THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: NASHUA-MERRIMACK X-A000(230), 14189 COUNTIES AND CODES: HILLSBOROUGH 011 DATE BIDS OPEN: AUGUST 19, 2004 SCOPE OF WORK: PAVEMENT REHABILITATION AND SAFETY WORK LOCATION: HENRI BURQUE HIGHWAY IN NASHUA AND GREELEY STREET IN MERRIMACK COMPLETION DATE: JULY 29, 2005 A PIKE INDUSTRIES INC. 3 EASTGATE PARK RD., BELMONT, NH 03220 $ 3,471,768.90 B CONTINENTAL PAVING INC. ONE CONTINENTAL DR., LONDONDERRY, NH 03053 $ 3,498,109.00 C ROADS CORPORATION 241 TREBLE COVE RD., N. BILLERICA, MA 01862 $ 4,189,345.00 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 202.7 REMOVAL OF GUARDRAIL (F) LF 1,326. 1.40 1,856.40 1.50 1,989.00 2.50 3,315.00 203.1 COMMON EXCAVATION CY 8,000. 8.00 64,000.00 8.00 64,000.00 14.00 112,000.00 203.2 ROCK EXCAVATION CY 1,550. 15.00 23,250.00 15.00 23,250.00 45.00 69,750.00 203.5540 GUARDRAIL TAPERED RAIL PLATFORM LF 50. 12.00 600.00 12.00 600.00 90.00 4,500.00 203.5552 GUARDRAIL ELT PLATFORMS U 11. 800.00 8,800.00 1,200.00 13,200.00 1,450.00 15,950.00 206.19 COMMON STRUCTURE EXCAVATION EXPLORATORY CY 75. 50.00 3,750.00 25.00 1,875.00 45.00 3,375.00 209.1 GRANULAR BACKFILL CY 550. 24.00 13,200.00 20.00 11,000.00 30.00 16,500.00 304.201 GRAVEL CY 4,300. 20.00 86,000.00 14.00 60,200.00 36.00 154,800.00 304.301 CRUSHED GRAVEL CY 2,150. 21.00 45,150.00 18.00 38,700.00 27.00 58,050.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING TON 600. 20.00 12,000.00 20.00 12,000.00 27.00 16,200.00 304.35 CRUSHED GRAVEL FOR DRIVES CY 25. 48.00 1,200.00 25.00 625.00 33.00 825.00 403.11052 HOT BITUMINOUS PAVEMENT MACHINE METHOD (SUPERPAVE) (QC/QA) TON 37,500. 38.00 1,425,000.00 38.00 1,425,000.00 34.00 1,275,000.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD TON 3,100. 73.00 226,300.00 75.00 232,500.00 90.00 279,000.00 403.98 HOT BITUMINOUS CONCRETE LEVELING, MACHINE METHOD TON 1,000. 38.00 38,000.00 38.00 38,000.00 41.50 41,500.00 417.01 COLD PLANING BITUMINOUS SURFACES SY 140,000. 1.00 140,000.00 1.40 196,000.00 2.00 280,000.00 603.83212 12" PLASTIC PIPE (SMOOTH INTERIOR) LF 450. 17.00 7,650.00 22.00 9,900.00 34.00 15,300.00 604.0007 POLYETHYLENE LINER EA 210. 200.00 42,000.00 150.00 31,500.00 130.00 27,300.00 604.12 CATCH BASINS TYPE B U 5. 1,290.00 6,450.00 1,500.00 7,500.00 1,250.00 6,250.00 604.4 RECONSTRUCTING CATCH BASINS & DROP INLETS LF 25. 190.00 4,750.00 300.00 7,500.00 325.00 8,125.00 14189 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 604.45 ADJUSTING CATCH BASIN DROP INLET GRATE AND FRAMES EA 195. 180.00 35,100.00 250.00 48,750.00 125.00 24,375.00 604.55 ADJUSTING MANHOLE COVERS AND FRAMES EA 35. 210.00 7,350.00 300.00 10,500.00 125.00 4,375.00 604.6 MANHOLE COVERS & FRAMES EA 10. 420.00 4,200.00 400.00 4,000.00 375.00 3,750.00 604.72 GRATES & FRAMES, TYPE B EA 20. 400.00 8,000.00 350.00 7,000.00 375.00 7,500.00 605.512 12" PERF. CORR. POLYETHLY PIPE UND. LF 600. 27.00 16,200.00 16.00 9,600.00 34.00 20,400.00 606.000 STEEL BEAM FOR BEAM GUARDRAIL LF 100. 8.00 800.00 7.00 700.00 19.50 1,950.00 606.014 6"X8" WOOD POST REPLACE- MENTS FOR BEAM GUARDRAIL POSTS EA 10. 50.00 500.00 50.00 500.00 145.00 1,450.00 606.0142 6"X8" WOOD POST ASSEMBLIES FOR BEAM GUARDRAIL POSTS EA 10. 10.00 100.00 10.00 100.00 19.00 190.00 606.140 BEAM GUARDRAIL (STANDARD SECTION- WOOD POSTS) LF 1,000. 25.00 25,000.00 17.00 17,000.00 14.50 14,500.00 606.1452 BEAM GUARDRAIL (TERMINAL UNIT TYPE ELT) U 11. 1,750.00 19,250.00 1,750.00 19,250.00 2,400.00 26,400.00 608.1201 2" BITUMINOUS SIDEWALK SY 2,750. 8.80 24,200.00 12.00 33,000.00 8.40 23,100.00 608.2401 4" CONCRETE SIDEWALK SY 90. 30.00 2,700.00 30.00 2,700.00 33.00 2,970.00 608.2601 6" CONCRETE SIDEWALK SY 3,000. 30.00 90,000.00 32.00 96,000.00 34.00 102,000.00 608.53 DETECTABLE WARNING PANELS YELLOW (SIDEWALK RAMPS) SY 25. 50.00 1,250.00 550.00 13,750.00 35.00 875.00 609.01 STRAIGHT GRANITE CURB LF 5,050. 13.70 69,185.00 14.00 70,700.00 19.50 98,475.00 609.5 RESET GRANITE CURB LF 11,500. 5.50 63,250.00 5.50 63,250.00 6.00 69,000.00 609.811 BITUMINOUS CURB, TYPE B (4" REVEAL) LF 900. 4.00 3,600.00 3.00 2,700.00 6.00 5,400.00 611.90001 ADJUSTING WATER GATES AND SHUTOFFS SET BY OTHERS EA 50. 75.00 3,750.00 150.00 7,500.00 75.00 3,750.00 614.511 CONCRETE PULL BOX 14" EA 6. 300.00 1,800.00 300.00 1,800.00 350.00 2,100.00 614.7314 3" PVC PLASTIC CONDUIT, SCHEDULE 40 LF 75. 10.00 750.00 10.00 750.00 18.00 1,350.00 614.7318 3" PVC PLASTIC CONDUIT, SCHEDULE 80 LF 150. 12.50 1,875.00 12.50 1,875.00 19.50 2,925.00 614.7328 3" 2-DUCT PVC PLASTIC CONDUIT, SCHEDULE 80 LF 250. 15.00 3,750.00 15.00 3,750.00 37.00 9,250.00 615.024 RELOCATING TRAFFIC SIGN, TYPE B U 1. 1,750.00 1,750.00 1,750.00 1,750.00 10,500.00 10,500.00 615.034 RELOCATING TRAFFIC SIGN, TYPE C U 13. 175.00 2,275.00 175.00 2,275.00 700.00 9,100.00 616.191 ALTERATIONS TO TRAFFIC SIGNALS U 1. 21,700.00 21,700.00 21,680.00 21,680.00 52,000.00 52,000.00 616.192 ALTERATIONS TO TRAFFIC SIGNALS U 1. 9,250.00 9,250.00 9,250.00 9,250.00 52,000.00 52,000.00 616.193 ALTERATIONS TO TRAFFIC SIGNALS U 1. 10,500.00 10,500.00 10,350.00 10,350.00 52,000.00 52,000.00 616.194 ALTERATIONS TO TRAFFIC SIGNALS U 1. 4,600.00 4,600.00 4,620.00 4,620.00 52,000.00 52,000.00 14189 PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 616.195 ALTERATIONS TO TRAFFIC SIGNAL U 1. 11,000.00 11,000.00 10,800.00 10,800.00 52,000.00 52,000.00 616.196 ALTERATIONS TO TRAFFIC SIGNALS U 1. 10,000.00 10,000.00 9,500.00 9,500.00 52,000.00 52,000.00 616.197 ALTERATIONS TO TRAFFIC SIGNALS U 1. 3,500.00 3,500.00 3,800.00 3,800.00 52,000.00 52,000.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 120,000.00 120,000.00 120,000.00 120,000.00 120,000.00 120,000.00 618.7 FLAGGERS HR 6,000. 19.00 114,000.00 20.00 120,000.00 15.00 90,000.00 619.1 MAINTENANCE OF TRAFFIC U 1. 148,000.00 148,000.00 100,000.00 100,000.00 150,400.00 150,400.00 619.25 PORTABLE CHANGEABLE MESSAGE SIGN U 2. 6,000.00 12,000.00 10,000.00 20,000.00 13,500.00 27,000.00 619.253 PORTABLE CHANGEABLE MESSAGE SIGN (UNIT WEEK) UWK 12. 300.00 3,600.00 300.00 3,600.00 750.00 9,000.00 621.2 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR EA 30. 5.00 150.00 5.00 150.00 4.00 120.00 621.31 SINGLE DELINEATOR WITH POST EA 200. 25.00 5,000.00 28.00 5,600.00 28.50 5,700.00 628.2 SAWED BITUMINOUS PAVEMENT LF 1,750. 2.00 3,500.00 1.00 1,750.00 1.25 2,187.50 632.0104 RETROREFLECTIVE PAINT PAVE. MARKING, 4" LINE LF 500,000. .12 60,000.00 .09 45,000.00 .10 50,000.00 632.0108 RETROREFLECTIVE PAINT PAVE. MARKING, 8" LINE LF 2,850. .20 570.00 .35 997.50 .25 712.50 632.0118 RETROREFLECTIVE PAINT PAVE. MARKING, 18" LINE LF 775. 1.80 1,395.00 1.15 891.25 .50 387.50 632.02 RETROREFLECTIVE PAINT PAVEMENT MARKING, SYMBOL OR WORD SF 1,700. 1.50 2,550.00 1.35 2,295.00 2.75 4,675.00 632.3106 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 6" LINE LF 400. 1.00 400.00 .75 300.00 .55 220.00 632.3118 RETROREFLECT. THERMOPLAS. PAVE. MARKING, 18" LINE LF 775. 2.50 1,937.50 2.15 1,666.25 1.60 1,240.00 632.32 RETROREFLECT. THERMOPLAS. PAVEMENT MARKING, SYMBOL OR WORD SF 1,700. 6.00 10,200.00 3.35 5,695.00 3.20 5,440.00 641. LOAM CY 750. 37.00 27,750.00 20.00 15,000.00 23.00 17,250.00 645.3 EROSION STONE TON 250. 34.00 8,500.00 25.00 6,250.00 38.00 9,500.00 645.531 SILT FENCE LF 250. 2.00 500.00 3.00 750.00 4.00 1,000.00 645.7 EROSION AND SEDIMENT CONTROL STORMWATER MANAGEMENT PLAN U 1. 4,000.00 4,000.00 3,000.00 3,000.00 8,250.00 8,250.00 645.71 MONITORING EROSION AND SEDIMENT CONTROL HR 100. 90.00 9,000.00 100.00 10,000.00 95.00 9,500.00 646.3 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS A 3.25 1,500.00 4,875.00 1,500.00 4,875.00 3,750.00 12,187.50 647.1 HUMUS CY 750. 20.00 15,000.00 15.00 11,250.00 19.00 14,250.00 692. MOBILIZATION U 1. 100,000.00 100,000.00 144,000.00 144,000.00 246,000.00 246,000.00 698.13 FIELD OFFICE TYPE C MON 12. 1,600.00 19,200.00 1,500.00 18,000.00 1,200.00 14,400.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 14189 PAGE 4 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 1008.21 ALTERATION AND ADDITIONS AS NEEDED- REPAIR TO SPRINKLER SYSTEM $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1008.3 ALTERATIONS AND ADDITIONS AS NEEDED - TEMPORARY DRAINAGE $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1010.11 FUEL ADJUSTMENT, DIESEL $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1010.12 FUEL ADJUSTMENT, GASOLINE $ 1. 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 1010.3 QUALITY CONTROL QUALITY ASSURANCE (QC/QA ASPHALT $ 1. 82,500.00 82,500.00 82,500.00 82,500.00 82,500.00 82,500.00 $3,471,768.90 $3,498,109.00 $4,189,345.00