NEWS RELEASE
| For Immediate Release July 29, 2010 |
Contacts: Lee Simpson Construction Bureau (603) 231-1101 Bill Boynton Public Information Office (603) 271-6495 |
| Night Paving Work Planned on NH Route 111 in Hampstead
Four Miles From West Road to Danville Road The New Hampshire Department of Transportation announces night work is scheduled to begin on a four-mile section of NH Route 111 in Hampstead, from the intersection of West Road to Danville Road. Weather permitting, the five nights of work will get underway on Sunday August 1, 2010 for milling and paving operations. Alternating one-way traffic will be used to keep any traffic moving through the work zone between the hours of 7:00 PM and 6:00 AM. Motorists and motorcycles should be prepared for lane closures and possible rough surfaces during both day and nighttime hours. Brox Industries Inc. of Dracut, Mass. is the contractor for the $1.2 million project, which has a completion date of October 8, 2010. |
|