NEWS RELEASE
| For Immediate Release June 18, 2010 |
Contacts: Steve Glines Construction Bureau (603) 271-2571 Bill Boynton Public Information Office (603) 271-6495 |
| Three Bridge Repair Projects On NH Route 175 In Woodstock
Will Require Single Lane Traffic Controlled By Signals The New Hampshire Department of Transportation announces bridge repairs are scheduled to begin Wednesday, June 23, 2010 on three bridges on NH Route 175 in Woodstock between Thornton Gore Road and Tripoli Road. Two of the bridges cross the Pemigewasset River and one crosses the Pemigewasset River Overflow. All three bridges are within a half-mile of each other. This bridge deck work will require alternating one-way traffic controlled by temporary signals. These traffic restrictions are expected to be in place until November 1, 2010. Beck & Bellucci, of Franklin, New Hampshire is the general contractor for the $1 million project. |
|