NH 107 Traffic Shift and Temporary Signals in Seabrook
Rehabilitation/Widening of Route 107 Bridge Over I-95

The New Hampshire Department of Transportation (NHDOT) announces the planned placement of temporary traffic signals on NH Route 107 and the I-95 southbound off-ramp, and a change in traffic pattern on NH 107 from US Route 1 to Batchelder Road in Seabrook, New Hampshire.

This night work will take place between 7:00 pm on Thursday, June 27, and 6:00 am on Friday, June 28, 2013.

This new traffic pattern will be in effect during the next construction phase of the project that is rehabilitating and widening the NH 107 bridge over I-95. The temporary traffic signals at the I-95 Exit 1 southbound off ramp will eventually become permanent once all work is completed along Route 107 between US 1 and Batchelder Road. The estimated completion date of the project is June 2014.

Crews will also be on Interstate 95 Wednesday night (June 26) and Thursday morning, between the hours of 8:00 pm and 5:00 am, to work on the Route 107 overpass. Lane closures will be in effect throughout the evening at various times and intervals.

Motorists are reminded to be alert and drive safely through this construction work zone.

R.S. Audley, Inc. of Bow, New Hampshire is the general contractor for the $6.4 million project.