THE STATE OF NEW HAMPSHIRE PAGE 1 DEPARTMENT OF TRANSPORTATION PROJECT: HAMPSTEAD 13462 COUNTIES AND CODES: ROCKINGHAM 015 DATE BIDS OPEN: JULY 22, 2004 SCOPE OF WORK: ROADWAY REHABILITATION LOCATION: NH 111 AND EAST ROAD COMPLETION DATE: MAY 20, 2005 A BUSBY CONSTRUCTION CO., INC. 9 POND LANE, ATKINSON, NH 03811 $ 685,000.00 B N. PANDELENA CONSTRUCTION CO., INC, 6 STARWOOD DR. HAMPSTEAD, NH 03841 $ 789,981.95 C NORTH EAST EARTH MECHANICS INC. 159 BARNSTEAD ROAD, PITTSFIELD, NH 03263 $ 793,869.70 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 201.1 CLEARING AND GRUBBING (F) HA .17 40,000.00 6,800.00 15,000.00 2,550.00 37,000.00 6,290.00 201.21 REMOVING SMALL TREES EA 2. 100.00 200.00 200.00 400.00 350.00 700.00 201.7 SELECTIVE CLEARING AND THINNING (F) HA .02 30,000.00 600.00 25,000.00 500.00 28,500.00 570.00 202.41 REMOVAL OF EXISTING PIPE 0-600 MM DIA. LM 176. 10.00 1,760.00 11.50 2,024.00 33.00 5,808.00 202.7 REMOVAL OF GUARDRAIL (F) LM 415. 5.91 2,452.65 6.50 2,697.50 7.00 2,905.00 202.85 REMOVAL OF FLASHING BEACON U 1. 1,417.50 1,417.50 1,500.00 1,500.00 1,150.00 1,150.00 203.1 COMMON EXCAVATION M3 3,550. 7.00 24,850.00 8.00 28,400.00 9.00 31,950.00 203.2 ROCK EXCAVATION M3 800. 47.50 38,000.00 54.00 43,200.00 52.00 41,600.00 203.6 EMBANKMENT-IN-PLACE (F) M3 1,392. 4.50 6,264.00 3.15 4,384.80 4.50 6,264.00 206.2 ROCK STRUCTURE EXCAVATION M3 160. 100.00 16,000.00 115.00 18,400.00 92.00 14,720.00 211.11 VIBRATION MONITORING SERVICES HR 40. 50.00 2,000.00 60.00 2,400.00 60.00 2,400.00 214. FINE GRADING U 1. 10,000.00 10,000.00 15,000.00 15,000.00 7,500.00 7,500.00 304.1 SAND (F) M3 226. 14.00 3,164.00 15.50 3,503.00 25.50 5,763.00 304.2 GRAVEL (F) M3 1,157. 20.00 23,140.00 16.50 19,090.50 26.00 30,082.00 304.3 CRUSHED GRAVEL (F) M3 1,290. 21.50 27,735.00 28.50 36,765.00 29.00 37,410.00 304.31 CRUSHED GRAVEL FOR SHIMMING M3 110. 21.50 2,365.00 30.00 3,300.00 31.00 3,410.00 304.32 CRUSHED GRAVEL FOR SHOULDER LEVELING T 105. 24.00 2,520.00 30.00 3,150.00 29.00 3,045.00 304.35 CRUSHED GRAVEL FOR DRIVES M3 35. 33.00 1,155.00 30.00 1,050.00 31.00 1,085.00 403.11 HOT BITUMINOUS PAVEMENT, MACHINE METHOD T 185. 46.00 8,510.00 50.00 9,250.00 62.00 11,470.00 403.11002 HOT BITUMINOUS PAVEMENT, MACHINE METHOD (QC/QA) T 2,000. 46.00 92,000.00 49.00 98,000.00 48.00 96,000.00 403.12 HOT BITUMINOUS PAVEMENT, HAND METHOD T 25. 115.00 2,875.00 105.00 2,625.00 96.00 2,400.00 13462 PAGE 2 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 411.1 HOT BITUMINOUS CONCRETE LEVELING COURSE T 100. 63.00 6,300.00 67.00 6,700.00 62.00 6,200.00 417. COLD PLANING BITUMINOUS SURFACES (F) M2 1,282. 5.10 6,538.20 6.70 8,589.40 6.60 8,461.20 520.1 CONCRETE CLASS A M3 10. 520.00 5,200.00 200.00 2,000.00 590.00 5,900.00 544.1 REINFORCING STEEL (ROADWAY) KG 56. 2.00 112.00 6.50 364.00 3.00 168.00 585.3 STONE FILL, CLASS C M3 11. 36.50 401.50 40.00 440.00 59.00 649.00 603.00204 375 MM R.C. PIPE, CLASS III LM 42. 118.00 4,956.00 80.00 3,360.00 141.00 5,922.00 603.00205 450 MM R.C. PIPE, CLASS III LM 13. 130.00 1,690.00 130.00 1,690.00 151.00 1,963.00 605.79 UNDERDRAIN FLUSHING BASINS EA 5. 250.00 1,250.00 300.00 1,500.00 250.00 1,250.00 605.915 150 MM PIPE UND.(CONTRACT ORS OPTION) LM 420. 40.00 16,800.00 38.00 15,960.00 49.00 20,580.00 606.140 BEAM GUARDRAIL (STANDARD SECTION- WOOD POSTS) LM 530. 53.22 28,206.60 55.50 29,415.00 52.00 27,560.00 606.1452 BEAM GUARDRAIL (TERMINAL UNIT TYPE ELT) U 4. 1,768.00 7,072.00 1,950.00 7,800.00 1,900.00 7,600.00 607.9 RESETTING RAILING AND FENCING LM 50. 39.38 1,969.00 43.00 2,150.00 41.00 2,050.00 609.01 STRAIGHT GRANITE CURB LM 150. 62.50 9,375.00 72.25 10,837.50 60.00 9,000.00 609.02 CURVED GRANITE CURB LM 30. 92.00 2,760.00 102.50 3,075.00 93.00 2,790.00 614.3081 75 MM STEEL CONDUIT LM 35. 61.00 2,135.00 64.00 2,240.00 22.00 770.00 614.511 CONCRETE PULL BOX 350 MM EA 4. 337.00 1,348.00 352.00 1,408.00 265.00 1,060.00 614.522 MOLDED PULL BOX 325 MM X 600 MM EA 4. 339.00 1,356.00 339.00 1,356.00 270.00 1,080.00 614.70814 75 MM PVC PLASTIC CONDUIT SCHEDULE 40 LM 185. 23.30 4,310.50 23.30 4,310.50 23.00 4,255.00 614.70818 75 MM PVC PLASTIC CONDUIT SCHEDULE 80 LM 110. 62.25 6,847.50 65.25 7,177.50 40.00 4,400.00 614.70828 75 MM 2-DUCT PVC PLASTIC CONDUIT, SCHEDULE 80 LM 100. 69.40 6,940.00 72.70 7,270.00 46.00 4,600.00 615.003 REMOVING TRAFFIC SIGN U 7. 15.00 105.00 20.00 140.00 16.00 112.00 615.004 RELOCATING TRAFFIC SIGN U 12. 100.00 1,200.00 100.00 1,200.00 110.00 1,320.00 615.022 TRAFFIC SIGN TYPE B, BREAKAWAY MOUNTS (F) M2 2.7 1,100.00 2,970.00 1,250.00 3,375.00 1,200.00 3,240.00 615.03 TRAFFIC SIGN TYPE C (F) M2 8.01 530.00 4,245.30 550.00 4,405.50 550.00 4,405.50 616.101 TRAFFIC SIGNALS U 1. 64,932.00 64,932.00 70,000.00 70,000.00 70,000.00 70,000.00 618.61 UNIFORMED OFFICERS WITH VEHICLE $ 1. 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 50,000.00 618.7 FLAGGERS HR 1,200. 14.00 16,800.00 16.50 19,800.00 26.00 31,200.00 619.1 MAINTENANCE OF TRAFFIC U 1. 9,850.00 9,850.00 25,000.00 25,000.00 30,000.00 30,000.00 619.253 PORTABLE CHANGEABLE MESSAGE SIGN (UNIT WEEK) UWK 32. 300.00 9,600.00 975.00 31,200.00 400.00 12,800.00 621.21 RETROREFLECTIVE BEAM GUARDRAIL DELINEATOR (WHITE) EA 20. 5.00 100.00 5.00 100.00 6.00 120.00 621.31 SINGLE DELINEATOR WITH POST EA 20. 29.00 580.00 30.00 600.00 30.00 600.00 13462 PAGE 3 ------------------------------------------------------------------------------------------------------------------------------------ ITEM A B C NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL ------------------------------------------------------------------------------------------------------------------------------------ 622.1 STEEL WITNESS MARKERS EA 5. 22.00 110.00 50.00 250.00 26.00 130.00 628.2 SAWED BITUMINOUS PAVEMENT LM 1,300. 6.56 8,528.00 5.00 6,500.00 8.00 10,400.00 632.0110 RETROREFLECTIVE PAINT PAVEMENT MARKING, 100 MM LINE LM 7,000. .62 4,340.00 .60 4,200.00 .60 4,200.00 632.0145 RETROREFLECTIVE PAINT PAVEMENT MARKING, 450 MM LINE LM 55. 5.25 288.75 6.00 330.00 5.00 275.00 632.3145 RETROREFLECT. THERMOPLAS. PAVE. MARKING 450 MM LIN LM 55. 12.00 660.00 15.00 825.00 17.00 935.00 632.32 RETROREFLECT. THERMOPLAS. PAVEMENT MARKING, SYMBOL OR WORD M2 22. 62.00 1,364.00 50.00 1,100.00 46.00 1,012.00 641. LOAM M3 100. 25.00 2,500.00 26.00 2,600.00 20.00 2,000.00 645.21 SLOPE STABILIZATION (2:1 OR FLATTER) M2 7,900. 1.60 12,640.00 1.90 15,010.00 1.50 11,850.00 645.3 EROSION STONE T 50. 28.00 1,400.00 30.00 1,500.00 23.00 1,150.00 645.51 HAY BALES FOR TEMPORARY EROSION CONTROL EA 250. 6.00 1,500.00 6.00 1,500.00 6.00 1,500.00 645.531 SILT FENCE LM 720. 9.00 6,480.00 14.00 10,080.00 10.00 7,200.00 645.7 EROSION AND SEDIMENT CONTROL STORMWATER MANAGEMENT PLAN U 1. 2,450.00 2,450.00 28,500.00 28,500.00 2,500.00 2,500.00 645.71 MONITORING EROSION AND SEDIMENT CONTROL HR 60. 85.00 5,100.00 120.00 7,200.00 85.00 5,100.00 646.31 TURF ESTABLISHMENT WITH MULCH AND TACKIFIERS M2 7,900. .40 3,160.00 .55 4,345.00 1.00 7,900.00 647.1 HUMUS M3 675. 15.50 10,462.50 10.50 7,087.50 14.50 9,787.50 670.066 MAILBOX SUPPORT ASSEMBLIES EA 3. 200.00 600.00 200.00 600.00 200.00 600.00 670.95 TEMPORARY SAFETY FENCE LM 85. 10.00 850.00 8.25 701.25 6.50 552.50 692. MOBILIZATION U 1. 41,209.00 41,209.00 30,000.00 30,000.00 60,000.00 60,000.00 698.13 FIELD OFFICE TYPE C MON 8. 1,200.00 9,600.00 3,000.00 24,000.00 1,525.00 12,200.00 699. MISCELLANEOUS TEMPORARY EROSION AND SEDIMENT CONTROL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1007. MISCELLANEOUS LANDSCAPE TREATMENT $ 1. 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00 1010.11 FUEL ADJUSTMENT, DIESEL $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1010.12 FUEL ADJUSTMENT, GASOLINE $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 1010.2 ASPHALT CEMENT ADJUSTMENT $ 1. 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00 1010.3 QUALITY CONTROL QUALITY ASSURANCE (QC/QA FOR ASPHALT $ 1. 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 $685,000.00 $789,981.95 $793,869.70