE PAVEMENT MARKING, SYMBOL OR WORD SF 800. 1.50 1,200.00 1.20 960.00 1.50 1,200.00 641. LOAM CY 490. 32.00 15,680.00 30.00 14,700.00 25.00 12,250.00 643.21 FERTILIZER FOR REFERTIL- IZATION LB 6,550. .30 1,965.00 .30 1,965.00 .30 1,965.00 643.22 FERTILIZER FOR REFERTIL- IZATION TON 1. 600.00 600.00 600.00 600.00 600.00 600.00 645.154 BARK MULCH 4 INCHES DEEP SY 300. 6.00 1,800.00 6.00 1,800.00 5.00 1,500.00 645.3 EROSION STONE TON 500. 34.00 17,000.00 30.00 15,000.00 40.00 20,000.00 645.51 HAY BALES FOR TEMPORARY EROSION CONTROL EA 1,200. 8.00 9,600.00 10.00 12,000.00 6.00 7,200.00 645.531 SILT FENCE LF 4,900. 2.50 12,250.00 3.00 14,700.00 3.00 14,700.00 645.7 STORM WATER POLLUTION PREVENTION PLAN U 1. 20,000.00 20,000.00 2,400.00 2,400.00 3,500.00 3,500.00 645.701 STORM WATER POLLUTION PREVENTION PLAN U 1. 15,000.00 15,000.00 2,400.00 2,400.00 2,000.00 2,000.00 645.71 MONITORING SWPPP AND EROSION AND SEDIMENT CONTROLS HR 775. 40.00 31,000.00 80.00 62,000.00 48.00 37,200.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 39,400. .35 13,790.00 .50 19,700.00 .30 11,820.00 647.1 HUMUS CY 3,450. 30.00 103,500.00 25.00 86,250.00 21.65 74,692.50 662.281 DECOMISSION MONITORING WELLS LF 212. 25.00 5,300.00 20.00 4,240.00 25.00 5,300.00 670.0451 CONSTRUCT AND REMOVE TEMPORARY DETOURS U 1. 440,000.00 440,000.00 200,000.00 200,000.00 170,000.00 170,000.00 670.101 TEMPORARY LIGHTING U 1. 15,000.00 15,000.00 10,000.00 10,000.00 5,500.00 5,500.00 670.1011 TEMPORARY LIGHTING U 1. 15,000.00 15,000.00 11,000.00 11,000.00 5,000.00 5,000.00 670.42 DUCTILE IRON BOLLARD EA 26. 800.00 20,800.00 500.00 13,000.00 1,000.00 26,000.00 692. MOBILIZATION U 1. 2,430,000.00 2,430,000.00 700,000.00 700,000.00 2,110,000.00 2,110,000.00 693. ON-THE-JOB TRAINING OF UNSKILLED WORKERS $ 1. 1,200.00 1,200.00 1,200.00 1,200.00 1,200.00 1,200.00 698.12 FIELD OFFICE TYPE B MON 36. 2,600.00 93,600.00 1,400.00 50,400.00 1,500.00 54,000.00 698.2 PHYSICAL TESTING LABORATORY MON 36. 1,000.00 36,000.00 750.00 27,000.00 810.00 29,160.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 80,000.00 80,000.00 80,000.00 80,000.00 80,000.00 80,000.00 699.1 MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1002.1 REPAIRS OR REPLACEMENTS AS NEEDED $ 1. 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 1008.11 ALTERATIONS AND ADDITIONS AS NEEDED- UNANTICIPATED WORK $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 1008.14 ALTERATIONS AND ADDITIONS AS NEEDED-SPECIAL TERMINAL PLATFORM $ 1. 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00 10622-C PAGE 12 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 1008.6 ALTERATIONS AND ADDITIONS AS NEEDED-ELECTRICAL SERVICE CONNECTION $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1008.61 BILLBOARD SIGN REMOVAL $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 1009.2 TREATMENT OR DISPOSAL OF CONTAMINATED SOIL/GROUNDWATER $ 1. 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 1009.21 TREATMENT OR DISPOSAL OF CONTAMINATED SOIL/GROUNDWATER $ 1. 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 1009.3 MONITORING, TREATMENT AND DISPOSAL ASBESTOS FILL $ 1. 75,000.00 75,000.00 75,000.00 75,000.00 75,000.00 75,000.00 1009.31 MONITORING, TREATMENT AND DISPOSAL ASBESTOS FILL $ 1. 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 1009.4 BUILDING ASBESTOS ABATEMENT $ 1. 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 1009.5 DISPOSAL FUEL SLUDGE $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 1009.7 PROJECT OPERATIONS PLAN $ 1. 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 1010.11 FUEL ADJUSTMENT, DIESEL $ 1. 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 1010.12 FUEL ADJUSTMENT, GASOLINE $ 1. 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 1010.41 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR CONCRETE $ 1. 40,000.00 40,000.00 40,000.00 40,000.00 40,000.00 40,000.00 1010.42 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR CONCRETE $ 1. 60,000.00 60,000.00 60,000.00 60,000.00 60,000.00 60,000.00 1010.43 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR CONCRETE $ 1. 1,500.00 1,500.00 1,500.00 1,500.00 1,500.00 1,500.00 $28,687,750.00 $28,768,567.27 $28,984,650.45 THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: MANCHESTER A000 (320), 10622-C MANCHESTER X-A000 (294), 14025-C COUNTIES AND CODES: HILLSBOROUGH 011 DATE BIDS OPEN: JUNE 29, 2005 SCOPE OF WORK: ROAD AND BRIDGE IMPROVEMENTS LOCATION: EXIT 5 INTERCHANGE ALONG I-293 AND GRANITE STREET CORRIDORS COMPLETION DATE: MAY 30, 2008 A THE MIDDLESEX CORPORATION ONE SPECTACLE POND ROAD, LITTLETON, MA 01460 $28,687,750.00 B REED & REED INC P O BOX 370, WOOLWICH, ME 04579 $28,768,567.27 C R.S. AUDLEY, INC. 609 ROUTE 3A, BOW, NH 03304 $28,984,650.45 D WEAVER BROS. CONST. CO., INC. P.O. BOX 132C CONCORD, NH 03302 $30,266,492.55 E E. D. SWETT, INC. 8 INDUSTRIAL PARK DR., CONCORD, NH 03301 $30,875,185.00 F PARK CONSTRUCTION CORP P O BOX 600 FITZWILLIAM, NH 03447 $32,528,829.91 G R. ZOPPO CORP. 160 OLD MAPLE STREET, STOUGHTON, MA 02072 $34,343,677.61 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 201.1 CLEARING AND GRUBBING (F) A 1.7 16,000.00 27,200.00 10,000.00 17,000.00 10,000.00 17,000.00 201.21 REMOVING SMALL TREES EA 6. 300.00 1,800.00 400.00 2,400.00 350.00 2,100.00 201.22 REMOVING LARGE TREES EA 2. 600.00 1,200.00 1,000.00 2,000.00 1,000.00 2,000.00 202.201 DEMOLISHING BUILDINGS U 1. 60,000.00 60,000.00 40,000.00 40,000.00 100,000.00 100,000.00 202.31 FILL ABANDONED PIPE CY 9. 250.00 2,250.00 400.00 3,600.00 125.00 1,125.00 202.41 REMOVAL OF EXISTING PIPE 0-24" DIAMETER LF 199. 12.00 2,388.00 15.00 2,985.00 25.00 4,975.00 202.5 REMOVAL OF CATCH BASINS, DROP INLETS, AND MANHOLES EA 31. 300.00 9,300.00 400.00 12,400.00 450.00 13,950.00 202.6 CURB REMOVAL FOR STORAGE LF 5,525. 1.75 9,668.75 2.00 11,050.00 10.00 55,250.00 202.7 REMOVAL OF GUARDRAIL (F) LF 13,800. 2.10 28,980.00 2.00 27,600.00 8.00 110,400.00 202.9 REMOVAL OF FUEL TANKS U 1. 20,000.00 20,000.00 35,000.00 35,000.00 10,000.00 10,000.00 203.1 COMMON EXCAVATION CY 67,600. 6.75 456,300.00 8.50 574,600.00 10.00 676,000.00 203.2 ROCK EXCAVATION CY 340. 20.00 6,800.00 25.00 8,500.00 30.00 10,200.00 203.35 HANDLING EXCAVATED, CONTAMINATED SOIL CY 22,245. 8.00 177,960.00 7.00 155,715.00 8.00 177,960.00 203.37 SEGREGATING AND REHANDLING, NON-CONTAMINATED SOIL CY 800. 15.00 12,000.00 15.00 12,000.00 8.00 6,400.00 10622-C PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 203.6 EMBANKMENT-IN-PLACE (F) CY 51,536. 12.60 649,353.60 6.00 309,216.00 4.00 206,144.00 203.62 EMBANKMENT-IN-PLACE, REPLACEMENT MATERIAL CY 2,900. 17.00 49,300.00 15.00 43,500.00 12.00 34,800.00 206.1 COMMON STRUCTURE EXCAVATION CY 1,650. 10.00 16,500.00 20.00 33,000.00 10.00 16,500.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 100. 35.00 3,500.00 50.00 5,000.00 20.00 2,000.00 206.2 ROCK STRUCTURE EXCAVATION CY 160. 190.00 30,400.00 125.00 20,000.00 125.00 20,000.00 207.3 UNCLASSIFIED CHANNEL EXCAVATION CY 2,108. 8.50 17,918.00 20.00 42,160.00 12.00 25,296.00 209.1 GRANULAR BACKFILL CY 165. 17.00 2,805.00 35.00 5,775.00 18.00 2,970.00 209.2 GRANULAR BACKFILL (BRIDGE) CY 65,185. 18.00 1,173,330.00 30.00 1,955,550.00 18.00 1,173,330.00 209.2014 GRANULAR BACKFILL (COARSE AGGREGATE) CY 3,521. 18.00 63,378.00 35.00 123,235.00 20.00 70,420.00 209.3 GRANULAR BACKFILL (SAND) CY 118. 17.00 2,006.00 35.00 4,130.00 20.00 2,360.00 209.4 GRANULAR BACKFILL (GRAV) CY 110. 20.00 2,200.00 35.00 3,850.00 20.00 2,200.00 210.62 GROUNDWATER OBSERVATION WELL (DRILLED) LF 192. 40.00 7,680.00 50.00 9,600.00 45.00 8,640.00 210.7 PROTECTIVE CASING WITH CAP AND LOCK EA 12. 150.00 1,800.00 250.00 3,000.00 150.00 1,800.00 214. FINE GRADING U 1. 185,000.00 185,000.00 150,000.00 150,000.00 150,000.00 150,000.00 214.1 FINE GRADING U 1. 38,000.00 38,000.00 90,000.00 90,000.00 50,000.00 50,000.00 304.1 SAND (F) CY 19,687. 19.00 374,053.00 17.00 334,679.00 15.00 295,305.00 304.2 GRAVEL (F) CY 18,321. 19.00 348,099.00 18.00 329,778.00 17.00 311,457.00 304.3 CRUSHED GRAVEL (F) CY 24,585. 22.00 540,870.00 20.00 491,700.00 20.00 491,700.00 304.31 CRUSHED GRAVEL FOR SHIMMING CY 500. 24.00 12,000.00 30.00 15,000.00 20.00 10,000.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 150. 24.00 3,600.00 30.00 4,500.00 25.00 3,750.00 403.1105 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (SUPERPAVE) TON 27,905. 46.00 1,283,630.00 44.25 1,234,796.25 48.00 1,339,440.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 670. 90.00 60,300.00 90.00 60,300.00 90.00 60,300.00 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 334. 120.00 40,080.00 75.00 25,050.00 85.00 28,390.00 403.98 HOT BITUMINOUS CONCRETE LEVELING, MACHINE METHOD TON 160. 55.00 8,800.00 70.00 11,200.00 65.00 10,400.00 403.989 HOT BITUMINOUS CONCRETE LEVELING, MACH. METHOD (NIGHT) TON 175. 85.00 14,875.00 70.00 12,250.00 65.00 11,375.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 3,450. 46.00 158,700.00 52.00 179,400.00 55.00 189,750.00 411.1 HOT BITUMINOUS CONCRETE LEVELING COURSE TON 225. 80.00 18,000.00 70.00 15,750.00 65.00 14,625.00 413.1 HOT-POURED CRACK SEALANT LB 8,250. 1.60 13,200.00 2.00 16,500.00 6.00 49,500.00 417. COLD PLANING BITUMINOUS SURFACES (F) SY 5,317. 10.00 53,170.00 5.00 26,585.00 5.00 26,585.00 417.19 COLD PLANING BITUMINOUS SURFACES (NIGHT) (F) SY 4,650. 11.50 53,475.00 6.00 27,900.00 6.00 27,900.00 10622-C PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 175,000.00 175,000.00 500,000.00 500,000.00 350,000.00 350,000.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 90,000.00 90,000.00 100,000.00 100,000.00 225,000.00 225,000.00 503.201 COFFERDAMS U 1. 60,000.00 60,000.00 100,000.00 100,000.00 150,000.00 150,000.00 503.202 COFFERDAMS U 1. 95,000.00 95,000.00 100,000.00 100,000.00 175,000.00 175,000.00 503.203 COFFERDAMS U 1. 95,000.00 95,000.00 100,000.00 100,000.00 175,000.00 175,000.00 503.204 COFFERDAMS U 1. 430,000.00 430,000.00 500,000.00 500,000.00 500,000.00 500,000.00 503.205 COFFERDAMS U 1. 15,000.00 15,000.00 25,000.00 25,000.00 17,500.00 17,500.00 503.206 COFFERDAMS U 1. 15,000.00 15,000.00 25,000.00 25,000.00 17,500.00 17,500.00 503.207 COFFERDAMS U 1. 15,000.00 15,000.00 25,000.00 25,000.00 17,500.00 17,500.00 503.208 COFFERDAMS U 1. 15,000.00 15,000.00 25,000.00 25,000.00 17,500.00 17,500.00 503.209 COFFERDAMS U 1. 25,000.00 25,000.00 10,000.00 10,000.00 10,000.00 10,000.00 503.210 COFFERDAMS U 1. 225,000.00 225,000.00 500,000.00 500,000.00 500,000.00 500,000.00 503.211 COFFERDAMS U 1. 70,000.00 70,000.00 1,000.00 1,000.00 200.00 200.00 503.212 COFFERDAMS U 1. 300,000.00 300,000.00 500,000.00 500,000.00 450,000.00 450,000.00 504.101 COMMON BRIDGE EXCAVATION CY 43,377. 7.00 303,639.00 11.00 477,147.00 10.00 433,770.00 504.2 ROCK BRIDGE EXCAVATION CY 644. 125.00 80,500.00 100.00 64,400.00 125.00 80,500.00 508. STRUCTURAL FILL CY 1,250. 35.00 43,750.00 30.00 37,500.00 20.00 25,000.00 510.11 PILE DRIVING EQUIPMENT (MINI-PILES) U 1. 140,000.00 140,000.00 200,000.00 200,000.00 15,000.00 15,000.00 510.2 PILE LOADING TESTS EA 2. 22,000.00 44,000.00 20,000.00 40,000.00 28,000.00 56,000.00 510.501 C-I-P CONCRETE PILES (DRILLED MINI-PILES) LF 24,985. 72.00 1,798,920.00 67.00 1,673,995.00 75.00 1,873,875.00 511.00 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 2,276. 6.00 13,656.00 10.00 22,760.00 12.00 27,312.00 511.02 PREPARATION FOR PARTIAL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 569. 250.00 142,250.00 50.00 28,450.00 50.00 28,450.00 511.03 PREPARATION FOR FULL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 114. 425.00 48,450.00 100.00 11,400.00 100.00 11,400.00 512.0201 PREPARATION FOR CONCRETE REPAIRS, CLASS II SY 50. 600.00 30,000.00 200.00 10,000.00 200.00 10,000.00 520.01 CONCRETE CLASS AA CY 51. 750.00 38,250.00 200.00 10,200.00 200.00 10,200.00 520.0102 CONCRETE CLASS AA (QC/QA) (F) CY 3,212. 430.00 1,381,160.00 350.00 1,124,200.00 300.00 963,600.00 520.028 PRECAST CONCRETE ARCHITECTURAL PANELS U 1. 310,000.00 310,000.00 350,000.00 350,000.00 350,000.00 350,000.00 520.12 CONCRETE CLASS A, ABOVE FOOTINGS (F) CY 1,050. 380.00 399,000.00 500.00 525,000.00 500.00 525,000.00 520.2 CONCRETE CLASS B CY 210. 275.00 57,750.00 300.00 63,000.00 300.00 63,000.00 520.21 CONCRETE CLASS B, FOOTINGS (F) CY 2,750. 180.00 495,000.00 300.00 825,000.00 300.00 825,000.00 520.421 CONCRETE CLASS F, FLOWABLE FILL, EXCAVATABLE CY 52. 200.00 10,400.00 125.00 6,500.00 125.00 6,500.00 520.7002 CONCRETE BRIDGE DECK (QC/QA) (F) CY 780. 620.00 483,600.00 750.00 585,000.00 600.00 468,000.00 10622-C PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 532.1 ANTI-GRAFFITI COATING SF 6,230. 2.25 14,017.50 2.50 15,575.00 2.50 15,575.00 534.1 WATER REPELLENT (LINSEED OIL) GAL 20. 27.00 540.00 50.00 1,000.00 50.00 1,000.00 534.3 WATER REPELLENT (SILANE- SILOXANE) GAL 773. 65.00 50,245.00 55.00 42,515.00 50.00 38,650.00 536.11 EPOXY COATING FOR CONCRETE (F) SF 1,550. 9.50 14,725.00 10.00 15,500.00 10.00 15,500.00 537. CONCRETE SEALER (F) SF 6,500. 1.10 7,150.00 1.00 6,500.00 1.00 6,500.00 538.2 BARRIER MEMBRANE, VERTICAL SURFACES (F) SY 110. 37.00 4,070.00 50.00 5,500.00 50.00 5,500.00 538.3 BARRIER MEMBRANE, LIQUID SPRAY (F) SY 3,725. 55.00 204,875.00 65.00 242,125.00 60.00 223,500.00 538.5 BARRIER MEMBRANE, WELDED BY TORCH (F) SY 5,456. 18.00 98,208.00 25.00 136,400.00 25.00 136,400.00 541.2 PVC WATERSTOPS, NH TYPE 2 (F) LF 113. 5.00 565.00 10.00 1,130.00 5.00 565.00 541.3 PVC WATERSTOPS, NH TYPE 3 (F) LF 55. 7.00 385.00 10.00 550.00 6.00 330.00 541.5 PVC WATERSTOPS, NH TYPE 5 (F) LF 119. 9.00 1,071.00 10.00 1,190.00 10.00 1,190.00 544. REINFORCING STEEL (F) LB 335,276. 1.10 368,803.60 1.00 335,276.00 .85 284,984.60 544.1 REINFORCING STEEL (ROADWAY) LB 15,300. .95 14,535.00 1.00 15,300.00 1.00 15,300.00 544.11 REINFORCING STEEL-MECH'L. CONNECTORS (F) LB 534. 3.00 1,602.00 5.00 2,670.00 3.50 1,869.00 544.2 REINFORCING STEEL, EPOXY COATED (F) LB 614,717. .95 583,981.15 1.10 676,188.70 1.00 614,717.00 544.21 REINFORCING STEEL, EPOXY COATED-MECHANICAL CONNECTORS (F) LB 4,548. 3.25 14,781.00 5.00 22,740.00 4.00 18,192.00 547. SHEAR CONNECTORS (F) EA 7,137. 2.60 18,556.20 2.50 17,842.50 2.50 17,842.50 548.21 ELASTOMERIC BEARING ASSEMBLIES (F) EA 13. 4,500.00 58,500.00 3,500.00 45,500.00 3,000.00 39,000.00 550.1 STRUCTURAL STEEL (F) LB 2,017,267. 1.10 2,218,993.70 1.00 2,017,267.00 1.08 2,178,648.36 550.2 BRIDGE SHOES (F) EA 13. 1,700.00 22,100.00 2,500.00 32,500.00 2,000.00 26,000.00 559.4 ELASTOMERIC PLUG TYPE EXPANSION JOINT (F) LF 410. 80.00 32,800.00 100.00 41,000.00 75.00 30,750.00 561.04 REHABILITATE EXPANSION JOINT U 1. 13,000.00 13,000.00 20,000.00 20,000.00 15,000.00 15,000.00 561.110 PREFABRICATED EXPANSION JOINT, TYPE A (F) LF 122. 450.00 54,900.00 500.00 61,000.00 500.00 61,000.00 563.22 BRIDGE RAIL T2 (F) LF 2,379. 90.00 214,110.00 110.00 261,690.00 120.00 285,480.00 563.223 BRIDGE RAIL T2 WITH SNOW SCREENING (F) LF 2,405. 130.00 312,650.00 160.00 384,800.00 150.00 360,750.00 563.225 BRIDGE RAIL T4 TO T2 TRANSITION (F) LF 52. 100.00 5,200.00 165.00 8,580.00 230.00 11,960.00 563.24 BRIDGE RAIL T4 (F) LF 139. 150.00 20,850.00 175.00 24,325.00 200.00 27,800.00 565.22 BRIDGE APPROACH RAIL T2 (F) LF 256. 135.00 34,560.00 125.00 32,000.00 120.00 30,720.00 565.24 BRIDGE APPROACH RAIL T4 (F) LF 110. 190.00 20,900.00 160.00 17,600.00 250.00 27,500.00 10622-C PAGE 5 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 565.63 BRIDGE APPROACH RAIL E LF 232. 115.00 26,680.00 75.00 17,400.00 75.00 17,400.00 570.9 RESETTING MASONRY WALL CY 110. 385.00 42,350.00 350.00 38,500.00 375.00 41,250.00 585.2 STONE FILL, CLASS B CY 385. 31.00 11,935.00 35.00 13,475.00 40.00 15,400.00 585.21 STONE FILL, CLASS B (BRIDGE) CY 2,190. 31.00 67,890.00 35.00 76,650.00 40.00 87,600.00 587.1 KEYED STONE FILL CY 1,950. 35.00 68,250.00 40.00 78,000.00 45.00 87,750.00 592.11 MECHANICALLY STABILIZED EARTH RETAINING WALL SF 71,111. 27.00 1,919,997.00 21.00 1,493,331.00 30.00 2,133,330.00 592.12 MECHANICALLY STABILIZED EARTH RETAINING WALL SF 20,181. 30.00 605,430.00 11.00 221,991.00 30.00 605,430.00 593.231 GEOTEXTILE; SEPARATION CL.3, NON-WOVEN SY 3,250. 2.50 8,125.00 2.00 6,500.00 5.00 16,250.00 593.411 GEOTEXTILE; PERM CONTROL CL.1, NON-WOVEN SY 2,770. 2.50 6,925.00 2.00 5,540.00 3.00 8,310.00 603.00212 12" R.C. PIPE, 2000D LF 103. 40.00 4,120.00 50.00 5,150.00 50.00 5,150.00 603.00215 15" R.C. PIPE, 2000D LF 8,600. 31.00 266,600.00 25.00 215,000.00 52.00 447,200.00 603.00218 18" R.C. PIPE, 2000D LF 1,950. 35.00 68,250.00 27.00 52,650.00 57.00 111,150.00 603.00224 24" R.C. PIPE, 2000D LF 515. 45.00 23,175.00 35.00 18,025.00 62.00 31,930.00 603.00230 30" R.C. PIPE, 2000D LF 1,600. 65.00 104,000.00 42.00 67,200.00 90.00 144,000.00 603.00236 36" R.C. PIPE, 2000D LF 21. 120.00 2,520.00 75.00 1,575.00 120.00 2,520.00 603.00248 48" R.C. PIPE, 2000D LF 4. 275.00 1,100.00 200.00 800.00 200.00 800.00 603.99015 15" TEMPORARY PIPE LF 135. 30.00 4,050.00 35.00 4,725.00 40.00 5,400.00 604.0007 POLYETHYLENE LINER EA 112. 210.00 23,520.00 300.00 33,600.00 150.00 16,800.00 604.0009 OIL-WATER SEPARATORS FOR CATCH BASINS EA 3. 700.00 2,100.00 450.00 1,350.00 600.00 1,800.00 604.12 CATCH BASINS TYPE B U 120. 1,600.00 192,000.00 1,500.00 180,000.00 1,500.00 180,000.00 604.125 CATCH BASINS TYPE B, 5-FOOT DIAMETER U 33. 2,300.00 75,900.00 2,150.00 70,950.00 2,000.00 66,000.00 604.126 CATCH BASINS TYPE B, 6-FOOT DIAMETER U 4. 3,000.00 12,000.00 2,700.00 10,800.00 2,800.00 11,200.00 604.15 CATCH BASINS TYPE E U 21. 1,700.00 35,700.00 2,300.00 48,300.00 1,700.00 35,700.00 604.155 CATCH BASINS TYPE E, 5-FOOT DIAMETER U 4. 2,600.00 10,400.00 2,500.00 10,000.00 2,200.00 8,800.00 604.191 SPECIAL CATCH BASINS U 1. 10,000.00 10,000.00 6,000.00 6,000.00 7,500.00 7,500.00 604.192 SPECIAL CATCH BASINS U 1. 10,000.00 10,000.00 5,650.00 5,650.00 7,000.00 7,000.00 604.193 SPECIAL CATCH BASINS U 1. 8,000.00 8,000.00 6,675.00 6,675.00 7,000.00 7,000.00 604.390 SPECIAL MANHOLE U 8. 400.00 3,200.00 2,000.00 16,000.00 4,500.00 36,000.00 604.4 RECONSTRUCTING CATCH BASINS & DROP INLETS LF 2. 400.00 800.00 500.00 1,000.00 300.00 600.00 604.45 ADJUSTING CATCH BASIN DROP INLET GRATE AND FRAMES EA 13. 325.00 4,225.00 400.00 5,200.00 250.00 3,250.00 604.51 RECONSTRUCT SEWER MANHOLE LF 17. 435.00 7,395.00 400.00 6,800.00 300.00 5,100.00 604.54 RECONSTRUCT MANHOLES (TELEPHONE) EA 2. 500.00 1,000.00 500.00 1,000.00 750.00 1,500.00 604.55 ADJUSTING MANHOLE COVERS AND FRAMES EA 35. 350.00 12,250.00 400.00 14,000.00 250.00 8,750.00 604.6 MANHOLE COVERS & FRAMES EA 1. 400.00 400.00 450.00 450.00 300.00 300.00 604.72 GRATES & FRAMES, TYPE B EA 4. 385.00 1,540.00 400.00 1,600.00 300.00 1,200.00 604.76 GRATES & FRAMES, TYPE F EA 1. 450.00 450.00 500.00 500.00 350.00 350.00 10622-C PAGE 6 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 604.85 WATER REPELLENT FOR EXISTING CB'S AND DI'S EA 11. 200.00 2,200.00 250.00 2,750.00 150.00 1,650.00 605.904 4" PIPE UND. (CONTRACTORS OPTION) LF 225. 16.00 3,600.00 15.00 3,375.00 20.00 4,500.00 606.000 STEEL BEAM FOR BEAM GUARDRAIL LF 6,900. 8.50 58,650.00 8.00 55,200.00 9.00 62,100.00 606.003 STEEL BEAM (THRIE BEAM) FOR BEAM GUARDRAIL LF 2,800. 14.50 40,600.00 14.00 39,200.00 15.00 42,000.00 606.014 6"X8" WOOD POST REPLACE- MENTS FOR BEAM GUARDRAIL POSTS EA 252. 65.00 16,380.00 50.00 12,600.00 50.00 12,600.00 606.0142 6"X8" WOOD POST ASSEMBLIES FOR BEAM GUARDRAIL POSTS EA 250. 16.00 4,000.00 10.00 2,500.00 10.00 2,500.00 606.140 BEAM GUARDRAIL (STANDARD SECTION- WOOD POSTS) LF 4,880. 18.00 87,840.00 18.00 87,840.00 18.00 87,840.00 606.1403 BEAM GUARDRAIL (THRIE BEAM) INCLUDING TRANSITION SECTION LF 20. 65.00 1,300.00 60.00 1,200.00 60.00 1,200.00 606.14422 BEAM GUARDRAIL (THRIE BEAM, DOUB. NEST.) INCL. TRANS. SECTS LF 20. 80.00 1,600.00 90.00 1,800.00 90.00 1,800.00 606.1454 BEAM GUARDRAIL (TERM. UNIT TYPE EAGRT 50 FT.) U 7. 2,500.00 17,500.00 2,500.00 17,500.00 3,000.00 21,000.00 606.1455 BEAM GUARDRAIL (TERM. UNIT EAGRT 25 FT.) U 1. 2,000.00 2,000.00 2,200.00 2,200.00 3,000.00 3,000.00 606.147 BEAM GUARDRAIL (TERMINAL UNIT TYPE G-2) U 6. 550.00 3,300.00 600.00 3,600.00 700.00 4,200.00 606.21403 DOUBLE-FACED BEAM GUARDRAIL (THRIE BEAM) INCLUD. TRANS. SECTION LF 275. 38.00 10,450.00 70.00 19,250.00 70.00 19,250.00 606.402 CONCRETE BARRIER, DOUBLE- FACED LF 1,940. 100.00 194,000.00 85.00 164,900.00 100.00 194,000.00 606.4029 MODIFIED CONCRETE MEDIAN BARRIER LF 1,340. 120.00 160,800.00 110.00 147,400.00 145.00 194,300.00 606.411 CONCRETE BARRIER, SINGLE- FACED, PRECAST LF 615. 90.00 55,350.00 75.00 46,125.00 90.00 55,350.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 11,300. 19.00 214,700.00 25.00 282,500.00 30.00 339,000.00 606.4175 PORTABLE CONCRETE BARRIER ANCHORED LF 480. 50.00 24,000.00 50.00 24,000.00 35.00 16,800.00 606.9523 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 3 U 7. 6,000.00 42,000.00 5,000.00 35,000.00 6,500.00 45,500.00 607.655 CHAIN LINK FENCE WITH VINYL-COATED STEEL FABRIC, 5 FEET HIGH LF 95. 40.00 3,800.00 26.00 2,470.00 30.00 2,850.00 607.659 POST ASSEMBLIES FOR CHAIN LINK FENCE, 5 FT. HIGH EA 2. 180.00 360.00 200.00 400.00 200.00 400.00 607.665 CHAIN LINK FENCE WITH VINYL-COATED STEEL FABRIC, 6 FEET HIGH LF 1,900. 20.00 38,000.00 18.00 34,200.00 20.00 38,000.00 10622-C PAGE 7 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 607.669 POST ASSEMBLIES FOR CHAIN LINK FENCE, 6 FT. HIGH EA 8. 175.00 1,400.00 200.00 1,600.00 250.00 2,000.00 608.12 2" BITUMINOUS SIDEWALK (F) SY 210. 11.00 2,310.00 12.00 2,520.00 15.00 3,150.00 608.24 4" CONCRETE SIDEWALK (F) SY 70. 40.00 2,800.00 40.00 2,800.00 45.00 3,150.00 608.263 6" BRICK EDGED CONCRETE SIDEWALK (F) SY 3,562. 140.00 498,680.00 125.00 445,250.00 85.00 302,770.00 608.28 8" CONCRETE SIDEWALK (F) SY 460. 50.00 23,000.00 50.00 23,000.00 55.00 25,300.00 608.46 6" TEXTURED REINFORCED CONCRETE SIDEWALK (F) SY 1,516. 250.00 379,000.00 224.00 339,584.00 85.00 128,860.00 608.52 DETECTABLE WARNING PAVERS (SIDEWALK RAMPS) SY 60. 500.00 30,000.00 500.00 30,000.00 150.00 9,000.00 609.01 STRAIGHT GRANITE CURB LF 3,300. 15.40 50,820.00 15.00 49,500.00 16.00 52,800.00 609.014 STRAIGHT GRANITE CURB 4" REVEAL LF 800. 15.00 12,000.00 12.00 9,600.00 15.00 12,000.00 609.02 CURVED GRANITE CURB LF 400. 26.00 10,400.00 23.00 9,200.00 25.00 10,000.00 609.0918 STRAIGHT GRANITE CURB 18" HIGH LF 145. 70.00 10,150.00 66.00 9,570.00 130.00 18,850.00 609.21 STRAIGHT GRANITE SLOPE CURB LF 8,900. 12.00 106,800.00 10.50 93,450.00 12.00 106,800.00 609.216 STRAIGHT GRANITE SLOPE CURB 6" HIGH LF 10. 15.00 150.00 13.00 130.00 45.00 450.00 609.22 STRAIGHT GRANITE SLOPE CURB WITH RADIAL JOINTS LF 110. 12.00 1,320.00 10.75 1,182.50 14.00 1,540.00 609.224 STRAIGHT GRANITE SLOPE CURB WITH RADIAL JOINTS, 4" HIGH LF 40. 13.00 520.00 10.75 430.00 14.00 560.00 609.23 CURVED GRANITE SLOPE CURB LF 7. 50.00 350.00 51.00 357.00 14.00 98.00 609.3 STRAIGHT GRANITE CURB (BRIDGE) LF 4,947. 30.00 148,410.00 35.00 173,145.00 32.00 158,304.00 609.35 CURVED GRANITE CURB (BRIDGE) LF 25. 55.00 1,375.00 45.00 1,125.00 42.00 1,050.00 609.5 RESET GRANITE CURB LF 4,745. 7.00 33,215.00 6.00 28,470.00 10.00 47,450.00 609.811 BITUMINOUS CURB, TYPE B (4" REVEAL) LF 1,100. 5.75 6,325.00 2.50 2,750.00 4.00 4,400.00 611.05206 6" CEMENT LINED DUCTILE IRON WATER PIPE , CL.52 LF 20. 50.00 1,000.00 100.00 2,000.00 40.00 800.00 611.811 ADJUSTING/RELOCATING HYDRANTS EA 1. 1,000.00 1,000.00 1,500.00 1,500.00 1,500.00 1,500.00 611.90001 ADJUSTING WATER GATES AND SHUTOFFS SET BY OTHERS EA 22. 200.00 4,400.00 200.00 4,400.00 75.00 1,650.00 613.411 STORMWATER TREATMENT SYSTEM (LEVEL 1) U 1. 50,000.00 50,000.00 36,000.00 36,000.00 125,000.00 125,000.00 613.412 STORMWATER TREATMENT SYSTEM (LEVEL 1) U 1. 110,000.00 110,000.00 90,000.00 90,000.00 50,000.00 50,000.00 614.01 TRANSFORMER SLAB U 3. 700.00 2,100.00 1,500.00 4,500.00 1,500.00 4,500.00 614.121 2 IN CONDUIT CONCRETE ENCASED LF 90. 10.00 900.00 22.00 1,980.00 22.00 1,980.00 614.131 3 IN CONDUIT CONCRETE ENCASED LF 1,300. 14.00 18,200.00 24.00 31,200.00 25.00 32,500.00 10622-C PAGE 8 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 614.132 3" 2-DUCT CONDUIT, CONC. ENCASED LF 100. 20.00 2,000.00 28.00 2,800.00 28.00 2,800.00 614.141 4" CONDUIT, CONC. ENCASED ENCASED LF 80. 16.00 1,280.00 24.00 1,920.00 25.00 2,000.00 614.142 4" 2-DUCT CONDUIT, CONC. ENCASED LF 400. 22.00 8,800.00 30.00 12,000.00 32.00 12,800.00 614.144 4 IN 4 DUCT CONDUIT CONCRETE ENCASED LF 350. 38.00 13,300.00 45.00 15,750.00 45.00 15,750.00 614.152 5 IN 2 DUCT CONDUIT CONCRETE ENCASED LF 275. 38.00 10,450.00 51.00 14,025.00 52.00 14,300.00 614.342 4 IN 2-DUCT STEEL CONDUIT LF 608. 85.00 51,680.00 52.00 31,616.00 55.00 33,440.00 614.511 CONCRETE PULL BOX 14" EA 24. 225.00 5,400.00 300.00 7,200.00 350.00 8,400.00 614.513 CONCRETE PULL BOX 24" EA 27. 425.00 11,475.00 800.00 21,600.00 800.00 21,600.00 614.523 MOLDED PULL BOX 17"X30" EA 9. 375.00 3,375.00 300.00 2,700.00 300.00 2,700.00 614.524 MOLDED PULL BOX 11" X 18" EA 32. 200.00 6,400.00 250.00 8,000.00 250.00 8,000.00 614.7214 2" PVC PLASTIC CONDUIT, SCHEDULE 40 LF 2,200. 5.50 12,100.00 7.00 15,400.00 7.00 15,400.00 614.7218 2" PVC PLASTIC CONDUIT, SCHEDULE 80 LF 1,330. 7.00 9,310.00 18.00 23,940.00 18.00 23,940.00 614.7314 3" PVC PLASTIC CONDUIT, SCHEDULE 40 LF 3,400. 7.00 23,800.00 7.00 23,800.00 7.00 23,800.00 614.7318 3" PVC PLASTIC CONDUIT, SCHEDULE 80 LF 850. 9.00 7,650.00 18.00 15,300.00 18.00 15,300.00 614.7424 4" 2-DUCT PVC CONDUIT, SCHEDULE 40 LF 5,250. 13.00 68,250.00 12.50 65,625.00 14.00 73,500.00 614.7428 4" 2-DUCT PVC CONDUIT, SCHEDULE 80 LF 980. 17.00 16,660.00 30.50 29,890.00 32.00 31,360.00 615.01 TRAFFIC SIGN TYPE A (F) SF 144. 45.00 6,480.00 45.00 6,480.00 45.00 6,480.00 615.012 TRAFFIC SIGN TYPE A, BREAKAWAY MOUNTS (F) SF 144. 60.00 8,640.00 50.00 7,200.00 55.00 7,920.00 615.02 TRAFFIC SIGN TYPE B (F) SF 158. 60.00 9,480.00 75.00 11,850.00 55.00 8,690.00 615.022 TRAFFIC SIGN TYPE B, BREAKAWAY MOUNTS (F) SF 179.83 75.00 13,487.25 85.00 15,285.55 65.00 11,688.95 615.03 TRAFFIC SIGN TYPE C (F) SF 397.8 35.00 13,923.00 50.00 19,890.00 40.00 15,912.00 615.032 TRAFFIC SIGN TYPE C, BREAKAWAY MOUNTS (F) SF 92. 55.00 5,060.00 55.00 5,060.00 60.00 5,520.00 615.034 RELOCATING TRAFFIC SIGN, TYPE C U 16. 110.00 1,760.00 150.00 2,400.00 200.00 3,200.00 615.04 TRAFFIC SIGN TYPE AA (F) SF 144.5 18.00 2,601.00 20.00 2,890.00 20.00 2,890.00 615.043 REMOVING TRAFFIC SIGN TYPE AA U 2. 110.00 220.00 500.00 1,000.00 250.00 500.00 615.046 RELOCATING TRAFFIC SIGN TYPE AA ON NEW FACILITIES SF 1,784.5 17.00 30,336.50 10.00 17,845.00 10.00 17,845.00 615.05 TRAFFIC SIGN TYPE BB (F) SF 14. 25.00 350.00 25.00 350.00 25.00 350.00 615.06 TRAFFIC SIGN TYPE CC (F) SF 164.3 11.00 1,807.30 10.00 1,643.00 15.00 2,464.50 615.10001 FULL TRAFFIC SIGN STRUCTURE U 1. 33,000.00 33,000.00 50,000.00 50,000.00 35,000.00 35,000.00 615.10002 FULL TRAFFIC SIGN STRUCTURE U 1. 30,000.00 30,000.00 50,000.00 50,000.00 35,000.00 35,000.00 10622-C PAGE 9 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 615.10003 FULL TRAFFIC SIGN STRUCTURE U 1. 30,000.00 30,000.00 50,000.00 50,000.00 35,000.00 35,000.00 615.10004 FULL TRAFFIC SIGN STRUCTURE U 1. 83,000.00 83,000.00 75,000.00 75,000.00 70,000.00 70,000.00 615.10301 REMOVING FULL TRAFFIC SIGN STRUCTURE U 1. 7,500.00 7,500.00 10,000.00 10,000.00 5,000.00 5,000.00 615.20001 CANTILEVER TRAFFIC SIGN STRUCTURE U 1. 30,000.00 30,000.00 35,000.00 35,000.00 40,000.00 40,000.00 615.20301 REMOVING CANTILEVER TRAFFIC SIGN STRUCTURE U 1. 2,000.00 2,000.00 5,000.00 5,000.00 2,500.00 2,500.00 615.20302 REMOVING CANTILEVER TRAFFIC SIGN STRUCTURE U 1. 2,000.00 2,000.00 5,000.00 5,000.00 2,500.00 2,500.00 615.30001 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 10,000.00 10,000.00 10,000.00 10,000.00 8,000.00 8,000.00 615.30002 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 9,000.00 9,000.00 10,000.00 10,000.00 8,000.00 8,000.00 615.30003 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 10,000.00 10,000.00 10,000.00 10,000.00 8,000.00 8,000.00 615.30004 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 9,000.00 9,000.00 10,000.00 10,000.00 8,000.00 8,000.00 616.101 TRAFFIC SIGNALS U 1. 113,000.00 113,000.00 150,000.00 150,000.00 160,000.00 160,000.00 616.102 TRAFFIC SIGNALS U 1. 80,000.00 80,000.00 100,000.00 100,000.00 150,000.00 150,000.00 616.103 TRAFFIC SIGNALS U 1. 81,000.00 81,000.00 150,000.00 150,000.00 132,000.00 132,000.00 616.111 VIDEO DETECTION SYSTEM U 1. 16,000.00 16,000.00 10,000.00 10,000.00 17,000.00 17,000.00 616.112 BACKUP POWER CONNECTION U 1. 2,000.00 2,000.00 1,500.00 1,500.00 2,000.00 2,000.00 616.122 COMMUNICATIONS CABLE LF 420. 3.00 1,260.00 3.00 1,260.00 3.00 1,260.00 616.123 COMMUNICATIONS CABLE LF 1,870. 2.50 4,675.00 3.00 5,610.00 3.00 5,610.00 616.141 COMPUTER EQUIPMENT AND SOFTWARE U 1. 8,000.00 8,000.00 9,000.00 9,000.00 8,000.00 8,000.00 616.1415 OPERATIONS AND MAINTENANCE TRAINING U 1. 3,500.00 3,500.00 1,000.00 1,000.00 3,000.00 3,000.00 616.161 TRAFFIC SIGNALS (TEMP.) U 1. 15,000.00 15,000.00 20,000.00 20,000.00 66,000.00 66,000.00 616.162 TRAFFIC SIGNAL (TEMP.) U 1. 13,000.00 13,000.00 20,000.00 20,000.00 66,000.00 66,000.00 616.163 TRAFFIC SIGNAL (TEMP.) U 1. 11,000.00 11,000.00 20,000.00 20,000.00 66,000.00 66,000.00 618.6 UNIFORMED OFFICERS $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 618.601 UNIFORMED OFFICERS WITH VEHICLES $ 1. 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 500,000.00 500,000.00 500,000.00 500,000.00 500,000.00 500,000.00 618.7 FLAGGERS HR 11,360. 17.00 193,120.00 15.00 170,400.00 17.00 193,120.00 619.1 MAINTENANCE OF TRAFFIC U 1. 579,000.00 579,000.00 200,000.00 200,000.00 225,000.00 225,000.00 619.11 MAINTENANCE OF TRAFFIC U 1. 255,000.00 255,000.00 100,000.00 100,000.00 150,000.00 150,000.00 619.253 PORTABLE CHANGEABLE MESSAGE SIGN (UNIT WEEK) UWK 544. 530.00 288,320.00 250.00 136,000.00 400.00 217,600.00 619.27 TRAILER-MOUNTED SPEED LIMIT SIGN U 4. 15,000.00 60,000.00 3,500.00 14,000.00 7,500.00 30,000.00 621.1 RETROREFLECTIVE MEDIAN BARRIER DELINEATOR EA 50. 8.00 400.00 6.00 300.00 15.00 750.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 110. 4.25 467.50 6.00 660.00 6.00 660.00 10622-C PAGE 10 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 621.31 SINGLE DELINEATOR WITH POST EA 300. 30.00 9,000.00 25.00 7,500.00 30.00 9,000.00 621.32 DOUBLE DELINEATOR WITH POST EA 40. 34.00 1,360.00 30.00 1,200.00 40.00 1,600.00 621.725 FLEXIBLE DELINEATORS, BRIDGE (YELLOW) EA 49. 55.00 2,695.00 50.00 2,450.00 20.00 980.00 622.1 STEEL WITNESS MARKERS EA 27. 27.00 729.00 25.00 675.00 30.00 810.00 622.4 STONE BOUNDS EA 19. 300.00 5,700.00 250.00 4,750.00 300.00 5,700.00 625.2 CONCRETE LIGHT POLE BASES, TYPE B EA 19. 530.00 10,070.00 500.00 9,500.00 400.00 7,600.00 625.22 CONCRETE LIGHT POLE BASES, TYPE B (FOR HIGH- WAY LIGHTING) EA 7. 525.00 3,675.00 500.00 3,500.00 400.00 2,800.00 625.52 LIGHT POLE (HIGHWAY) U 7. 1,700.00 11,900.00 1,500.00 10,500.00 1,600.00 11,200.00 625.521 RELOCATED LIGHT POLE (HIGHWAY) U 2. 675.00 1,350.00 500.00 1,000.00 500.00 1,000.00 625.551 ORNAMENTAL STREET LIGHTING, TYPE A EA 15. 9,000.00 135,000.00 8,500.00 127,500.00 9,000.00 135,000.00 625.554 ORNAMENTAL STREET LIGHTING, TYPE D EA 4. 9,000.00 36,000.00 8,500.00 34,000.00 9,000.00 36,000.00 625.555 ORNAMENTAL STREET LIGHTING, TYPE F (WALL MOUNT) EA 4. 9,000.00 36,000.00 8,500.00 34,000.00 9,000.00 36,000.00 628.2 SAWED BITUMINOUS PAVEMENT LF 16,500. 2.40 39,600.00 2.00 33,000.00 2.00 33,000.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 32,000. .11 3,520.00 .11 3,520.00 .15 4,800.00 632.0106 RETROREFLECTIVE PAINT PAVE. MARKING, 6" LINE LF 111,300. .15 16,695.00 .14 15,582.00 .15 16,695.00 632.0108 RETROREFLECTIVE PAINT PAVE. MARKING, 8" LINE LF 300. .40 120.00 .35 105.00 .40 120.00 632.0112 RETROREFLECTIVE PAINT PAVE. MARKING, 12" LINE LF 10,700. .80 8,560.00 .70 7,490.00 1.00 10,700.00 632.0118 RETROREFLECTIVE PAINT PAVE. MARKING, 18" LINE LF 1,100. 1.25 1,375.00 1.05 1,155.00 2.00 2,200.00 632.02 RETROREFLECTIVE PAINT PAVEMENT MARKING, SYMBOL OR WORD SF 2,000. 1.55 3,100.00 1.35 2,700.00 2.00 4,000.00 632.3106 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 6" LINE LF 550. 1.00 550.00 .70 385.00 1.00 550.00 632.3112 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 12" LINE LF 1,700. 1.55 2,635.00 1.35 2,295.00 2.00 3,400.00 632.3118 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 18" LINE LF 530. 2.40 1,272.00 1.95 1,033.50 2.00 1,060.00 632.32 RETROREFLECT. THERMOPLAS. PAVEMENT MARKING, SYMBOL OR WORD SF 1,330. 4.00 5,320.00 3.55 4,721.50 4.00 5,320.00 632.9104 OBLITERATE PAVEMENT MARKING, 4" LINE LF 8,000. .45 3,600.00 .35 2,800.00 .40 3,200.00 632.9106 OBLITERATE PAVEMENT MARKING, 6" LINE LF 27,800. .50 13,900.00 .45 12,510.00 .50 13,900.00 10622-C PAGE 11 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 632.9112 OBLITERATE PAVEMENT MARKING, 12" LINE LF 1,750. 1.00 1,750.00 .75 1,312.50 1.00 1,750.00 632.92 OBLITERATE PAVEMENT MARKING, SYMBOL OR WORD SF 800. 1.30 1,040.00 1.20 960.00 2.00 1,600.00 641. LOAM CY 490. 16.00 7,840.00 30.00 14,700.00 35.00 17,150.00 643.21 FERTILIZER FOR REFERTIL- IZATION LB 6,550. .33 2,161.50 .30 1,965.00 .50 3,275.00 643.22 FERTILIZER FOR REFERTIL- IZATION TON 1. 650.00 650.00 600.00 600.00 1,000.00 1,000.00 645.154 BARK MULCH 4 INCHES DEEP SY 300. 6.50 1,950.00 5.00 1,500.00 7.00 2,100.00 645.3 EROSION STONE TON 500. 25.00 12,500.00 30.00 15,000.00 25.00 12,500.00 645.51 HAY BALES FOR TEMPORARY EROSION CONTROL EA 1,200. 7.00 8,400.00 10.00 12,000.00 6.00 7,200.00 645.531 SILT FENCE LF 4,900. 2.50 12,250.00 3.00 14,700.00 3.00 14,700.00 645.7 STORM WATER POLLUTION PREVENTION PLAN U 1. 5,000.00 5,000.00 10,000.00 10,000.00 30,000.00 30,000.00 645.701 STORM WATER POLLUTION PREVENTION PLAN U 1. 4,500.00 4,500.00 5,000.00 5,000.00 12,000.00 12,000.00 645.71 MONITORING SWPPP AND EROSION AND SEDIMENT CONTROLS HR 775. 52.00 40,300.00 75.00 58,125.00 120.00 93,000.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 39,400. .43 16,942.00 .40 15,760.00 .50 19,700.00 647.1 HUMUS CY 3,450. 14.50 50,025.00 25.00 86,250.00 18.00 62,100.00 662.281 DECOMISSION MONITORING WELLS LF 212. 20.00 4,240.00 20.00 4,240.00 35.00 7,420.00 670.0451 CONSTRUCT AND REMOVE TEMPORARY DETOURS U 1. 350,000.00 350,000.00 200,000.00 200,000.00 100,000.00 100,000.00 670.101 TEMPORARY LIGHTING U 1. 8,000.00 8,000.00 10,000.00 10,000.00 10,000.00 10,000.00 670.1011 TEMPORARY LIGHTING U 1. 6,000.00 6,000.00 10,000.00 10,000.00 11,000.00 11,000.00 670.42 DUCTILE IRON BOLLARD EA 26. 1,500.00 39,000.00 1,400.00 36,400.00 350.00 9,100.00 692. MOBILIZATION U 1. 1,500,000.00 1,500,000.00 2,160,000.00 2,160,000.00 3,100,000.00 3,100,000.00 693. ON-THE-JOB TRAINING OF UNSKILLED WORKERS $ 1. 1,200.00 1,200.00 1,200.00 1,200.00 1,200.00 1,200.00 698.12 FIELD OFFICE TYPE B MON 36. 1,900.00 68,400.00 1,000.00 36,000.00 650.00 23,400.00 698.2 PHYSICAL TESTING LABORATORY MON 36. 1,100.00 39,600.00 200.00 7,200.00 350.00 12,600.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 80,000.00 80,000.00 80,000.00 80,000.00 80,000.00 80,000.00 699.1 MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1002.1 REPAIRS OR REPLACEMENTS AS NEEDED $ 1. 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 1008.11 ALTERATIONS AND ADDITIONS AS NEEDED- UNANTICIPATED WORK $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 1008.14 ALTERATIONS AND ADDITIONS AS NEEDED-SPECIAL TERMINAL PLATFORM $ 1. 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00 10622-C PAGE 12 ------------------------------------------------------------------------------------------------------------------------------------ ITEM D E F NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 1008.6 ALTERATIONS AND ADDITIONS AS NEEDED-ELECTRICAL SERVICE CONNECTION $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1008.61 BILLBOARD SIGN REMOVAL $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 1009.2 TREATMENT OR DISPOSAL OF CONTAMINATED SOIL/GROUNDWATER $ 1. 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 1009.21 TREATMENT OR DISPOSAL OF CONTAMINATED SOIL/GROUNDWATER $ 1. 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 1009.3 MONITORING, TREATMENT AND DISPOSAL ASBESTOS FILL $ 1. 75,000.00 75,000.00 75,000.00 75,000.00 75,000.00 75,000.00 1009.31 MONITORING, TREATMENT AND DISPOSAL ASBESTOS FILL $ 1. 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 1009.4 BUILDING ASBESTOS ABATEMENT $ 1. 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 1009.5 DISPOSAL FUEL SLUDGE $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 1009.7 PROJECT OPERATIONS PLAN $ 1. 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 1010.11 FUEL ADJUSTMENT, DIESEL $ 1. 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 1010.12 FUEL ADJUSTMENT, GASOLINE $ 1. 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 55,000.00 1010.41 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR CONCRETE $ 1. 40,000.00 40,000.00 40,000.00 40,000.00 40,000.00 40,000.00 1010.42 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR CONCRETE $ 1. 60,000.00 60,000.00 60,000.00 60,000.00 60,000.00 60,000.00 1010.43 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR CONCRETE $ 1. 1,500.00 1,500.00 1,500.00 1,500.00 1,500.00 1,500.00 $30,266,492.55 $30,875,185.00 $32,528,829.91 THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: MANCHESTER A000 (320), 10622-C MANCHESTER X-A000 (294), 14025-C COUNTIES AND CODES: HILLSBOROUGH 011 DATE BIDS OPEN: JUNE 29, 2005 SCOPE OF WORK: ROAD AND BRIDGE IMPROVEMENTS LOCATION: EXIT 5 INTERCHANGE ALONG I-293 AND GRANITE STREET CORRIDORS COMPLETION DATE: MAY 30, 2008 A THE MIDDLESEX CORPORATION ONE SPECTACLE POND ROAD, LITTLETON, MA 01460 $28,687,750.00 B REED & REED INC P O BOX 370, WOOLWICH, ME 04579 $28,768,567.27 C R.S. AUDLEY, INC. 609 ROUTE 3A, BOW, NH 03304 $28,984,650.45 D WEAVER BROS. CONST. CO., INC. P.O. BOX 132C CONCORD, NH 03302 $30,266,492.55 E E. D. SWETT, INC. 8 INDUSTRIAL PARK DR., CONCORD, NH 03301 $30,875,185.00 F PARK CONSTRUCTION CORP P O BOX 600 FITZWILLIAM, NH 03447 $32,528,829.91 G R. ZOPPO CORP. 160 OLD MAPLE STREET, STOUGHTON, MA 02072 $34,343,677.61 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 201.1 CLEARING AND GRUBBING (F) A 1.7 20,000.00 34,000.00 201.21 REMOVING SMALL TREES EA 6. 500.00 3,000.00 201.22 REMOVING LARGE TREES EA 2. 1,000.00 2,000.00 202.201 DEMOLISHING BUILDINGS U 1. 70,000.00 70,000.00 202.31 FILL ABANDONED PIPE CY 9. 200.00 1,800.00 202.41 REMOVAL OF EXISTING PIPE 0-24" DIAMETER LF 199. 50.00 9,950.00 202.5 REMOVAL OF CATCH BASINS, DROP INLETS, AND MANHOLES EA 31. 650.00 20,150.00 202.6 CURB REMOVAL FOR STORAGE LF 5,525. 12.00 66,300.00 202.7 REMOVAL OF GUARDRAIL (F) LF 13,800. 3.00 41,400.00 202.9 REMOVAL OF FUEL TANKS U 1. 30,000.00 30,000.00 203.1 COMMON EXCAVATION CY 67,600. 20.00 1,352,000.00 203.2 ROCK EXCAVATION CY 340. 100.00 34,000.00 203.35 HANDLING EXCAVATED, CONTAMINATED SOIL CY 22,245. 3.00 66,735.00 203.37 SEGREGATING AND REHANDLING, NON-CONTAMINATED SOIL CY 800. 20.00 16,000.00 10622-C PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 203.6 EMBANKMENT-IN-PLACE (F) CY 51,536. 15.00 773,040.00 203.62 EMBANKMENT-IN-PLACE, REPLACEMENT MATERIAL CY 2,900. 20.00 58,000.00 206.1 COMMON STRUCTURE EXCAVATION CY 1,650. 40.00 66,000.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 100. 100.00 10,000.00 206.2 ROCK STRUCTURE EXCAVATION CY 160. 150.00 24,000.00 207.3 UNCLASSIFIED CHANNEL EXCAVATION CY 2,108. 25.00 52,700.00 209.1 GRANULAR BACKFILL CY 165. 30.00 4,950.00 209.2 GRANULAR BACKFILL (BRIDGE) CY 65,185. 30.00 1,955,550.00 209.2014 GRANULAR BACKFILL (COARSE AGGREGATE) CY 3,521. 30.00 105,630.00 209.3 GRANULAR BACKFILL (SAND) CY 118. 25.00 2,950.00 209.4 GRANULAR BACKFILL (GRAV) CY 110. 25.00 2,750.00 210.62 GROUNDWATER OBSERVATION WELL (DRILLED) LF 192. 40.00 7,680.00 210.7 PROTECTIVE CASING WITH CAP AND LOCK EA 12. 100.00 1,200.00 214. FINE GRADING U 1. 200,000.00 200,000.00 214.1 FINE GRADING U 1. 50,000.00 50,000.00 304.1 SAND (F) CY 19,687. 20.00 393,740.00 304.2 GRAVEL (F) CY 18,321. 25.00 458,025.00 304.3 CRUSHED GRAVEL (F) CY 24,585. 30.00 737,550.00 304.31 CRUSHED GRAVEL FOR SHIMMING CY 500. 30.00 15,000.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 150. 35.00 5,250.00 403.1105 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (SUPERPAVE) TON 27,905. 43.00 1,199,915.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 670. 90.00 60,300.00 403.911 HOT BITUMINOUS BRIDGE PAVEMENT, 1" BASE COURSE (F) TON 334. 90.00 30,060.00 403.98 HOT BITUMINOUS CONCRETE LEVELING, MACHINE METHOD TON 160. 60.00 9,600.00 403.989 HOT BITUMINOUS CONCRETE LEVELING, MACH. METHOD (NIGHT) TON 175. 70.00 12,250.00 403.99 TEMPORARY BITUMINOUS PAVEMENT TON 3,450. 60.00 207,000.00 411.1 HOT BITUMINOUS CONCRETE LEVELING COURSE TON 225. 70.00 15,750.00 413.1 HOT-POURED CRACK SEALANT LB 8,250. 2.00 16,500.00 417. COLD PLANING BITUMINOUS SURFACES (F) SY 5,317. 6.00 31,902.00 417.19 COLD PLANING BITUMINOUS SURFACES (NIGHT) (F) SY 4,650. 7.00 32,550.00 10622-C PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 502.101 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 400,000.00 400,000.00 502.102 REMOVAL OF EXISTING BRIDGE STRUCTURE U 1. 150,000.00 150,000.00 503.201 COFFERDAMS U 1. 50,000.00 50,000.00 503.202 COFFERDAMS U 1. 80,000.00 80,000.00 503.203 COFFERDAMS U 1. 80,000.00 80,000.00 503.204 COFFERDAMS U 1. 500,000.00 500,000.00 503.205 COFFERDAMS U 1. 20,000.00 20,000.00 503.206 COFFERDAMS U 1. 20,000.00 20,000.00 503.207 COFFERDAMS U 1. 20,000.00 20,000.00 503.208 COFFERDAMS U 1. 20,000.00 20,000.00 503.209 COFFERDAMS U 1. 10,000.00 10,000.00 503.210 COFFERDAMS U 1. 500,000.00 500,000.00 503.211 COFFERDAMS U 1. 1.00 1.00 503.212 COFFERDAMS U 1. 350,000.00 350,000.00 504.101 COMMON BRIDGE EXCAVATION CY 43,377. 20.00 867,540.00 504.2 ROCK BRIDGE EXCAVATION CY 644. 100.00 64,400.00 508. STRUCTURAL FILL CY 1,250. 25.00 31,250.00 510.11 PILE DRIVING EQUIPMENT (MINI-PILES) U 1. 20,000.00 20,000.00 510.2 PILE LOADING TESTS EA 2. 25,000.00 50,000.00 510.501 C-I-P CONCRETE PILES (DRILLED MINI-PILES) LF 24,985. 70.00 1,748,950.00 511.00 CONCRETE BRIDGE DECK PAVEMENT REMOVAL (F) SY 2,276. 15.00 34,140.00 511.02 PREPARATION FOR PARTIAL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 569. 50.00 28,450.00 511.03 PREPARATION FOR FULL DEPTH CONCRETE BRIDGE DECK REPAIRS SY 114. 100.00 11,400.00 512.0201 PREPARATION FOR CONCRETE REPAIRS, CLASS II SY 50. 200.00 10,000.00 520.01 CONCRETE CLASS AA CY 51. 200.00 10,200.00 520.0102 CONCRETE CLASS AA (QC/QA) (F) CY 3,212. 300.00 963,600.00 520.028 PRECAST CONCRETE ARCHITECTURAL PANELS U 1. 300,000.00 300,000.00 520.12 CONCRETE CLASS A, ABOVE FOOTINGS (F) CY 1,050. 500.00 525,000.00 520.2 CONCRETE CLASS B CY 210. 260.00 54,600.00 520.21 CONCRETE CLASS B, FOOTINGS (F) CY 2,750. 300.00 825,000.00 520.421 CONCRETE CLASS F, FLOWABLE FILL, EXCAVATABLE CY 52. 100.00 5,200.00 520.7002 CONCRETE BRIDGE DECK (QC/QA) (F) CY 780. 600.00 468,000.00 10622-C PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 532.1 ANTI-GRAFFITI COATING SF 6,230. 3.00 18,690.00 534.1 WATER REPELLENT (LINSEED OIL) GAL 20. 50.00 1,000.00 534.3 WATER REPELLENT (SILANE- SILOXANE) GAL 773. 50.00 38,650.00 536.11 EPOXY COATING FOR CONCRETE (F) SF 1,550. 10.00 15,500.00 537. CONCRETE SEALER (F) SF 6,500. 1.00 6,500.00 538.2 BARRIER MEMBRANE, VERTICAL SURFACES (F) SY 110. 50.00 5,500.00 538.3 BARRIER MEMBRANE, LIQUID SPRAY (F) SY 3,725. 60.00 223,500.00 538.5 BARRIER MEMBRANE, WELDED BY TORCH (F) SY 5,456. 25.00 136,400.00 541.2 PVC WATERSTOPS, NH TYPE 2 (F) LF 113. 5.00 565.00 541.3 PVC WATERSTOPS, NH TYPE 3 (F) LF 55. 5.00 275.00 541.5 PVC WATERSTOPS, NH TYPE 5 (F) LF 119. 10.00 1,190.00 544. REINFORCING STEEL (F) LB 335,276. 1.00 335,276.00 544.1 REINFORCING STEEL (ROADWAY) LB 15,300. 1.00 15,300.00 544.11 REINFORCING STEEL-MECH'L. CONNECTORS (F) LB 534. 4.00 2,136.00 544.2 REINFORCING STEEL, EPOXY COATED (F) LB 614,717. 1.00 614,717.00 544.21 REINFORCING STEEL, EPOXY COATED-MECHANICAL CONNECTORS (F) LB 4,548. 4.00 18,192.00 547. SHEAR CONNECTORS (F) EA 7,137. 3.00 21,411.00 548.21 ELASTOMERIC BEARING ASSEMBLIES (F) EA 13. 3,000.00 39,000.00 550.1 STRUCTURAL STEEL (F) LB 2,017,267. 1.03 2,077,785.01 550.2 BRIDGE SHOES (F) EA 13. 2,000.00 26,000.00 559.4 ELASTOMERIC PLUG TYPE EXPANSION JOINT (F) LF 410. 75.00 30,750.00 561.04 REHABILITATE EXPANSION JOINT U 1. 15,000.00 15,000.00 561.110 PREFABRICATED EXPANSION JOINT, TYPE A (F) LF 122. 500.00 61,000.00 563.22 BRIDGE RAIL T2 (F) LF 2,379. 100.00 237,900.00 563.223 BRIDGE RAIL T2 WITH SNOW SCREENING (F) LF 2,405. 120.00 288,600.00 563.225 BRIDGE RAIL T4 TO T2 TRANSITION (F) LF 52. 130.00 6,760.00 563.24 BRIDGE RAIL T4 (F) LF 139. 100.00 13,900.00 565.22 BRIDGE APPROACH RAIL T2 (F) LF 256. 100.00 25,600.00 565.24 BRIDGE APPROACH RAIL T4 (F) LF 110. 100.00 11,000.00 10622-C PAGE 5 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 565.63 BRIDGE APPROACH RAIL E LF 232. 80.00 18,560.00 570.9 RESETTING MASONRY WALL CY 110. 350.00 38,500.00 585.2 STONE FILL, CLASS B CY 385. 75.00 28,875.00 585.21 STONE FILL, CLASS B (BRIDGE) CY 2,190. 75.00 164,250.00 587.1 KEYED STONE FILL CY 1,950. 75.00 146,250.00 592.11 MECHANICALLY STABILIZED EARTH RETAINING WALL SF 71,111. 25.00 1,777,775.00 592.12 MECHANICALLY STABILIZED EARTH RETAINING WALL SF 20,181. 1.00 20,181.00 593.231 GEOTEXTILE; SEPARATION CL.3, NON-WOVEN SY 3,250. 1.00 3,250.00 593.411 GEOTEXTILE; PERM CONTROL CL.1, NON-WOVEN SY 2,770. 1.00 2,770.00 603.00212 12" R.C. PIPE, 2000D LF 103. 100.00 10,300.00 603.00215 15" R.C. PIPE, 2000D LF 8,600. 110.00 946,000.00 603.00218 18" R.C. PIPE, 2000D LF 1,950. 120.00 234,000.00 603.00224 24" R.C. PIPE, 2000D LF 515. 140.00 72,100.00 603.00230 30" R.C. PIPE, 2000D LF 1,600. 150.00 240,000.00 603.00236 36" R.C. PIPE, 2000D LF 21. 400.00 8,400.00 603.00248 48" R.C. PIPE, 2000D LF 4. 1,000.00 4,000.00 603.99015 15" TEMPORARY PIPE LF 135. 50.00 6,750.00 604.0007 POLYETHYLENE LINER EA 112. 100.00 11,200.00 604.0009 OIL-WATER SEPARATORS FOR CATCH BASINS EA 3. 500.00 1,500.00 604.12 CATCH BASINS TYPE B U 120. 2,000.00 240,000.00 604.125 CATCH BASINS TYPE B, 5-FOOT DIAMETER U 33. 3,000.00 99,000.00 604.126 CATCH BASINS TYPE B, 6-FOOT DIAMETER U 4. 4,000.00 16,000.00 604.15 CATCH BASINS TYPE E U 21. 2,000.00 42,000.00 604.155 CATCH BASINS TYPE E, 5-FOOT DIAMETER U 4. 3,000.00 12,000.00 604.191 SPECIAL CATCH BASINS U 1. 5,000.00 5,000.00 604.192 SPECIAL CATCH BASINS U 1. 5,000.00 5,000.00 604.193 SPECIAL CATCH BASINS U 1. 5,000.00 5,000.00 604.390 SPECIAL MANHOLE U 8. 5,000.00 40,000.00 604.4 RECONSTRUCTING CATCH BASINS & DROP INLETS LF 2. 500.00 1,000.00 604.45 ADJUSTING CATCH BASIN DROP INLET GRATE AND FRAMES EA 13. 300.00 3,900.00 604.51 RECONSTRUCT SEWER MANHOLE LF 17. 500.00 8,500.00 604.54 RECONSTRUCT MANHOLES (TELEPHONE) EA 2. 1,200.00 2,400.00 604.55 ADJUSTING MANHOLE COVERS AND FRAMES EA 35. 300.00 10,500.00 604.6 MANHOLE COVERS & FRAMES EA 1. 500.00 500.00 604.72 GRATES & FRAMES, TYPE B EA 4. 500.00 2,000.00 604.76 GRATES & FRAMES, TYPE F EA 1. 500.00 500.00 10622-C PAGE 6 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 604.85 WATER REPELLENT FOR EXISTING CB'S AND DI'S EA 11. 200.00 2,200.00 605.904 4" PIPE UND. (CONTRACTORS OPTION) LF 225. 30.00 6,750.00 606.000 STEEL BEAM FOR BEAM GUARDRAIL LF 6,900. 8.00 55,200.00 606.003 STEEL BEAM (THRIE BEAM) FOR BEAM GUARDRAIL LF 2,800. 15.00 42,000.00 606.014 6"X8" WOOD POST REPLACE- MENTS FOR BEAM GUARDRAIL POSTS EA 252. 55.00 13,860.00 606.0142 6"X8" WOOD POST ASSEMBLIES FOR BEAM GUARDRAIL POSTS EA 250. 12.00 3,000.00 606.140 BEAM GUARDRAIL (STANDARD SECTION- WOOD POSTS) LF 4,880. 20.00 97,600.00 606.1403 BEAM GUARDRAIL (THRIE BEAM) INCLUDING TRANSITION SECTION LF 20. 70.00 1,400.00 606.14422 BEAM GUARDRAIL (THRIE BEAM, DOUB. NEST.) INCL. TRANS. SECTS LF 20. 80.00 1,600.00 606.1454 BEAM GUARDRAIL (TERM. UNIT TYPE EAGRT 50 FT.) U 7. 3,000.00 21,000.00 606.1455 BEAM GUARDRAIL (TERM. UNIT EAGRT 25 FT.) U 1. 3,000.00 3,000.00 606.147 BEAM GUARDRAIL (TERMINAL UNIT TYPE G-2) U 6. 700.00 4,200.00 606.21403 DOUBLE-FACED BEAM GUARDRAIL (THRIE BEAM) INCLUD. TRANS. SECTION LF 275. 70.00 19,250.00 606.402 CONCRETE BARRIER, DOUBLE- FACED LF 1,940. 80.00 155,200.00 606.4029 MODIFIED CONCRETE MEDIAN BARRIER LF 1,340. 110.00 147,400.00 606.411 CONCRETE BARRIER, SINGLE- FACED, PRECAST LF 615. 80.00 49,200.00 606.417 PORTABLE CONCRETE BARRIER FOR TRAFFIC CONTROL LF 11,300. 30.00 339,000.00 606.4175 PORTABLE CONCRETE BARRIER ANCHORED LF 480. 50.00 24,000.00 606.9523 TEMP. IMPACT ATTENUATION DEVICE (NON-REDIRECTIVE) TEST LEVEL 3 U 7. 12,000.00 84,000.00 607.655 CHAIN LINK FENCE WITH VINYL-COATED STEEL FABRIC, 5 FEET HIGH LF 95. 30.00 2,850.00 607.659 POST ASSEMBLIES FOR CHAIN LINK FENCE, 5 FT. HIGH EA 2. 220.00 440.00 607.665 CHAIN LINK FENCE WITH VINYL-COATED STEEL FABRIC, 6 FEET HIGH LF 1,900. 20.00 38,000.00 10622-C PAGE 7 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 607.669 POST ASSEMBLIES FOR CHAIN LINK FENCE, 6 FT. HIGH EA 8. 240.00 1,920.00 608.12 2" BITUMINOUS SIDEWALK (F) SY 210. 15.00 3,150.00 608.24 4" CONCRETE SIDEWALK (F) SY 70. 35.00 2,450.00 608.263 6" BRICK EDGED CONCRETE SIDEWALK (F) SY 3,562. 120.00 427,440.00 608.28 8" CONCRETE SIDEWALK (F) SY 460. 45.00 20,700.00 608.46 6" TEXTURED REINFORCED CONCRETE SIDEWALK (F) SY 1,516. 200.00 303,200.00 608.52 DETECTABLE WARNING PAVERS (SIDEWALK RAMPS) SY 60. 250.00 15,000.00 609.01 STRAIGHT GRANITE CURB LF 3,300. 15.00 49,500.00 609.014 STRAIGHT GRANITE CURB 4" REVEAL LF 800. 15.00 12,000.00 609.02 CURVED GRANITE CURB LF 400. 25.00 10,000.00 609.0918 STRAIGHT GRANITE CURB 18" HIGH LF 145. 60.00 8,700.00 609.21 STRAIGHT GRANITE SLOPE CURB LF 8,900. 11.00 97,900.00 609.216 STRAIGHT GRANITE SLOPE CURB 6" HIGH LF 10. 12.00 120.00 609.22 STRAIGHT GRANITE SLOPE CURB WITH RADIAL JOINTS LF 110. 11.00 1,210.00 609.224 STRAIGHT GRANITE SLOPE CURB WITH RADIAL JOINTS, 4" HIGH LF 40. 11.00 440.00 609.23 CURVED GRANITE SLOPE CURB LF 7. 50.00 350.00 609.3 STRAIGHT GRANITE CURB (BRIDGE) LF 4,947. 32.00 158,304.00 609.35 CURVED GRANITE CURB (BRIDGE) LF 25. 42.00 1,050.00 609.5 RESET GRANITE CURB LF 4,745. 6.00 28,470.00 609.811 BITUMINOUS CURB, TYPE B (4" REVEAL) LF 1,100. 3.00 3,300.00 611.05206 6" CEMENT LINED DUCTILE IRON WATER PIPE , CL.52 LF 20. 200.00 4,000.00 611.811 ADJUSTING/RELOCATING HYDRANTS EA 1. 1,500.00 1,500.00 611.90001 ADJUSTING WATER GATES AND SHUTOFFS SET BY OTHERS EA 22. 100.00 2,200.00 613.411 STORMWATER TREATMENT SYSTEM (LEVEL 1) U 1. 100,000.00 100,000.00 613.412 STORMWATER TREATMENT SYSTEM (LEVEL 1) U 1. 60,000.00 60,000.00 614.01 TRANSFORMER SLAB U 3. 700.00 2,100.00 614.121 2 IN CONDUIT CONCRETE ENCASED LF 90. 8.00 720.00 614.131 3 IN CONDUIT CONCRETE ENCASED LF 1,300. 12.00 15,600.00 10622-C PAGE 8 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 614.132 3" 2-DUCT CONDUIT, CONC. ENCASED LF 100. 16.00 1,600.00 614.141 4" CONDUIT, CONC. ENCASED ENCASED LF 80. 14.00 1,120.00 614.142 4" 2-DUCT CONDUIT, CONC. ENCASED LF 400. 20.00 8,000.00 614.144 4 IN 4 DUCT CONDUIT CONCRETE ENCASED LF 350. 35.00 12,250.00 614.152 5 IN 2 DUCT CONDUIT CONCRETE ENCASED LF 275. 35.00 9,625.00 614.342 4 IN 2-DUCT STEEL CONDUIT LF 608. 80.00 48,640.00 614.511 CONCRETE PULL BOX 14" EA 24. 185.00 4,440.00 614.513 CONCRETE PULL BOX 24" EA 27. 375.00 10,125.00 614.523 MOLDED PULL BOX 17"X30" EA 9. 350.00 3,150.00 614.524 MOLDED PULL BOX 11" X 18" EA 32. 185.00 5,920.00 614.7214 2" PVC PLASTIC CONDUIT, SCHEDULE 40 LF 2,200. 5.00 11,000.00 614.7218 2" PVC PLASTIC CONDUIT, SCHEDULE 80 LF 1,330. 6.00 7,980.00 614.7314 3" PVC PLASTIC CONDUIT, SCHEDULE 40 LF 3,400. 6.00 20,400.00 614.7318 3" PVC PLASTIC CONDUIT, SCHEDULE 80 LF 850. 8.00 6,800.00 614.7424 4" 2-DUCT PVC CONDUIT, SCHEDULE 40 LF 5,250. 12.00 63,000.00 614.7428 4" 2-DUCT PVC CONDUIT, SCHEDULE 80 LF 980. 15.00 14,700.00 615.01 TRAFFIC SIGN TYPE A (F) SF 144. 42.00 6,048.00 615.012 TRAFFIC SIGN TYPE A, BREAKAWAY MOUNTS (F) SF 144. 50.00 7,200.00 615.02 TRAFFIC SIGN TYPE B (F) SF 158. 50.00 7,900.00 615.022 TRAFFIC SIGN TYPE B, BREAKAWAY MOUNTS (F) SF 179.83 100.00 17,983.00 615.03 TRAFFIC SIGN TYPE C (F) SF 397.8 35.00 13,923.00 615.032 TRAFFIC SIGN TYPE C, BREAKAWAY MOUNTS (F) SF 92. 60.00 5,520.00 615.034 RELOCATING TRAFFIC SIGN, TYPE C U 16. 170.00 2,720.00 615.04 TRAFFIC SIGN TYPE AA (F) SF 144.5 18.00 2,601.00 615.043 REMOVING TRAFFIC SIGN TYPE AA U 2. 250.00 500.00 615.046 RELOCATING TRAFFIC SIGN TYPE AA ON NEW FACILITIES SF 1,784.5 8.00 14,276.00 615.05 TRAFFIC SIGN TYPE BB (F) SF 14. 20.00 280.00 615.06 TRAFFIC SIGN TYPE CC (F) SF 164.3 12.00 1,971.60 615.10001 FULL TRAFFIC SIGN STRUCTURE U 1. 30,000.00 30,000.00 615.10002 FULL TRAFFIC SIGN STRUCTURE U 1. 30,000.00 30,000.00 10622-C PAGE 9 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 615.10003 FULL TRAFFIC SIGN STRUCTURE U 1. 30,000.00 30,000.00 615.10004 FULL TRAFFIC SIGN STRUCTURE U 1. 70,000.00 70,000.00 615.10301 REMOVING FULL TRAFFIC SIGN STRUCTURE U 1. 5,000.00 5,000.00 615.20001 CANTILEVER TRAFFIC SIGN STRUCTURE U 1. 30,000.00 30,000.00 615.20301 REMOVING CANTILEVER TRAFFIC SIGN STRUCTURE U 1. 3,000.00 3,000.00 615.20302 REMOVING CANTILEVER TRAFFIC SIGN STRUCTURE U 1. 3,000.00 3,000.00 615.30001 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 8,000.00 8,000.00 615.30002 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 8,000.00 8,000.00 615.30003 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 8,000.00 8,000.00 615.30004 BRIDGE MOUNTED TRAFFIC SIGN STRUCTURE U 1. 8,000.00 8,000.00 616.101 TRAFFIC SIGNALS U 1. 100,000.00 100,000.00 616.102 TRAFFIC SIGNALS U 1. 70,000.00 70,000.00 616.103 TRAFFIC SIGNALS U 1. 80,000.00 80,000.00 616.111 VIDEO DETECTION SYSTEM U 1. 15,000.00 15,000.00 616.112 BACKUP POWER CONNECTION U 1. 2,000.00 2,000.00 616.122 COMMUNICATIONS CABLE LF 420. 2.00 840.00 616.123 COMMUNICATIONS CABLE LF 1,870. 2.00 3,740.00 616.141 COMPUTER EQUIPMENT AND SOFTWARE U 1. 8,000.00 8,000.00 616.1415 OPERATIONS AND MAINTENANCE TRAINING U 1. 3,000.00 3,000.00 616.161 TRAFFIC SIGNALS (TEMP.) U 1. 15,000.00 15,000.00 616.162 TRAFFIC SIGNAL (TEMP.) U 1. 10,000.00 10,000.00 616.163 TRAFFIC SIGNAL (TEMP.) U 1. 10,000.00 10,000.00 618.6 UNIFORMED OFFICERS $ 1. 50,000.00 50,000.00 618.601 UNIFORMED OFFICERS WITH VEHICLES $ 1. 35,000.00 35,000.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 500,000.00 500,000.00 618.7 FLAGGERS HR 11,360. 30.00 340,800.00 619.1 MAINTENANCE OF TRAFFIC U 1. 200,000.00 200,000.00 619.11 MAINTENANCE OF TRAFFIC U 1. 40,000.00 40,000.00 619.253 PORTABLE CHANGEABLE MESSAGE SIGN (UNIT WEEK) UWK 544. 200.00 108,800.00 619.27 TRAILER-MOUNTED SPEED LIMIT SIGN U 4. 5,000.00 20,000.00 621.1 RETROREFLECTIVE MEDIAN BARRIER DELINEATOR EA 50. 8.00 400.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 110. 5.00 550.00 10622-C PAGE 10 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 621.31 SINGLE DELINEATOR WITH POST EA 300. 25.00 7,500.00 621.32 DOUBLE DELINEATOR WITH POST EA 40. 28.00 1,120.00 621.725 FLEXIBLE DELINEATORS, BRIDGE (YELLOW) EA 49. 21.00 1,029.00 622.1 STEEL WITNESS MARKERS EA 27. 21.00 567.00 622.4 STONE BOUNDS EA 19. 260.00 4,940.00 625.2 CONCRETE LIGHT POLE BASES, TYPE B EA 19. 500.00 9,500.00 625.22 CONCRETE LIGHT POLE BASES, TYPE B (FOR HIGH- WAY LIGHTING) EA 7. 500.00 3,500.00 625.52 LIGHT POLE (HIGHWAY) U 7. 1,500.00 10,500.00 625.521 RELOCATED LIGHT POLE (HIGHWAY) U 2. 600.00 1,200.00 625.551 ORNAMENTAL STREET LIGHTING, TYPE A EA 15. 8,000.00 120,000.00 625.554 ORNAMENTAL STREET LIGHTING, TYPE D EA 4. 8,000.00 32,000.00 625.555 ORNAMENTAL STREET LIGHTING, TYPE F (WALL MOUNT) EA 4. 8,000.00 32,000.00 628.2 SAWED BITUMINOUS PAVEMENT LF 16,500. 1.00 16,500.00 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 32,000. .10 3,200.00 632.0106 RETROREFLECTIVE PAINT PAVE. MARKING, 6" LINE LF 111,300. .15 16,695.00 632.0108 RETROREFLECTIVE PAINT PAVE. MARKING, 8" LINE LF 300. .35 105.00 632.0112 RETROREFLECTIVE PAINT PAVE. MARKING, 12" LINE LF 10,700. .70 7,490.00 632.0118 RETROREFLECTIVE PAINT PAVE. MARKING, 18" LINE LF 1,100. 1.00 1,100.00 632.02 RETROREFLECTIVE PAINT PAVEMENT MARKING, SYMBOL OR WORD SF 2,000. 1.50 3,000.00 632.3106 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 6" LINE LF 550. 1.00 550.00 632.3112 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 12" LINE LF 1,700. 1.00 1,700.00 632.3118 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 18" LINE LF 530. 1.00 530.00 632.32 RETROREFLECT. THERMOPLAS. PAVEMENT MARKING, SYMBOL OR WORD SF 1,330. 4.00 5,320.00 632.9104 OBLITERATE PAVEMENT MARKING, 4" LINE LF 8,000. .40 3,200.00 632.9106 OBLITERATE PAVEMENT MARKING, 6" LINE LF 27,800. .60 16,680.00 10622-C PAGE 11 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 632.9112 OBLITERATE PAVEMENT MARKING, 12" LINE LF 1,750. .80 1,400.00 632.92 OBLITERATE PAVEMENT MARKING, SYMBOL OR WORD SF 800. 2.00 1,600.00 641. LOAM CY 490. 30.00 14,700.00 643.21 FERTILIZER FOR REFERTIL- IZATION LB 6,550. .30 1,965.00 643.22 FERTILIZER FOR REFERTIL- IZATION TON 1. 600.00 600.00 645.154 BARK MULCH 4 INCHES DEEP SY 300. 6.00 1,800.00 645.3 EROSION STONE TON 500. 30.00 15,000.00 645.51 HAY BALES FOR TEMPORARY EROSION CONTROL EA 1,200. 10.00 12,000.00 645.531 SILT FENCE LF 4,900. 5.00 24,500.00 645.7 STORM WATER POLLUTION PREVENTION PLAN U 1. 3,000.00 3,000.00 645.701 STORM WATER POLLUTION PREVENTION PLAN U 1. 3,000.00 3,000.00 645.71 MONITORING SWPPP AND EROSION AND SEDIMENT CONTROLS HR 775. 80.00 62,000.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS SY 39,400. .50 19,700.00 647.1 HUMUS CY 3,450. 20.00 69,000.00 662.281 DECOMISSION MONITORING WELLS LF 212. 12.00 2,544.00 670.0451 CONSTRUCT AND REMOVE TEMPORARY DETOURS U 1. 200,000.00 200,000.00 670.101 TEMPORARY LIGHTING U 1. 7,000.00 7,000.00 670.1011 TEMPORARY LIGHTING U 1. 6,000.00 6,000.00 670.42 DUCTILE IRON BOLLARD EA 26. 1,500.00 39,000.00 692. MOBILIZATION U 1. 3,000,000.00 3,000,000.00 693. ON-THE-JOB TRAINING OF UNSKILLED WORKERS $ 1. 1,200.00 1,200.00 698.12 FIELD OFFICE TYPE B MON 36. 2,500.00 90,000.00 698.2 PHYSICAL TESTING LABORATORY MON 36. 1,500.00 54,000.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 80,000.00 80,000.00 699.1 MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 20,000.00 20,000.00 1002.1 REPAIRS OR REPLACEMENTS AS NEEDED $ 1. 15,000.00 15,000.00 1008.11 ALTERATIONS AND ADDITIONS AS NEEDED- UNANTICIPATED WORK $ 1. 50,000.00 50,000.00 1008.14 ALTERATIONS AND ADDITIONS AS NEEDED-SPECIAL TERMINAL PLATFORM $ 1. 3,000.00 3,000.00 10622-C PAGE 12 ------------------------------------------------------------------------------------------------------------------------------------ ITEM G NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 1008.6 ALTERATIONS AND ADDITIONS AS NEEDED-ELECTRICAL SERVICE CONNECTION $ 1. 5,000.00 5,000.00 1008.61 BILLBOARD SIGN REMOVAL $ 1. 10,000.00 10,000.00 1009.2 TREATMENT OR DISPOSAL OF CONTAMINATED SOIL/GROUNDWATER $ 1. 100,000.00 100,000.00 1009.21 TREATMENT OR DISPOSAL OF CONTAMINATED SOIL/GROUNDWATER $ 1. 100,000.00 100,000.00 1009.3 MONITORING, TREATMENT AND DISPOSAL ASBESTOS FILL $ 1. 75,000.00 75,000.00 1009.31 MONITORING, TREATMENT AND DISPOSAL ASBESTOS FILL $ 1. 15,000.00 15,000.00 1009.4 BUILDING ASBESTOS ABATEMENT $ 1. 15,000.00 15,000.00 1009.5 DISPOSAL FUEL SLUDGE $ 1. 10,000.00 10,000.00 1009.7 PROJECT OPERATIONS PLAN $ 1. 30,000.00 30,000.00 1010.11 FUEL ADJUSTMENT, DIESEL $ 1. 55,000.00 55,000.00 1010.12 FUEL ADJUSTMENT, GASOLINE $ 1. 55,000.00 55,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 55,000.00 55,000.00 1010.41 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR CONCRETE $ 1. 40,000.00 40,000.00 1010.42 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR CONCRETE $ 1. 60,000.00 60,000.00 1010.43 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR CONCRETE $ 1. 1,500.00 1,500.00 $34,343,677.61